1.1 Background
2 ENVIRONMENTAL MONITORING AND AUDIT
3 IMPLEMENTATION STATUS ON THE ENVIRONMENTAL PROTECTION REQUIREMENTS
Table 1.1 Summary of Awarded Works Contracts
Table 2.1 Summary of Works Contracts and Respective EPs
Table 2.2 Summary of Major Construction Activities in the Reporting Period
Table 2.3 Summary of TSP Monitoring Results in the Reporting Period
Table 2.4 Summary of Construction Noise Monitoring Results in the Reporting Period
Table 2.5 Log for Environmental Complaints, Notification of Summons and Successful Prosecutions for the Reporting Month
Table 3.1 Summary of Status of Required Submissions for EP-438/2012/L
1.1.1 The Shatin to Central Link (SCL) is a 17km extension of the existing Ma On Shan Line (MOL) and East Rail Line (EAL) comprising (i) The East-West Corridor which extends the MOL from Tai Wai to Hung Hom via East Kowloon to connect with the West Rail Line (WRL) at Hung Hom Station (HUH) and Stabling Sidings at Hung Hom Freight Yard (HHS); and (ii) The North-South Corridor which is an extension of the East Rail Line (EAL) at Hung Hom across the harbour to Admiralty Station (ADM).
1.1.2 Shatin to Central Link – Tai Wai to Hung Hom Section [SCL (TAW-HUH)] (hereafter referred to as “the Project”) are parts of the SCL. Shatin to Central Link – Stabling Sidings at Hung Hom Freight Yard [SCL (HHS)] is a proposed stabling sidings option for SCL (TAW – HUH) at the former freight yard in Hung Hom.
1.1.3 The Environmental Impact Assessment (EIA) Reports for SCL (TAW-HUH) (Register No.: AEIAR-167/2012) and SCL (HHS) (Register No.: AEIAR-164/2012) were approved on 17 February 2012 under the Environmental Impact Assessment Ordinance (EIAO). Following the approval of the EIA Reports, the Environmental Permit (EP) was granted on 22 March 2012 - SCL (TAW-HUH) and SCL (HHS) (EP No: EP-438/2012), for the
construction and operation. Variations of environmental permit (VEP) were subsequently applied for EP-438/2012. The latest Environmental Permits (EP No. EP-438/2012/L) was issued by Director of Environmental Protection (DEP) on 14 August 2024.
1.2.1 Thirteen civil construction works contracts of the Project have been awarded since July 2012. The construction of the Project commenced in September 2012. Table 1.1 summarises the information of the awarded Works Contracts. All major construction works under eleven out of thirteen civil construction works contracts have been completed.
Works Contract |
Description |
Construction Start Date |
Contractor |
Environmental Team |
1101(1) |
Ma On Shan Line Modification Works |
December 2012 |
Sun Fook Kong Joint Venture (SFKJV) |
ANewR Consulting Ltd. (ANewR) |
1102(6) |
Hin Keng Station and Approach Structures |
October 2013 |
Penta-Ocean Construction Co. Ltd. |
Wellab Limited (Wellab) |
1103(7) |
Hin Keng to Diamond Hill Tunnels |
February 2013 |
Vinci Construction Grands Projets |
Ove Arup & Partners Hong Kong Ltd. (Arup) |
October 2019 |
Wing Ho Yuen Landscaping Co. Ltd. |
MTR Co. Limited |
||
1106(8) |
Diamond Hill Station |
March 2013 |
Leader Joint Venture |
Cinotech Consultants Ltd. (Cinotech) |
1107(4) |
Diamond Hill to Kai Tak Tunnels |
May 2013 |
Chun Wo - SELI Joint Venture |
Cinotech Consultants Ltd. (Cinotech) |
1108(5) |
Kai Tak Station and Associated Tunnels |
June 2013 |
Kaden -Chun Wo Joint
Venture |
Environmental Pioneers & Solutions Ltd. |
Works Contract |
Description |
Construction Start Date |
Contractor |
Environmental Team |
1108A(2) |
Kai Tak Barging Point Facilities |
September 2012 |
Concentric – Hong Kong River Joint Venture (CCL- HKR JV) |
Cinotech Consultants Ltd. (Cinotech) |
1109(10) |
Stations and Tunnels of Kowloon City Section |
September 2012 |
Samsung-Hsin Chong JV (SSHCJV) |
ERM-Hong Kong Limited (ERM) |
1111(9) |
Hung Hom North Approach Tunnels |
January 2013 |
Gammon-Kaden SCL1111 JV |
AECOM Asia Co. Ltd. |
1112(11) |
Hung Hom Station and Stabling Sidings |
June 2013 |
Leighton Contractors (Asia) Limited |
SMEC Asia Ltd., HK |
11240(3) |
Excavation, Sorting and Disposal of Stockpiled Spoils to Approved Receptor Site |
October 2017 |
Crown Asia Engineering Limited (CAEL) |
MTR Corporation Limited |
11286 |
Pedestrian Link Connecting Pak Tai Street and Sung Wong Toi Station |
July 2023 |
Paul Y. Construction Co., Ltd. |
ERM-Hong Kong Limited (ERM) |
11234 |
Re-provisioning of Ma Chai Hang Recreation Ground |
March 2024 |
Build King Civil Engineering Ltd. |
Fugro Technical Services Ltd. |
Notes:
(1) All construction works (works areas at Tai Wai Mei Tin Road and the offsite temporary storage areas) under Works Contract 1101 were completed on 29 February 2016.
(2) All construction works (Kai Tak Barging Point Facilities) under Works Contract 1108A were completed on 29 September 2016.
(3) All construction works (Excavation, Sorting and Disposal of Stockpiled Spoils to Approved Receptor Site) under Works Contract 11240 were completed on 3 January 2018.
(4) All construction works (Diamond Hill to Kai Tak Tunnels) under Works Contract 1107 were completed on 22 February 2018.
(5) All construction works (Kai Tak Station and associated tunnels) under Works Contract 1108 were completed in July 2018.
(6) All construction works (Hin Keng Station and Approach Structures) under Works Contract 1102 were completed in December 2018. The Environmental Team was taken over by Wellab Limited starting from 1 January 2019.
(7) All construction works (Hin Keng to Diamond Hill Tunnels) under Works Contract 1103 were completed in June 2019. Minor landscaping works at Fung Tak had been commenced in mid- October and all the works were completed at the end of October 2019.
(8) All construction works (Diamond Hill Station) under Works Contract 1106 with significant environmental impacts were substantially completed by 25 June 2019.
(9) All major construction works (Hung Hom North Approach Tunnels) under Works Contract 1111 have been substantially completed since 18 November 2018.
(10) All construction works (Stations and Tunnels of Kowloon City Section) under Works Contract 1109 have been substantially completed on 12 August 2020.
(11) All major construction works (Hung Hom Station and Stabling Sidings) under Works Contract 1112 have been substantially completed by 17 September 2020.
1.2.2 All major construction works for SCL (TAW-HUH) and SCL (HHS) which were covered by EP No. EP-438/2012/L had been completed. The remaining works, including (1) the re-provision of recreational facilities at Ma Chai Hang and (2) a pedestrian link connecting Sung Wong Toi Station to Pak Tai Street, have been carried out by other works contracts in 2023 -2024 resulting in the liaison with Railway Development Office (RDO), relevant government departments and stakeholders. Apart from the above, the remaining tree planting works at Kai Tak Station Square (Phase 2) which have been scheduled after the full opening of SCL were completed.
1.3.1 The Environmental Monitoring and Audit (EM&A) programme for the Project commenced in September 2012. This is the one hundred and twentieth EM&A Report for the Project which summarises the EM&A works undertaken during the period from 1 to 28 February 2025.
2.1.1 The construction of SCL has been divided into different civil construction works contracts which are covered by the Environmental Permit (EP-438/2012/L). As per the EP Conditions, Monthly EM&A Reports and Final EM&A Review Report for Works Contracts as shown in the table below except 11286 and 11234 have been prepared by the corresponding Contractor’s ETs.
Works Contract |
Contract Title |
Works Covered in Environmental Permit No. |
1101 |
Ma On Shan Modification Works |
EP-438/2012/L |
1102 |
Hin Keng Station and Approach Structures |
EP-438/2012/L |
1103 |
Hin Keng to Diamond Hill Tunnels |
EP-438/2012/L |
1106 |
Diamond Hill Station |
EP-438/2012/L |
1107 |
Diamond Hill to Kai Tak Tunnels |
EP-438/2012/L |
1108 |
Kai Tak Station and Associated Tunnels |
EP-438/2012/L |
1108A |
Kai Tak Barging Point Facilities |
EP-438/2012/L |
1109 |
Stations and Tunnels of Kowloon City Section |
EP-438/2012/L |
1111 |
Hung Hom North Approach Tunnels |
EP-438/2012/L |
1112 |
Hung Hom Station and Stabling Sidings |
EP-438/2012/L |
11240 |
Excavation, Sorting and Disposal of Stockpiled Spoils to Approved Receptor Site |
EP-438/2012/L |
11286 |
Pedestrian Link Connecting Pak Tai Street and Sung Wong Toi Station |
EP-438/2012/L |
11234 |
Re-provisioning of Ma Chai Hang Recreation Ground |
EP-438/2012/L |
2.1.2 The EM&A Reports for Works Contract Nos. 11286 (a pedestrian link connecting Sung Wong Toi Station to Pak Tai Street) and 11234 (the re-provision of recreational facilities at Ma Chai Hang) prepared by the respective Contractor’s ETs are provided in Appendix A and Appendix B respectively. The EM&A Report provide details of the project information, EM&A requirements, impact monitoring and audit results for the corresponding Contracts.
2.1.3 A summary of the major construction activities undertaken by the respective Contractors of various Works Contracts during the reporting period are presented in Table 2.2.
Works Contract |
Site |
Construction Activities |
11286 |
Works in Sung Wong Toi (SUW) (formerly named as To Kwa Wan (TKW)) |
Near Sung Wong Toi Exit D (W1) • ELS • On-site fabrication of Footbridge • Pier construction works
Near Pak Tai Street (H2) • Pumping Test • Grout curtain works • ELS |
11234 |
Re-provisioning of Ma Chai Hang Recreation Ground |
• Site Clearance • Installation of mesh for football pitch fence • Laying of artificial turfing system • Testing and Commissioning for football pitch • Hard & Soft landscaping |
2.1.4 Impact monitoring for air quality and construction noise were conducted in accordance with the EM&A Manual in the reporting period under Works Contract 11286. Continuous noise monitoring was not required in the reporting period for the Works Contracts according to the Continuous Noise Monitoring Plan (CNMP). The air quality and construction noise for this reporting period are summarised in Tables 2.3 and 2.4. Details of the monitoring requirements, locations, equipment, methodology and QA/QC procedures are presented in the EM&A Reports as provided in Appendices A.
2.1.5 No environmental complaint; no exceedance of action and limit levels; and no notification of summons or successful prosecutions was received during this reporting period. Log for environmental complaints, notification of summons and successful prosecutions are provided in Table 2.5.
2.1.6 Regular site inspections were conducted by the respective ETs (both Works Contract Nos. 11286 and 11234) on a weekly basis to check the implementation of environmental pollution control and mitigation measures for the Project. No non-conformance was identified in the reporting period.
Monitoring Station ID |
Location |
TSP Concentration (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
Exceedance due to the Project Construction (Yes/ No/ N/A) |
Works Contracts 1102 and 1103 |
|||||
DMS-1(10) |
C.U.H.K.A.A. Thomas Cheung School |
N/A |
148.7 |
260 |
N/A |
Works Contract 1103 |
|||||
DMS-2(11) |
Price Memorial Catholic Primary School |
N/A |
167.4 |
260 |
N/A |
Works Contracts 1103 and 1106 |
|||||
DMS-3(12) |
Hong Kong S.K.H Nursing Home (1) |
N/A |
159.1 |
260 |
N/A |
Works Contract 1106(9) |
|||||
DMS-4(12) |
Block 1, Rhythm Garden |
N/A |
160.4 |
260 |
N/A |
Works Contract 1108 (4) |
|||||
Works Contract 1109 |
|||||
DMS-6 |
Katherine Building (2) |
N/A |
156.8 |
260 |
N/A |
DMS-8 |
SKH Good Shepherd Primary School |
N/A |
152.2 |
260 |
N/A |
DMS-9 |
No. 12 Pau Chung Street (3)(8) |
N/A |
160.9 |
260 |
N/A |
DMS-10 |
Chat Ma Mansion |
N/A |
170.4 |
260 |
N/A |
Works Contract 1111 |
|||||
AM1(5)(13) |
No. 234 – 238 Chatham Road North (6) |
N/A |
183.9 |
260 |
N/A |
Works Contract 1112 |
|||||
AM2 |
Site Boundary of Finger Pier Adjacent to Harbourfront Horizon (7) |
N/A |
182 |
260 |
N/A |
Works Contract 11240 (4) |
|||||
Works Contract 11286 |
|||||
DMS-7 (14) |
Sky Tower - Tower 2 |
23 - 93 |
166.7 |
260 |
No |
Notes:
(1) Alternative monitoring location to Shek On House
(2) Alternative monitoring location to Prosperity House
(3) Alternative monitoring location to Lucky Building
(4) No TSP monitoring is required under this contract
(5) AM1 named as HUH-1-3 in SCL(TAW-HUH) and SCL(HHS) EIA Reports.
(6) Alternative monitoring location to Wing Fung Building
(7) Alternative monitoring location to Harbourfront Horizon
(8) Alternative monitoring location of No. 26 Kowloon City Road
(9) The 24-hour TSP monitoring works would be taken up by Works Contract 1106 since the completion of Works Contract 1107 in Feb 2018.
(10) The cessation of monitoring works at DMS-1 was approved by EPD and the last monitoring was conducted on 16 Jul 2018.
(11) The temporary cessation of monitoring works at DMS-2 was approved by EPD in end-June 2019. The last monitoring date was 27 June 2019.
(12) The cessation of monitoring works at DMS-3 and DMS-4 was approved by EPD on 31 Jul 2019. The last monitoring was conducted on 30 Jul 2019.
(13) The cessation of monitoring works at AM1 was proposed on 25 Jul 2019 and EPD expressed no objection on 31 Jul 2019.
(14) ET has obtained the permission from Sky Tower to deploy the High-Volume Sampler (HVS) at the location same as the originally proposed dust monitoring location of DMS-7 in the approved EM&A Manual for SCL (TAW HUH). 24-hour TSP thus has been conducted at Sky Tower - Tower 2 (podium level) since 27 October 2023.
Monitoring Station ID |
Location |
Noise Level (LAeq,30mins, dB(A)) |
Limit Level (dB(A)) |
Exceedance due to the Project Construction (Yes/No/N/A) |
||
Measured |
Baseline |
Corrected (7) |
||||
Works Contracts 1102 and 1103 |
||||||
NMS-CA-1(12) |
C.U.H.K.A.A. Thomas Cheung School |
N/A |
57.0 |
N/A |
70 (65 during examination period) |
N/A |
Works Contract 1103 |
||||||
NMS-CA-2(13) |
Price Memorial Catholic Primary School |
N/A |
66.0 |
N/A |
70 (65 during examination period) |
N/A |
Works Contracts 1103 and 1106 |
||||||
NMS-CA-3(14) |
Hong Kong S.K.H Nursing Home (1) |
N/A |
73.0 |
N/A |
70 |
N/A |
Works Contracts 1106(11) |
||||||
NMS-CA-4(14) |
Block 1, Rhythm Garden (north- eastern façade) |
N/A |
71.0 |
N/A |
75 |
N/A |
NMS-CA-5(14) |
Block 1, Rhythm Garden (northern façade) (2) |
N/A |
74.0 |
N/A |
70 (65 during examination period) |
N/A |
Works Contract 1108 (6) |
||||||
Works Contract 1109 |
||||||
NMS-CA-6 |
No. 16-23 Nam Kok Road (3) |
N/A |
76.1 |
N/A |
75 |
N/A |
NMS-CA-8 |
SKH Good Shepherd Primary School |
N/A |
75.4 |
N/A |
70 (65 during examination period) (79 during the period of conducting the continuous noise monitoring) (8) |
N/A |
NMS-CA-9 |
Kong Yiu Mansion (4) |
N/A |
69.2 |
N/A |
75 |
N/A |
NMS-CA-10 |
Chat Ma Mansion |
N/A |
76.6 |
N/A |
75 |
N/A |
Works Contract 1111 |
||||||
NM1(15) |
Carmel Secondary School (South Block) |
N/A |
68.0 |
N/A |
70 (65 during examination period) (68 during the period of conducting the continuous noise monitoring) (9) |
N/A |
NM2(15) |
No. 234 – 238 Chatham Road North (5) |
N/A |
79.0 |
N/A |
75 (77) (10) |
N/A |
Works Contract 1112 (6) |
||||||
Works Contract 11240 (6) |
Monitoring Station ID |
Location |
Noise Level (LAeq,30mins, dB(A)) |
Limit Level (dB(A)) |
Exceedance due to the Project Construction (Yes/No/N/A) |
||
Measured |
Baseline |
Corrected (7) |
||||
Works Contract 11286 |
||||||
NMS-CA-7 |
Sky Tower - Tower 2 |
66.6 – 69.7 |
70.0 |
< Baseline |
75 |
No |
Notes:
(1) Alternative monitoring location to Shek On House.
(2) Alternative monitoring location to Canossa Primary School (San Po Kong).
(3) Alternative monitoring location to Prosperity House.
(4) Alternative monitoring location to Lucky Building.
(5) Alternative monitoring location to Wing Fung Building.
(6) No construction noise monitoring is required under this contract.
(7) The measured noise levels are corrected against the corresponding baseline noise levels.
(8) The Limit Level of 79 dB(A) was updated on 22 Aug 2013 as per the latest Construction Noise Mitigation Measures Plan (CNMMP) and Continuous Noise Monitoring Plan (CNMP) which were approved by EPD.
(9) The Limit of 68 dB(A) was updated on 20 Jan 2014 as per the latest CNMMP and CNMP which were approved by EPD.
(10) Daytime noise Limit Level of 77 dB(A) applies during the continuous noise monitoring period.
(11) The construction noise monitoring works would be taken up by Works Contract 1106 since the completion of Works Contract 1107 in Feb 2018.
(12) The cessation of monitoring works at NMS-CA-1 was approved by EPD and the last monitoring was conducted on 17 Jul 2018.
(13) The temporary cessation of monitoring works at NMS-CA-2 was approved by EPD in end-June 2019. The last monitoring date was 24 Jun 2019.
(14) The cessation of monitoring works at NMS-CA-3, NMS-CA-4 and NMS-CA-5 was approved by EPD on 31 Jul 2019. The last monitoring proposed on 31 Jul 2019 was rescheduled to 1 Aug 2019 due to adverse weather and the hoist of Typhoon Signal No.8 (Typhoon “Wipha”).
(15) The cessation of monitoring works at NM1 and NM2 were proposed on 25 Jul 2019 and EPD expressed no objection on 31 Jul 2019.
Works Contract |
Environmental Complaints |
Notification of Summons |
Successful Prosecutions |
11286 |
0 |
0 |
0 |
11234 |
0 |
0 |
0 |
3.1.1 The respective Contractors have implemented all mitigation measures and requirements as stated in the EIA Reports, EM&A Manuals and EP-438/2012/K. The status of required submissions under the EP as of the reporting period are summarised in Tables 3.1.
Table 3.1 Summary of Status of Required Submissions for EP-438/2012/L
EP Condition (EP-438/2012/K) |
Submission |
Submission date |
Condition 1.12 |
Notification of Commencement Date of Construction of the Project |
1 Aug 2012 |
Condition 2.3 |
Notification of Information of Community Liaison Groups |
13 Jul 2012 (1st submission) 31 Aug 2012 (2nd submission) 30 Nov 2012 (3rd submission) |
Condition 2.7 |
Management Organisation of Main Construction Companies |
27 Jul 2012 (1st submission) 21 Aug 2012 (2nd submission) 19 Dec 2012 (3rd submission) 22 Jan 2013 (4th submission) 30 Apr 2013 (5th submission) 21 May 2013 (6th submission) |
Condition 2.8 |
Construction Programme and EP Submission Schedule |
27 Jul 2012 |
Condition 2.9 |
Construction Noise Mitigation Measures Plan (CNMMP) |
1 Aug 2012 (1st submission) 28 Sep 2012 (2nd submission) 30 Nov 2012 (3rd submission) 11 Jan 2013 (4th submission) 8 Feb 2013 (Approved) 8 Feb 2013 (5th submission) 26 Apr 2013 (6th submission) 11 Jun 2013 (7th submission) 12 Jul 2013 (Approved) 26 Jul 2013 (8th submission) 22 Aug 2013 (Approved) 23 Aug 2013 (9th submission) 13 Sep 2013 (Approved) 20 Jan 2014 (10th submission) 26 Feb 2014 (Approved) 31 Mar 2015 (Contract 1106 submission only) 13 Apr 2015 (Contract 1106 submission only) 15 Apr 2015 (Approved) |
Condition 2.10 |
Continuous Noise Monitoring Plan (CNMP) |
1 Aug 2012 (1st submission) 28 Sep 2012 (2nd submission) 30 Nov 2012 (3rd submission) 11 Jan 2013 (4th submission) 8 Feb 2013 (Approved) 8 Feb 2013 (5th submission) 26 Apr 2013 (6th submission) 11 Jun 2013 (7th submission) 12 Jul 2013 (Approved) 26 Jul 2013 (8th submission) 22 Aug 2013 (Approved) 23 Aug 2013 (9th submission) |
EP Condition (EP-438/2012/K) |
Submission |
Submission date |
|
|
13 Sep 2013 (Approved) 20 Jan 2014 (10th submission) 26 Feb 2014 (Approved) 7 Oct 2014 (11th submission) 23 Oct 2014 (Approved) |
Condition 2.11 |
Construction and Demolition Materials Management Plan (C&DMMP) |
6 Jul 2012 (1st submission) 12 Sep 2012 (2nd submission) 10 Oct 2012 (Approved) |
Condition 2.12 |
Sediment Management Plan |
6 Jul 2012 (1st submission) 12 Sep 2012 (2nd submission) 5 Oct 2012 (3rd submission) 10 Oct 2012 (Approved) 4 Mar 2013 (4th submission) 9 May 2013 (5th submission) 24 Jul 2013 (6th submission) 26 Jul 2013 (Approved) |
Condition 2.13 |
Visual, Landscape, Tree Planting & Tree Protection Plan |
6 Jul 2012 (1st submission) 30 Aug 2012 (2nd submission) 3 Oct 2012 (3rd submission) 13 Nov 2013 (Approved) 14 Nov 2012 (4th submission) 8 Feb 2013 (5th submission) 18 Mar 2013 (6th submission) 18 Jun 2013 (7th submission) 12 Jul 2013 (Approved) 23 Mar 2017 (8th submission) 7 Mar 2018 (9th submission) 30 Jul 2018 (10th submission) 28 Feb 2019 (11th submission) 5 Mar 2019 (12th submission) 29 May 2019 (13th submission) 19 Jul 2019 (Approved) |
Condition 2.14 |
Transplantation Proposal for Plant Species of Conservation Importance |
22 Aug 2012 (1st submission) 5 Oct 2012 (2nd submission) 26 Nov 2012 (3rd submission) 4 Dec 2012 (Approved) |
Condition 2.15 |
Conservation Plan |
31 Jan 2013 (1st submission) 18 Mar 2013 (2nd submission) 24 Apr 2013 (Approved) |
Condition 2.16 |
Archaeological Action Plan(s) (AAP(s)) for Works Contract 1109 |
10 Aug 2012 (1st submission) 3 Sep 2012 (2nd submission) 21 Sep 2012 (Approved) 11 Oct 2013 (3rd submission) 1 Nov 2013 (Approved) |
Condition 2.16 |
Archaeological Action Plan(s) (AAP(s)) for Works Contract 1106 |
29 Jan 2013 (1st submission) 19 Mar 2013 (2nd submission) 8 Apr 2013 (Approved) |
Condition 2.23 |
Supplementary Contamination Assessment Report for New Territories South Animal Centre |
28 Sep 2012 25 Oct 2012 (Approved) |
Condition 2.27 |
Operational Ground-borne Noise Mitigation Measures Plan |
18 Mar 2016 (Batch 1 Version A submission) 28 Apr 2016 (Batch 1 Version B submission) 28 Apr 2016 (Batch 2 Version A submission) 1 Jun 2016 (Batch 1 Version C submission) 1 Jun 2016 (Batch 2 Version B submission) 23 Jun 2016 (Batch 1 Version D submission) |
EP Condition (EP-438/2012/K) |
Submission |
Submission date |
|
|
23 Jun 2016 (Batch 2 Version C submission) 15 Jul 2016 (Batch 1 Version D approved) 15 Jul 2016 (Batch 2 Version C approved) 15 Sep 2016 (Batch 3 Version A submission) 4 Oct 2016 (Batch 3 Version A approved) 8 Mar 2017 (Batch 4 Version A) 7 Apr 2017 (Batch 4 Version A approved) 7 Jun 2017 (Final) 20 Jul 2017 (Approved) |
Condition 2.28 |
As-built Drawings for Operational Ground- borne Noise Mitigation Measures |
10 Aug 2017 (1st submission) 15 Sep 2017 (Approved) |
Condition 2.30 |
As-built Drawings for Operational Air-borne Noise Mitigation Measures |
4 Dec 2015 (1st submission) 28 Dec 2015 (2nd submission) 4 Feb 2016 (Approved) 20 Mar 2018 (3rd submission) 18 Jul 2018 (Approved) 4 May 2018 (4th submission) 23 Jul 2018 (Approved) 20 Feb 2020 (5th submission) 17 Mar 2020 (Approved) |
Condition 2.31 |
Performance Test Report for Train Noise – Operational Airborne Railway and Ground- borne Noise |
15 Nov 2018 (Batch 1 Version A submission) 30 Jan 2019 (Batch 2 Version A submission) 29 Mar 2019 (Batch 1 Version A & Batch 2 Version B submission) 15 April 2019 (Approved) |
Condition 2.32 |
Proposal for Updating Maximum Allowable Sound Power Levels of Fixed Plant Sources |
30 Jan 2019 (Batch 1 Version A submission) 27 Feb 2019 (Batch 1 Version B submission) 13 Mar 2019 (Batch 1 Version B approved) 15 Mar 2019 (Batch 2 Version A submission) 8 Apr 2019 (Batch 2 Version A approved) 24 April 2019 (Batch 3 & 4 Version A submission) 21 May 2019 (Batch 3 Version B submission) 11 Jun 2019 (Batch 3 Version B & Batch 4 Version A approved) 21 Jun 2019 (Batch 5 Version A submission) 17 Jul 2019 (Batch 5 Version A approved) 19 Jul 2019 (Batch 6 Version A submission) 26 Jul 2019 (Batch 7 Version A submission) 29 Jul 2019 (Batch 6 Version A approved) 14 Aug 2019 (Batch 7 Version A approved) |
EP Condition (EP-438/2012/K) |
Submission |
Submission date |
Condition 2.32 |
Fixed Plant Noise Audit Report |
30 Jan 2019 (Batch 1 Version A submission) 15 Mar 2019 (Batch 1 Version B submission) 4 Apr 2019 (Batch 1 Version B approved) 16 Apr 2019 (Batch 2 Version A submission) 7 May 2019 (Batch 2 Version A approved) 24 Jun 2019 (Batch 3 Version A and Batch 4 Version A submission) 6 Jul 2019 (Batch 3 Version A and Batch 4 Version A approved) 2 Aug 2019 (Batch 5 Version A submission) 27 Aug 2019 (Batch 6 Version A submission) 29 Aug 2019 (Batch 7 Version A submission) 3 Sep 2019 (Batch 5 Version A approved) 13 Sep 2019 (Batch 6 Version B approved) 23 Sep 2019 (Batch 7 Version B submission) 11 Oct 2019 (Batch 7 Version B approved) |
Condition 2.33 |
As-built Drawings for Landscape and Visual Mitigation Measures |
4 Dec 2015 (1st submission) 28 Dec 2015 (2nd submission) 4 Feb 2016 (Approved) 22 Aug 2018 (3rd submission) 5 Nov 2018 (4th submission) 6 Sep 2019 (5th submission) 11 Sep 2019 (Approved) 27 Sep 2019 (6th submission) 21 Feb 2020 (7th submission) 17 Sep 2020 (8th submission) 4 Nov 2020 (9th submission) 18 Jan 2024 (10th submission) 26 Jun 2024 (11th submission) |
Condition 2.36 |
Contamination Assessment Plan (CAP) for the Temporary Magazine Site at TKO Area 137 |
23 Mar 2016 (1st submission) 20 Apr 2016 (2nd submission) 22 Apr 2016 (Approved) |
Condition 2.36 |
Contamination Assessment Report (CAR) for the Temporary Magazine Site at TKO Area 137 |
19 May 2016 (1st submission) 3 Jun 2016 (2nd submission) 15 Jun 2016 (Approved) |
Condition 3.1 |
Proposal for Termination of Environmental Monitoring and Audit (EM&A) Programme for Kai Tak Barging Point Facilities |
7 Oct 2016 (Approved) |
Condition 3.1 |
Proposal for Cessation of EM&A Works at Hin Keng |
9 May 2018 (1st submission) 16 Jul 2018 (Approved) |
Condition 3.1 |
Proposal for Cessation of EM&A Programme at Diamond Hill Station |
25 Jul 2019 (1st submission) 31 Jul 2019 (Approved) |
Condition 3.1 |
Proposal for Cessation of EM&A Programme at Hung Hom North Approach Tunnels |
25 Jul 2019 (1st submission) 31 Jul 2019 (Approved) |
EP Condition (EP-438/2012/K) |
Submission |
Submission date |
Condition 3.1 |
Proposal for Cessation of EM&A Programme at Stations and Tunnels of Kowloon City Section |
24 Aug 2020 (1st submission) 28 Aug 2020 (Approved) |
Condition 3.1 |
Proposal for Cessation of EM&A Programme at Hung Hom Station and Stabling Sidings |
21 Oct 2020 (1st submission) 29 Oct 2020 (Approved) |
Condition 3.3 |
Baseline Monitoring Report (Works Contract 1109 - Stations and Tunnels of Kowloon City Section) |
27 Jul 2012 |
Condition 3.3 |
Baseline Monitoring Report (Works Contract 1108A – Kai Tak Barging Point Facilities) |
31 Jul 2012 |
Condition 3.3 |
Baseline Monitoring Report (Works Contracts 1103, 1106 and 1111 – Hin Keng to Diamond Hill Tunnels, Diamond Hill Station, and Hung Hom North Approach Tunnels) |
19 Oct 2012 |
Condition 3.4 |
Monthly Operational Airborne Rail Noise Monitoring Report (Festival City) No. 1-6 |
Reported in previous Monthly EM&A Reports |
Condition 3.4 |
Monthly EM&A Reports No. 1-118
Monthly EM&A Report No.119 |
Reported in previous Monthly EM&A Reports 14 February 2025 |