MTR Corporation Limited
Shatin to Central Link –
Tai Wai to Hung Hom Section
and Mong Kok East to Hung Hom Section
Monthly EM&A Report
No.115
[Period from 1 to 30 September 2024]
Page
2 ENVIRONMENTAL MONITORING AND AUDIT.................................................... 4
3 IMPLEMENTATION STATUS ON THE ENVIRONMENTAL PROTECTION REQUIREMENTS
......................................................................................................................... 9
Table 1.1 Summary of Awarded Works Contracts
Table 2.1 Summary of Works Contracts and Respective EPs
Table 2.2 Summary of Major Construction Activities in the Reporting Period
Table 2.3 Summary of TSP Monitoring Results in the Reporting Period
Table 2.4 Summary of Construction Noise Monitoring Results in the Reporting Period
Table 2.5 Log for Environmental Complaints, Notification of Summons and Successful Prosecutions for the Reporting Month
Table 3.1 Summary of Status of Required Submissions for EP-437/2012/B
Table 3.2 Summary of Status of Required Submissions for EP-438/2012/L
Appendix A Monthly EM&A Report for SCL (TAW-HUH) and SCL (MKK-HUH) – Pedestrian Link Connecting Pak Tai Street and Sung Wong Toi Station (Contract No. 11286)
Appendix B Monthly EM&A Report for SCL (TAW-HUH) and SCL (MKK-HUH) – Re-provisioning of Ma Chai Hang Recreation Ground (Contract No. 11234)
1.1.1
The Shatin to Central Link (SCL) is a 17km extension of the existing Ma
On Shan Line (MOL) and East Rail Line (EAL) comprising (i) The East-West
Corridor which extends the MOL from Tai Wai to Hung Hom via East Kowloon
to connect with the West Rail Line (WRL) at Hung Hom Station (HUH) and
Stabling Sidings at Hung Hom Freight Yard (HHS); and (ii) The North-South
Corridor which is an extension of the East Rail Line (EAL) at Hung Hom across
the harbour to Admiralty Station (ADM).
1.1.2
Shatin to Central Link – Tai Wai
to Hung Hom Section [SCL (TAW-HUH)] and Shatin to Central Link – Mong Kok East to Hung Hom Section
[SCL (MKK-HUH) (hereafter referred to as “the Project”) are parts of the SCL. Shatin to
Central Link – Stabling Sidings at Hung Hom Freight
Yard [SCL (HHS)]
is a proposed stabling sidings
option for SCL (TAW
– HUH) at the former freight yard in Hung Hom.
1.1.3
The Environmental Impact Assessment (EIA) Reports for SCL (TAW-HUH)
(Register No.: AEIAR-167/2012), SCL (MKK-HUH) (Register
No.: AEIAR-165/2012) and SCL
(HHS) (Register No.: AEIAR-164/2012) were approved on 17 February 2012 under the Environmental Impact Assessment Ordinance (EIAO). Following the approval of the EIA Reports, two Environmental Permits (EPs) were granted on 22 March 2012, one covers SCL (TAW-HUH) and SCL (HHS) (EP No: EP-438/2012) and the other covers SCL (MKK-HUH) and SCL (HHS) (EP No.: EP-437/2012), for their construction and operation. Variations of environmental permit (VEP) were subsequently applied for EP-438/2012 and EP-437/2012. The latest Environmental Permits (EP Nos.: EP-438/2012/L and EP- 437/2012/B) were issued by Director of Environmental Protection (DEP) on 14 August 2024 and 8 February 2024, respectively.
1.2.1
Thirteen civil construction works contracts of the Project have been
awarded since July 2012. The construction of the Project commenced in September
2012. Table 1.1 summarises the
information of the awarded Works Contracts. All major construction works under
eleven out of thirteen civil construction works contracts have been completed.
Works Contract |
Description |
Construction Start Date |
Contractor |
Environmental
Team |
1101(1) |
Ma On Shan Line
Modification Works |
December 2012 |
Sun Fook Kong Joint Venture (SFKJV) |
ANewR Consulting Ltd. (ANewR) |
1102(6) |
Hin Keng Station
and Approach Structures |
October 2013 |
Penta-Ocean Construction Co. Ltd. |
Wellab Limited (Wellab) |
1103(7) |
Hin Keng to Diamond
Hill Tunnels |
February 2013 |
Vinci Construction Grands Projets |
Ove Arup & Partners Hong Kong Ltd. (Arup) |
October 2019 |
Wing Ho Yuen Landscaping Co. Ltd. |
MTR Co. Limited |
||
1106(8) |
Diamond Hill Station |
March 2013 |
Leader Joint Venture |
Cinotech Consultants Ltd. (Cinotech) |
1107(4) |
Diamond Hill to Kai Tak Tunnels |
May 2013 |
Chun Wo - SELI Joint Venture |
Cinotech Consultants Ltd. (Cinotech) |
Works Contract |
Description |
Construction Start Date |
Contractor |
Environmental
Team |
1108(5) |
Kai Tak Station
and Associated Tunnels |
June 2013 |
Kaden -Chun Wo Joint Venture |
Environmental Pioneers & Solutions Ltd. |
1108A(2) |
Kai Tak Barging
Point Facilities |
September 2012 |
Concentric – Hong
Kong River Joint Venture (CCL- HKR JV) |
Cinotech
Consultants Ltd. (Cinotech) |
1109(10) |
Stations and Tunnels of Kowloon City Section |
September 2012 |
Samsung-Hsin Chong JV (SSHCJV) |
ERM-Hong Kong Limited (ERM) |
1111(9) |
Hung Hom North Approach Tunnels |
January 2013 |
Gammon-Kaden
SCL1111 JV |
AECOM Asia
Co. Ltd. |
1112(11) |
Hung Hom Station
and Stabling Sidings |
June 2013 |
Leighton Contractors (Asia) Limited |
SMEC Asia Ltd., HK |
11240(3) |
Excavation,
Sorting and Disposal of Stockpiled
Spoils to Approved Receptor Site |
October 2017 |
Crown Asia Engineering Limited (CAEL) |
MTR Corporation
Limited |
11286 |
Pedestrian
Link Connecting Pak Tai Street and Sung
Wong Toi Station |
July 2023 |
Paul Y. Construction Co., Ltd. |
ERM-Hong Kong Limited (ERM) |
11234 |
Re-provisioning of Ma
Chai Hang Recreation Ground |
March 2024 |
Build King Civil
Engineering Ltd. |
Fugro Technical Services Ltd. |
Notes:
(1) All construction works (works areas at Tai Wai Mei Tin Road and the offsite temporary storage areas) under
Works Contract 1101 were completed on 29 February 2016.
(2) All
construction works (Kai Tak Barging Point Facilities) under Works Contract
1108A were completed on 29 September 2016.
(3) All construction works (Excavation, Sorting
and Disposal of Stockpiled Spoils to Approved
Receptor Site) under Works Contract 11240 were completed on 3 January
2018.
(4) All
construction works (Diamond Hill to Kai Tak Tunnels) under Works Contract 1107
were completed on 22 February 2018.
(5) All
construction works (Kai Tak Station and associated tunnels) under Works
Contract 1108 were completed in July 2018.
(6) All construction works (Hin Keng Station and Approach Structures) under Works Contract
1102 were completed in December 2018. The
Environmental Team was taken over by Wellab
Limited starting from 1
January 2019.
(7) All
construction works (Hin Keng to Diamond Hill Tunnels) under Works Contract 1103
were completed in June 2019. Minor landscaping works at Fung Tak had been
commenced in mid- October and all the works were completed at the end of
October 2019.
(8) All
construction works (Diamond Hill Station) under Works Contract 1106 with
significant environmental impacts were substantially completed by 25 June 2019.
(9) All major
construction works (Hung
Hom North Approach
Tunnels) under Works
Contract 1111 have been substantially completed since
18 November 2018.
(10) All
construction works (Stations and Tunnels of Kowloon City Section) under Works
Contract 1109 have been substantially completed on 12 August 2020.
(11) All major
construction works (Hung Hom Station and Stabling Sidings) under Works Contract
1112 have been substantially completed by 17 September 2020.
1.2.2
All major construction works for SCL (TAW-HUH) and SCL (HHS) which were
covered by EP No. EP-438/2012/L had been completed. The remaining works, including (1) the
re-provision of recreational facilities at Ma Chai Hang and (2) a pedestrian link connecting Sung Wong Toi Station
to Pak Tai Street, have been carried
out by other works contracts in 2023 -2024 resulting in the
liaison with Railway Development Office (RDO), relevant government departments
and stakeholders. Apart
from the above, the remaining tree
planting works at Kai Tak Station Square (Phase 2) which have been scheduled after the full opening of SCL were completed.
1.2.3
All major construction works for SCL (MKK-HUH) and SCL (HHS) which were
covered by EP No. EP-437/2012/B had been completed. Apart from that, those proposed additional tree seedlings at the trackside in Hung Hom and the remaining planting
works of additional tree seedlings and Kai Tak Station Square (Phase 1)
which were carried out at a later stage in 2023 were completed.
1.3.1
The Environmental Monitoring and Audit (EM&A) programme for the Project commenced in September 2012. This is the one hundred
and thirteenth EM&A
Report for the Project
which summarises the EM&A works undertaken during the period from 1 to 30
September 2024.
2.1.1
The construction of SCL has been divided
into different civil
construction works contracts which are covered by EP No.
EP-437/2012/B and/or EP-438/2012/L. As per the EP Conditions, EM&A Reports
for the works contracts as shown in the table below have been prepared by the
respective Contractor’s ETs.
Works
Contract |
Contract Title |
Works Covered in
Environmental Permit No. |
1101 |
Ma On Shan
Modification Works |
EP-438/2012/L |
1102 |
Hin Keng Station and Approach
Structures |
EP-438/2012/L |
1103 |
Hin Keng to Diamond Hill
Tunnels |
EP-438/2012/L |
1106 |
Diamond Hill Station |
EP-438/2012/L |
1107 |
Diamond Hill to Kai Tak Tunnels |
EP-438/2012/L |
1108 |
Kai Tak Station and Associated Tunnels |
EP-438/2012/L |
1108A |
Kai Tak Barging
Point Facilities |
EP-438/2012/L |
1109 |
Stations and Tunnels of Kowloon City Section |
EP-438/2012/L |
1111 |
Hung Hom North
Approach Tunnels |
EP-437/2012/B & EP-438/2012/L |
1112 |
Hung Hom Station and Stabling Sidings |
EP-437/2012/B & EP-438/2012/L |
11240 |
Excavation, Sorting and Disposal of Stockpiled Spoils to Approved Receptor Site |
EP-438/2012/L |
11286 |
Pedestrian Link Connecting Pak Tai Street and
Sung Wong Toi Station |
EP-438/2012/L |
11234 |
Re-provisioning of Ma Chai Hang Recreation Ground |
EP-438/2012/L |
2.1.2
The EM&A Reports for Works Contract Nos. 11286 (a pedestrian link
connecting Sung Wong Toi Station
to Pak Tai Street) and 11234 (the re-provision of recreational facilities at Ma Chai Hang) prepared by the respective Contractor’s ETs are provided in Appendix A and Appendix B respectively. The EM&A Report provide details of the
project information, EM&A requirements, impact monitoring and audit results
for the corresponding Contracts.
2.1.3
A summary of the major construction activities undertaken by the respective Contractors of various Works Contracts
during the reporting period are presented in Table 2.2.
Works Contract |
Site |
Construction Activities |
11286 |
Works in Sung
Wong Toi (SUW) (formerly named as To Kwa
Wan (TKW)) |
Near Sung
Wong Toi Exit
D (W1) •
ELS •
Pile cap works •
Grout curtain works •
On-site fabrication of Footbridge |
|
|
Near Pak Tai Street
(H2) •
Socket H pile |
11234 |
Re-provisioning of Ma Chai
Hang Recreation Ground |
•
Site Clearance •
Construction of football pitch fence footing |
2.1.4
Impact monitoring for air quality and construction noise were conducted
in accordance with the EM&A
Manual in the reporting period
under Works Contract
11286. Continuous noise
monitoring was not required in the reporting period for the Works Contracts
according to the Continuous Noise Monitoring Plan (CNMP). The air quality and construction noise for
this reporting period are summarised in Tables
2.3 and 2.4. Details of the
monitoring requirements, locations, equipment, methodology and QA/QC procedures
are presented in the EM&A Reports as provided in Appendices A.
2.1.5
No environmental complaint; no exceedance of action and limit levels;
and no notification of summons or successful prosecutions was received during this reporting
period. Log for environmental
complaints, notification of summons and successful prosecutions are provided in
Table 2.5.
2.1.6
Regular site inspections were conducted by the respective ETs (both
Works Contract Nos. 11286 and 11234) on a weekly
basis to check the implementation of environmental
pollution control and mitigation measures for the Project. No non-conformance
was identified in the reporting period.
Monitoring Station ID |
Location |
TSP Concentration (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
Exceedance
due to the Project Construction (Yes/ No/ N/A) |
Works Contracts 1102
and 1103 |
|||||
DMS-1(10) |
C.U.H.K.A.A. Thomas Cheung School |
N/A |
148.7 |
260 |
N/A |
Works Contract 1103 |
|||||
DMS-2(11) |
Price Memorial Catholic Primary School |
N/A |
167.4 |
260 |
N/A |
Works Contracts 1103
and 1106 |
|||||
DMS-3(12) |
Hong Kong S.K.H Nursing Home (1) |
N/A |
159.1 |
260 |
N/A |
Works Contract 1106(9) |
|||||
DMS-4(12) |
Block 1, Rhythm Garden |
N/A |
160.4 |
260 |
N/A |
Works Contract 1108
(4) |
|||||
Works Contract 1109 |
|||||
DMS-6 |
Katherine Building (2) |
N/A |
156.8 |
260 |
N/A |
DMS-8 |
SKH Good Shepherd Primary School |
N/A |
152.2 |
260 |
N/A |
DMS-9 |
No. 12 Pau Chung Street (3)(8) |
N/A |
160.9 |
260 |
N/A |
DMS-10 |
Chat Ma Mansion |
N/A |
170.4 |
260 |
N/A |
Works Contract 1111 |
|||||
AM1(5)(13) |
No. 234 – 238 Chatham Road North (6) |
N/A |
183.9 |
260 |
N/A |
Works Contract 1112 |
|||||
AM2 |
Site Boundary of Finger Pier Adjacent to
Harbourfront Horizon (7) |
N/A |
182 |
260 |
N/A |
Works Contract 11240
(4) |
|||||
Works Contract 11286 |
|||||
DMS-7 (14) |
Sky Tower
- Tower 2 |
20-52 |
166.7 |
260 |
No |
Notes:
(1)
Alternative monitoring location
to Shek On House
(2) Alternative monitoring location to Prosperity House
(3)
Alternative monitoring location
to Lucky Building
(4) No TSP monitoring is required under this contract
(5)
AM1 named as HUH-1-3 in SCL(TAW-HUH) and SCL(HHS) EIA
Reports.
(6)
Alternative monitoring location
to Wing Fung Building
(7)
Alternative monitoring location
to Harbourfront Horizon
(8) Alternative monitoring location of No. 26 Kowloon
City Road
(9) The 24-hour TSP monitoring works would be taken up by Works Contract 1106 since the completion
of Works Contract 1107 in Feb 2018.
(10) The cessation of monitoring
works at DMS-1 was approved by EPD and the last monitoring was conducted on 16
Jul 2018.
(11) The temporary cessation of
monitoring works at DMS-2 was approved by EPD in end-June 2019. The last
monitoring date was 27 June 2019.
(12) The cessation of monitoring works at DMS-3 and DMS-4 was approved
by EPD on 31 Jul 2019. The last monitoring was conducted on 30
Jul 2019.
(13) The cessation of monitoring
works at AM1 was proposed on 25 Jul 2019 and EPD expressed no objection on 31
Jul 2019.
(14) ET has obtained the
permission from Sky Tower to deploy the High-Volume Sampler (HVS) at the
location same as the originally proposed dust monitoring location of DMS-7 in
the approved EM&A Manual for SCL (TAW HUH). 24-hour TSP thus has been conducted at Sky Tower - Tower 2 (podium level) since 27 October 2023.
Monitoring Station ID |
Location |
Noise Level (LAeq,30mins, dB(A)) |
Limit Level (dB(A)) |
Exceedance due to the Project Construction (Yes/No/N/A) |
||
Measured |
Baseline |
Corrected (7) |
||||
Works Contracts 1102
and 1103 |
||||||
NMS-CA-1(12) |
C.U.H.K.A.A. Thomas Cheung School |
N/A |
57.0 |
N/A |
70 (65 during examination period) |
N/A |
Works Contract 1103 |
||||||
NMS-CA-2(13) |
Price Memorial Catholic Primary School |
N/A |
66.0 |
N/A |
70 (65 during examination period) |
N/A |
Works Contracts 1103
and 1106 |
||||||
NMS-CA-3(14) |
Hong Kong S.K.H Nursing Home (1) |
N/A |
73.0 |
N/A |
70 |
N/A |
Works Contracts 1106(11) |
||||||
NMS-CA-4(14) |
Block 1, Rhythm
Garden (north- eastern
façade) |
N/A |
71.0 |
N/A |
75 |
N/A |
NMS-CA-5(14) |
Block 1, Rhythm
Garden (northern façade) (2) |
N/A |
74.0 |
N/A |
70 (65 during examination period) |
N/A |
Works Contract 1108 (6) |
||||||
Works Contract 1109 |
||||||
NMS-CA-6 |
No. 16-23
Nam Kok Road
(3) |
N/A |
76.1 |
N/A |
75 |
N/A |
NMS-CA-8 |
SKH Good Shepherd
Primary School |
N/A |
75.4 |
N/A |
70 (65 during examination period) (79 during the period of
conducting the continuous noise monitoring) (8) |
N/A |
NMS-CA-9 |
Kong Yiu
Mansion (4) |
N/A |
69.2 |
N/A |
75 |
N/A |
NMS-CA-10 |
Chat Ma
Mansion |
N/A |
76.6 |
N/A |
75 |
N/A |
Works Contract 1111 |
||||||
NM1(15) |
Carmel Secondary School (South Block) |
N/A |
68.0 |
N/A |
70 (65 during examination period) (68 during the period of
conducting the continuous noise monitoring) (9) |
N/A |
NM2(15) |
No. 234 – 238 Chatham Road North (5) |
N/A |
79.0 |
N/A |
75 (77) (10) |
N/A |
Works Contract 1112 (6) |
||||||
Works Contract 11240 (6) |
Monitoring Station ID |
Location |
Noise Level (LAeq,30mins, dB(A)) |
Limit Level (dB(A)) |
Exceedance due to the Project Construction (Yes/No/N/A) |
||
Measured |
Baseline |
Corrected (7) |
||||
Works Contract 11286 |
||||||
NMS-CA-7 |
Sky Tower - Tower 2 |
67.9 – 68.9 |
70.0 |
< Baseline |
75 |
No |
Notes:
(1)
Alternative monitoring location
to Shek On House.
(2)
Alternative monitoring location
to Canossa Primary
School (San Po Kong).
(3)
Alternative monitoring location
to Prosperity House.
(4)
Alternative monitoring location
to Lucky Building.
(5)
Alternative monitoring location
to Wing Fung Building.
(6)
No construction noise
monitoring is required
under this contract.
(7)
The measured noise
levels are corrected
against the corresponding baseline noise levels.
(8)
The Limit Level of 79 dB(A) was updated on 22 Aug 2013 as per the latest
Construction Noise Mitigation Measures Plan (CNMMP)
and Continuous Noise Monitoring
Plan (CNMP) which were approved by EPD.
(9)
The Limit of 68 dB(A)
was updated on 20 Jan 2014 as per the latest CNMMP and CNMP which were approved by EPD.
(10) Daytime noise Limit Level of 77 dB(A) applies
during the continuous noise monitoring period.
(11)
The construction noise
monitoring works would
be taken up by Works
Contract 1106 since
the completion of Works Contract
1107 in Feb 2018.
(12) The cessation of monitoring works at NMS-CA-1
was approved by EPD and the last monitoring was conducted on 17 Jul
2018.
(13) The temporary cessation of monitoring works
at NMS-CA-2 was approved by EPD in end-June 2019.
The last monitoring date was 24 Jun 2019.
(14) The cessation of monitoring works at NMS-CA-3,
NMS-CA-4 and NMS-CA-5
was approved by EPD on 31 Jul 2019. The last monitoring proposed on 31 Jul 2019 was
rescheduled to 1 Aug 2019 due to adverse weather and the hoist of Typhoon
Signal No.8 (Typhoon “Wipha”).
(15)
The cessation of monitoring works at NM1 and NM2 were proposed
on 25 Jul 2019 and EPD expressed
no objection on 31 Jul
2019.
Works Contract |
Environmental Complaints |
Notification of Summons |
Successful Prosecutions |
11286 |
0 |
0 |
0 |
11234 |
0 |
0 |
0 |
3.1.1 The respective Contractors have implemented all mitigation measures and requirements as stated in the EIA Reports, EM&A Manuals and EPs (EP-437/2012/B and EP- 438/2012/K). The status of required submissions under the EPs as of the reporting period are summarised in Tables 3.1 and 3.2.
Table 3.1 Summary of Status of Required Submissions for EP-437/2012/B
EP Condition (EP-437/2012/B) |
Submission |
Submission date |
Condition 1.11 |
Notification of Commencement Date of
Construction of the Project |
30 Nov 2012 |
Condition 2.3 |
Notification of Information of Community
Liaison Groups |
30 Nov 2012 |
Condition 2.5 |
Management Organisation of Main
Construction Companies |
19 Dec 2012
(1st submission) 30 Apr 2013
(2nd submission) |
Condition 2.6 |
Construction Programme and EP Submission Schedule |
19 Dec 2012 |
Condition 2.7 |
Construction Noise Mitigation Measures Plan (CNMMP) |
30 Nov 2012
(1st submission) 8 Feb 2013
(Approved) 26 Apr 2013
(2nd submission) 11 Jun 2013 (3rd submission) 27 Aug 2013
(Approved) 20 Jan 2014
(4th submission) 28 Apr 2016 (Approved) |
Condition 2.8 |
Continuous Noise Monitoring Plan (CNMP) |
30 Nov 2012
(1st submission) 11 Jan 2013
(2nd submission) 8 Feb 2013
(Approved) 20 Jan 2014 (3rd submission) 28 Apr 2016
(Approved) |
Condition 2.9 |
Construction and Demolition Materials Management Plan (C&DMMP) |
6 Jul 2012
(1st submission) 12 Sep 2012 (2nd submission) 15 Oct 2012
(Approved) |
Condition 2.10 |
Sediment Management Plan |
6 Jul 2012 (1st submission) 12 Sep 2012 (2nd submission) 5 Oct 2012 (3rd submission) 15 Oct 2012
(Approved) |
Condition 2.11 |
Visual, Landscape, Tree Planting &
Tree Protection Plan (VLTTP) |
14 Nov 2012
(1st submission) 8 Feb 2013 (2nd submission) 4 Feb 2015
(3rd submission) 26 Jun 2015
(4th submission) 12 May 2017
(5th submission) 17 Apr 2018
(6th submission) 17 Apr 2019
(7th submission) 9 Apr 2020
(8th submission) |
Condition 2.14 |
As-built drawing(s) of
Measures for Mitigating Landscape and Visual Impact and Tree Planting |
23 August 2021 (1st submission) 23 March 2022
(2nd submission) 18 Jan 2024 (3rd submission) 26 Jun 2024
(Approved) |
Condition 2.16 |
Operational
Ground-borne Noise Mitigation Measures Plan |
23 Mar 2017
(1st submission) 17 May 2017
(2nd submission) 28 Jun 2017 (3rd submission) 20 Jul 2017
(Approved) |
Condition 2.19 |
As-built drawing(s) for Operation Air-borne Noise Mitigation Measure |
10 Jan 2018
(1st submission) 9 Feb 2018
(Approved) |
EP Condition (EP-437/2012/B) |
Submission |
Submission date |
Condition 2.21 |
Proposal for Updating Maximum
Allowable Sound Power Levels of Fixed Plant Sources |
26 Jul 2019
(Batch 1 Version
A submission) 14 Aug 2019
(Batch 1 Version A approved) |
Condition 2.21 |
Fixed Plant
Noise Audit Report |
29 Aug 2019
(Batch 1 Version A submission) 11 Oct 2019
(Approved) |
Condition 3.1 |
Proposal for Cessation of EM&A Programme at Hung Hom North Approach Tunnels |
25 Jul 2019
(1st submission) 31 Jul 2019
(Approved) |
Condition 3.1 |
Proposal for Cessation of EM&A Programme at Hung Hom Station and Stabling Sidings |
21 Oct 2020 (1st submission) 29 Oct 2020
(Approved) |
Condition 3.3 |
Baseline Monitoring Report (Works Contracts 1103,
1106 and 1111
– Hin Keng to Diamond Hill Tunnels, Diamond Hill Station, and Hung
Hom North Approach Tunnels) |
19 Oct 2012 |
Condition 3.4 |
Monthly EM&A Reports No. 5-99 |
Reported
in previous Monthly EM&A Reports |
Condition 3.4 |
Final EM&A Review Report |
15 Jan 2024 (1st submission) |
Table 3.2 Summary of Status of Required Submissions for EP-438/2012/L
EP Condition (EP-438/2012/K) |
Submission |
Submission date |
Condition 1.12 |
Notification of Commencement Date
of Construction of the Project |
1 Aug 2012 |
Condition 2.3 |
Notification of Information of Community Liaison
Groups |
13 Jul 2012 (1st submission) 31 Aug 2012 (2nd submission) 30 Nov 2012 (3rd submission) |
Condition 2.7 |
Management Organisation of Main
Construction Companies |
27 Jul 2012 (1st submission) 21 Aug 2012 (2nd submission) 19 Dec 2012 (3rd submission) 22 Jan 2013 (4th submission) 30 Apr 2013 (5th submission) 21 May 2013 (6th submission) |
Condition 2.8 |
Construction Programme and EP Submission Schedule |
27 Jul 2012 |
Condition 2.9 |
Construction Noise
Mitigation Measures Plan
(CNMMP) |
1 Aug 2012 (1st submission) 28 Sep 2012 (2nd submission) 30 Nov 2012 (3rd submission) 11 Jan 2013 (4th submission) 8 Feb 2013 (Approved) 8 Feb 2013 (5th submission) 26 Apr 2013 (6th submission) 11 Jun 2013 (7th submission) 12 Jul 2013 (Approved) 26 Jul 2013 (8th submission) 22 Aug 2013
(Approved) 23 Aug 2013 (9th submission) 13 Sep 2013
(Approved) 20 Jan 2014 (10th submission) 26 Feb 2014 (Approved) 31 Mar 2015 (Contract 1106 submission only) 13 Apr 2015 (Contract 1106 submission only) 15 Apr 2015 (Approved) |
EP Condition (EP-438/2012/K) |
Submission |
Submission date |
Condition 2.10 |
Continuous
Noise Monitoring Plan
(CNMP) |
1 Aug 2012 (1st submission) 28 Sep 2012 (2nd submission) 30 Nov 2012 (3rd submission) 11 Jan 2013 (4th submission) 8 Feb 2013 (Approved) 8 Feb 2013 (5th submission) 26 Apr 2013 (6th submission) 11 Jun 2013 (7th submission) 12 Jul 2013
(Approved) 26 Jul 2013 (8th submission) 22 Aug 2013
(Approved) 23 Aug 2013 (9th submission) 13 Sep 2013 (Approved) 20 Jan 2014 (10th submission) 26 Feb 2014
(Approved) 7 Oct 2014 (11th submission) 23 Oct 2014 (Approved) |
Condition 2.11 |
Construction and Demolition Materials Management Plan (C&DMMP) |
6 Jul 2012 (1st submission) 12 Sep 2012 (2nd submission) 10 Oct 2012 (Approved) |
Condition 2.12 |
Sediment Management Plan |
6 Jul 2012 (1st submission) 12 Sep 2012 (2nd submission) 5 Oct 2012 (3rd submission) 10 Oct 2012 (Approved) 4 Mar 2013 (4th submission) 9 May 2013 (5th submission) 24 Jul 2013 (6th submission) 26 Jul 2013
(Approved) |
Condition 2.13 |
Visual, Landscape, Tree Planting &
Tree Protection Plan |
6 Jul 2012 (1st submission) 30 Aug 2012 (2nd submission) 3 Oct 2012 (3rd submission) 13 Nov 2013 (Approved) 14 Nov 2012 (4th submission) 8 Feb 2013 (5th submission) 18 Mar 2013 (6th submission) 18 Jun 2013 (7th submission) 12 Jul 2013 (Approved) 23 Mar 2017 (8th submission) 7 Mar 2018 (9th submission) 30 Jul 2018 (10th submission) 28 Feb 2019 (11th submission) 5 Mar 2019 (12th submission) 29 May 2019 (13th submission) 19 Jul 2019 (Approved) |
Condition 2.14 |
Transplantation Proposal for Plant Species of Conservation Importance |
22 Aug 2012 (1st submission) 5 Oct 2012 (2nd submission) 26 Nov 2012 (3rd submission) 4 Dec 2012 (Approved) |
Condition 2.15 |
Conservation Plan |
31 Jan 2013 (1st submission) 18 Mar 2013 (2nd submission) 24 Apr 2013 (Approved) |
Condition 2.16 |
Archaeological Action
Plan(s) (AAP(s)) for Works Contract 1109 |
10 Aug 2012 (1st submission) 3 Sep 2012 (2nd submission) 21 Sep 2012 (Approved) 11 Oct 2013 (3rd submission) 1 Nov 2013
(Approved) |
Condition 2.16 |
Archaeological Action Plan(s) (AAP(s)) for Works Contract 1106 |
29 Jan 2013 (1st submission) 19 Mar 2013 (2nd submission) 8 Apr 2013 (Approved) |
Condition 2.23 |
Supplementary Contamination Assessment Report for New Territories South Animal Centre |
28 Sep 2012 25 Oct 2012 (Approved) |
EP Condition (EP-438/2012/K) |
Submission |
Submission date |
Condition 2.27 |
Operational Ground-borne Noise Mitigation
Measures Plan |
18 Mar 2016 (Batch
1 Version A submission) 28 Apr
2016 (Batch 1 Version B submission) 28 Apr
2016 (Batch 2 Version A submission) 1 Jun
2016 (Batch 1 Version C submission) 1 Jun
2016 (Batch 2 Version B submission) 23 Jun
2016 (Batch 1 Version D submission) 23 Jun
2016 (Batch 2 Version C submission) 15 Jul 2016
(Batch 1 Version D approved) 15 Jul
2016 (Batch 2 Version C approved) 15 Sep
2016 (Batch 3 Version A submission) 4 Oct
2016 (Batch 3 Version A approved) 8 Mar 2017 (Batch
4 Version A) 7 Apr
2017 (Batch 4 Version A approved) 7 Jun 2017 (Final) 20 Jul 2017 (Approved) |
Condition 2.28 |
As-built Drawings for Operational Ground- borne Noise Mitigation Measures |
10 Aug 2017 (1st submission) 15 Sep 2017
(Approved) |
Condition 2.30 |
As-built Drawings for
Operational Air-borne Noise
Mitigation Measures |
4 Dec 2015 (1st submission) 28 Dec 2015 (2nd submission) 4 Feb 2016 (Approved) 20 Mar 2018 (3rd submission) 18 Jul 2018 (Approved) 4 May 2018 (4th submission) 23 Jul 2018 (Approved) 20 Feb 2020 (5th submission) 17 Mar 2020 (Approved) |
Condition 2.31 |
Performance Test Report
for Train Noise
– Operational Airborne Railway and Ground- borne
Noise |
15 Nov
2018 (Batch 1 Version A submission) 30 Jan
2019 (Batch 2 Version A submission) 29 Mar 2019
(Batch 1 Version A & Batch 2 Version B submission) 15 April 2019 (Approved) |
Condition 2.32 |
Proposal for Updating Maximum
Allowable Sound Power Levels of Fixed Plant Sources |
30 Jan
2019 (Batch 1 Version A submission) 27 Feb
2019 (Batch 1 Version B submission) 13 Mar
2019 (Batch 1 Version B approved) 15 Mar
2019 (Batch 2 Version A submission) 8 Apr
2019 (Batch 2 Version A approved) 24 April 2019
(Batch 3 &
4 Version A submission) 21 May
2019 (Batch 3 Version B submission) 11 Jun 2019
(Batch 3 Version B & Batch 4 Version A approved) 21 Jun 2019 (Batch
5 Version A submission) |
EP Condition (EP-438/2012/K) |
Submission |
Submission date |
|
|
17 Jul 2019 (Batch
5 Version A approved) 19 Jul
2019 (Batch 6 Version A submission) 26 Jul
2019 (Batch 7 Version A submission) 29 Jul
2019 (Batch 6 Version A approved) 14 Aug 2019 (Batch
7 Version A approved) |
Condition 2.32 |
Fixed Plant Noise
Audit Report |
30 Jan
2019 (Batch 1 Version A submission) 15 Mar
2019 (Batch 1 Version B submission) 4 Apr
2019 (Batch 1 Version B approved) 16 Apr
2019 (Batch 2 Version A submission) 7 May
2019 (Batch 2 Version A approved) 24 Jun 2019
(Batch 3 Version A and Batch 4 Version A submission) 6 Jul 2019
(Batch 3 Version A and Batch 4 Version A approved) 2 Aug
2019 (Batch 5 Version A submission) 27 Aug
2019 (Batch 6 Version A submission) 29 Aug
2019 (Batch 7 Version A submission) 3 Sep
2019 (Batch 5 Version A approved) 13 Sep
2019 (Batch 6 Version B approved) 23 Sep
2019 (Batch 7 Version B submission) 11 Oct 2019 (Batch
7 Version B approved) |
Condition 2.33 |
As-built Drawings for Landscape and Visual Mitigation Measures |
4 Dec 2015 (1st submission) 28 Dec 2015 (2nd submission) 4 Feb 2016 (Approved) 22 Aug 2018 (3rd submission) 5 Nov 2018 (4th submission) 6 Sep 2019 (5th submission) 11 Sep 2019
(Approved) 27 Sep 2019 (6th submission) 21 Feb 2020 (7th submission) 17 Sep 2020 (8th submission) 4 Nov 2020 (9th submission) 18 Jan 2024 (10th submission) 26 Jun 2024 (11th submission) |
Condition 2.36 |
Contamination Assessment Plan (CAP) for the
Temporary Magazine Site
at TKO Area 137 |
23 Mar 2016
(1st submission) 20 Apr 2016 (2nd submission) 22 Apr 2016 (Approved) |
Condition 2.36 |
Contamination Assessment Report (CAR) for the Temporary Magazine Site
at TKO Area 137 |
19 May 2016
(1st submission) 3 Jun 2016 (2nd submission) 15 Jun 2016
(Approved) |
Condition 3.1 |
Proposal for Termination of Environmental
Monitoring and Audit (EM&A) Programme for Kai Tak Barging Point
Facilities |
7 Oct 2016 (Approved) |
EP Condition (EP-438/2012/K) |
Submission |
Submission date |
Condition 3.1 |
Proposal for Cessation of EM&A Works
at Hin Keng |
9 May 2018 (1st submission) 16 Jul 2018 (Approved) |
Condition 3.1 |
Proposal for Cessation of EM&A Programme at Diamond Hill Station |
25 Jul 2019 (1st submission) 31 Jul 2019 (Approved) |
Condition 3.1 |
Proposal for Cessation of EM&A Programme at Hung Hom North Approach Tunnels |
25 Jul 2019 (1st submission) 31 Jul 2019 (Approved) |
Condition 3.1 |
Proposal for Cessation of EM&A Programme at Stations and Tunnels of Kowloon City Section |
24 Aug 2020 (1st submission) 28 Aug 2020 (Approved) |
Condition 3.1 |
Proposal for Cessation of EM&A Programme at Hung Hom Station and Stabling Sidings |
21 Oct 2020 (1st
submission) 29 Oct 2020 (Approved) |
Condition 3.3 |
Baseline Monitoring Report (Works Contract 1109
- Stations and
Tunnels of Kowloon City
Section) |
27 Jul 2012 |
Condition 3.3 |
Baseline Monitoring Report (Works Contract 1108A
– Kai Tak
Barging Point Facilities) |
31 Jul 2012 |
Condition 3.3 |
Baseline Monitoring Report (Works Contracts 1103,
1106 and 1111
– Hin Keng to Diamond Hill Tunnels, Diamond Hill Station, and Hung Hom North Approach Tunnels) |
19 Oct 2012 |
Condition 3.4 |
Monthly Operational Airborne Rail Noise Monitoring Report (Festival City)
No. 1-6 |
Reported in previous Monthly EM&A Reports |
Condition 3.4 |
Monthly EM&A Reports No. 1-113 Monthly EM&A Report No.114 |
Reported in previous Monthly EM&A Reports 13 September 2024 |
Appendix A Monthly EM&A Report for SCL (TAW-HUH) and
SCL(MKK-HUH) – Pedestrian Link Connecting Pak Tai Street and Sung Wong Toi Station
Appendix B
Monthly EM&A
Report for
SCL (TAW-HUH)
and SCL(MKK-HUH) –
Re-provisioning of Ma Chai Hang Recreation Ground (Contract No. 11234)