MTR Corporation Limited

 

 

 

 

 

 

 

 

Shatin to Central Link

Tai Wai to Hung Hom Section and Mong Kok East to Hung Hom Section

 

Monthly EM&A Report No.115

 

[Period from 1 to 30 September 2024]


Table of Contents

 

Page

1                 INTRODUCTION................................................................................................. 2

1.1             Background............................................................................................. 2

1.2             Project Programme.................................................................................. 2

1.3             Purpose of the Report.............................................................................. 4

2                 ENVIRONMENTAL MONITORING AND AUDIT.................................................... 4

3                 IMPLEMENTATION STATUS ON THE ENVIRONMENTAL PROTECTION REQUIREMENTS

......................................................................................................................... 9

 

List of Tables

 

Table 1.1          Summary of Awarded Works Contracts

Table 2.1          Summary of Works Contracts and Respective EPs

Table 2.2          Summary of Major Construction Activities in the Reporting Period

Table 2.3          Summary of TSP Monitoring Results in the Reporting Period

Table 2.4          Summary of Construction Noise Monitoring Results in the Reporting Period

Table 2.5          Log for Environmental Complaints, Notification of Summons and Successful Prosecutions for the Reporting Month

Table 3.1          Summary of Status of Required Submissions for EP-437/2012/B

Table 3.2          Summary of Status of Required Submissions for EP-438/2012/L

 

 

List of Appendices

Appendix A       Monthly EM&A Report for SCL (TAW-HUH) and SCL (MKK-HUH) – Pedestrian Link Connecting Pak Tai Street and Sung Wong Toi Station (Contract No. 11286)

Appendix B       Monthly EM&A Report for SCL (TAW-HUH) and SCL (MKK-HUH) Re-provisioning of Ma Chai Hang Recreation Ground (Contract No. 11234)


1                 INTRODUCTION

1.1             Background

1.1.1        The Shatin to Central Link (SCL) is a 17km extension of the existing Ma On Shan Line (MOL) and East Rail Line (EAL) comprising (i) The East-West Corridor which extends the MOL from Tai Wai to Hung Hom via East Kowloon to connect with the West Rail Line (WRL) at Hung Hom Station (HUH) and Stabling Sidings at Hung Hom Freight Yard (HHS); and (ii) The North-South Corridor which is an extension of the East Rail Line (EAL) at Hung Hom across the harbour to Admiralty Station (ADM).

1.1.2        Shatin to Central Link – Tai Wai to Hung Hom Section [SCL (TAW-HUH)] and Shatin to Central Link Mong Kok East to Hung Hom Section [SCL (MKK-HUH) (hereafter referred to as “the Project”) are parts of the SCL. Shatin to Central Link – Stabling Sidings at Hung Hom Freight Yard [SCL (HHS)] is a proposed stabling sidings option for SCL (TAW – HUH) at the former freight yard in Hung Hom.

1.1.3        The Environmental Impact Assessment (EIA) Reports for SCL (TAW-HUH) (Register No.: AEIAR-167/2012), SCL (MKK-HUH) (Register No.: AEIAR-165/2012) and SCL

(HHS) (Register No.: AEIAR-164/2012) were approved on 17 February 2012 under the Environmental Impact Assessment Ordinance (EIAO). Following the approval of the EIA Reports, two Environmental Permits (EPs) were granted on 22 March 2012, one covers SCL (TAW-HUH) and SCL (HHS) (EP No: EP-438/2012) and the other covers SCL (MKK-HUH) and SCL (HHS) (EP No.: EP-437/2012), for their construction and operation. Variations of environmental permit (VEP) were subsequently applied for EP-438/2012 and EP-437/2012. The latest Environmental Permits (EP Nos.: EP-438/2012/L and EP- 437/2012/B) were issued by Director of Environmental Protection (DEP) on 14 August 2024 and 8 February 2024, respectively.

 

 

1.2             Project Programme

1.2.1        Thirteen civil construction works contracts of the Project have been awarded since July 2012. The construction of the Project commenced in September 2012. Table 1.1 summarises the information of the awarded Works Contracts. All major construction works under eleven out of thirteen civil construction works contracts have been completed.

Table 1.1          Summary of Awarded Works Contracts

Works Contract

Description

Construction Start Date

Contractor

Environmental Team

1101(1)

Ma On Shan Line Modification Works

 

December 2012

Sun Fook Kong

Joint Venture (SFKJV)

ANewR Consulting Ltd. (ANewR)

1102(6)

Hin Keng Station and Approach Structures

October 2013

Penta-Ocean

Construction Co. Ltd.

Wellab Limited (Wellab)

 

 

1103(7)

 

 

Hin Keng to Diamond Hill Tunnels

February 2013

Vinci Construction Grands Projets

Ove Arup & Partners Hong

Kong Ltd. (Arup)

October 2019

Wing Ho Yuen Landscaping Co.

Ltd.

MTR Co. Limited

1106(8)

Diamond Hill Station

March 2013

Leader Joint Venture

Cinotech

Consultants Ltd. (Cinotech)

1107(4)

Diamond Hill to Kai Tak Tunnels

May 2013

Chun Wo - SELI Joint Venture

Cinotech

Consultants Ltd. (Cinotech)


 

Works Contract

Description

Construction Start Date

Contractor

Environmental Team

1108(5)

Kai Tak Station and Associated Tunnels

June 2013

Kaden -Chun Wo Joint Venture

Environmental

Pioneers & Solutions Ltd.

 

1108A(2)

Kai Tak Barging Point Facilities

 

September 2012

Concentric Hong Kong River Joint Venture (CCL-

HKR JV)

Cinotech Consultants Ltd. (Cinotech)

 

1109(10)

Stations and Tunnels

of Kowloon City Section

September 2012

Samsung-Hsin

Chong JV (SSHCJV)

ERM-Hong Kong Limited (ERM)

1111(9)

Hung Hom North Approach Tunnels

January 2013

Gammon-Kaden SCL1111 JV

AECOM Asia Co. Ltd.

 

1112(11)

Hung Hom Station and Stabling Sidings

June 2013

Leighton

Contractors (Asia) Limited

SMEC Asia Ltd., HK

 

11240(3)

Excavation, Sorting and Disposal of Stockpiled Spoils to Approved Receptor

Site

 

October 2017

Crown Asia Engineering Limited (CAEL)

 

MTR Corporation Limited

 

11286

Pedestrian Link Connecting Pak Tai Street and Sung Wong

Toi Station

 

July 2023

Paul Y. Construction Co., Ltd.

ERM-Hong Kong Limited (ERM)

11234

Re-provisioning of Ma Chai Hang Recreation

Ground

March 2024

Build King Civil Engineering Ltd.

Fugro Technical Services Ltd.

Notes:

(1)       All construction works (works areas at Tai Wai Mei Tin Road and the offsite temporary storage areas) under Works Contract 1101 were completed on 29 February 2016.

(2)       All construction works (Kai Tak Barging Point Facilities) under Works Contract 1108A were completed on 29 September 2016.

(3)       All construction works (Excavation, Sorting and Disposal of Stockpiled Spoils to Approved Receptor Site) under Works Contract 11240 were completed on 3 January 2018.

(4)       All construction works (Diamond Hill to Kai Tak Tunnels) under Works Contract 1107 were completed on 22 February 2018.

(5)       All construction works (Kai Tak Station and associated tunnels) under Works Contract 1108 were completed in July 2018.

(6)       All construction works (Hin Keng Station and Approach Structures) under Works Contract 1102 were completed in December 2018. The Environmental Team was taken over by Wellab Limited starting from 1 January 2019.

(7)       All construction works (Hin Keng to Diamond Hill Tunnels) under Works Contract 1103 were completed in June 2019. Minor landscaping works at Fung Tak had been commenced in mid- October and all the works were completed at the end of October 2019.

(8)       All construction works (Diamond Hill Station) under Works Contract 1106 with significant environmental impacts were substantially completed by 25 June 2019.

(9)       All major construction works (Hung Hom North Approach Tunnels) under Works Contract 1111 have been substantially completed since 18 November 2018.

(10)    All construction works (Stations and Tunnels of Kowloon City Section) under Works Contract 1109 have been substantially completed on 12 August 2020.

(11)    All major construction works (Hung Hom Station and Stabling Sidings) under Works Contract 1112 have been substantially completed by 17 September 2020.

 

1.2.2        All major construction works for SCL (TAW-HUH) and SCL (HHS) which were covered by EP No. EP-438/2012/L had been completed. The remaining works, including (1) the re-provision of recreational facilities at Ma Chai Hang and (2) a pedestrian link connecting Sung Wong Toi Station to Pak Tai Street, have been carried out by other works contracts in 2023 -2024 resulting in the liaison with Railway Development Office (RDO), relevant government departments and stakeholders. Apart from the above, the remaining tree


planting works at Kai Tak Station Square (Phase 2) which have been scheduled after the full opening of SCL were completed.

1.2.3        All major construction works for SCL (MKK-HUH) and SCL (HHS) which were covered by EP No. EP-437/2012/B had been completed. Apart from that, those proposed additional tree seedlings at the trackside in Hung Hom and the remaining planting works of additional tree seedlings and Kai Tak Station Square (Phase 1) which were carried out at a later stage in 2023 were completed.

 

1.3             Purpose of the Report

1.3.1        The Environmental Monitoring and Audit (EM&A) programme for the Project commenced in September 2012. This is the one hundred and thirteenth EM&A Report for the Project which summarises the EM&A works undertaken during the period from 1 to 30 September 2024.

 

2                 ENVIRONMENTAL MONITORING AND AUDIT

2.1.1        The construction of SCL has been divided into different civil construction works contracts which are covered by EP No. EP-437/2012/B and/or EP-438/2012/L. As per the EP Conditions, EM&A Reports for the works contracts as shown in the table below have been prepared by the respective Contractor’s ETs.

Table 2.1          Summary of Works Contracts and Respective EPs

Works Contract

Contract Title

Works Covered in Environmental Permit No.

1101

Ma On Shan Modification Works

EP-438/2012/L

1102

Hin Keng Station and Approach Structures

EP-438/2012/L

1103

Hin Keng to Diamond Hill Tunnels

EP-438/2012/L

1106

Diamond Hill Station

EP-438/2012/L

1107

Diamond Hill to Kai Tak Tunnels

EP-438/2012/L

1108

Kai Tak Station and Associated Tunnels

EP-438/2012/L

1108A

Kai Tak Barging Point Facilities

EP-438/2012/L

1109

Stations and Tunnels of Kowloon City Section

EP-438/2012/L

1111

Hung Hom North Approach Tunnels

EP-437/2012/B & EP-438/2012/L

1112

Hung Hom Station and Stabling Sidings

EP-437/2012/B & EP-438/2012/L

 

11240

Excavation, Sorting and Disposal of

Stockpiled Spoils to Approved Receptor Site

EP-438/2012/L

11286

Pedestrian Link Connecting Pak Tai Street and Sung Wong Toi Station

EP-438/2012/L

11234

Re-provisioning of Ma Chai Hang Recreation Ground

EP-438/2012/L

 

2.1.2        The EM&A Reports for Works Contract Nos. 11286 (a pedestrian link connecting Sung Wong Toi Station to Pak Tai Street) and 11234 (the re-provision of recreational facilities at Ma Chai Hang) prepared by the respective Contractor’s ETs are provided in Appendix A and Appendix B respectively. The EM&A Report provide details of the project information, EM&A requirements, impact monitoring and audit results for the corresponding Contracts.


2.1.3        A summary of the major construction activities undertaken by the respective Contractors of various Works Contracts during the reporting period are presented in Table 2.2.

Table 2.2          Summary of Major Construction Activities in the Reporting Period

Works

Contract

Site

Construction Activities

 

 

 

11286

 

 

Works in Sung Wong Toi

(SUW) (formerly named as To Kwa Wan (TKW))

Near Sung Wong Toi Exit D (W1)

            ELS

            Pile cap works

            Grout curtain works

            On-site fabrication of Footbridge

 

 

Near Pak Tai Street (H2)

            Socket H pile

 

11234

Re-provisioning of Ma Chai Hang Recreation Ground

            Site Clearance

            Construction of football pitch fence footing

 

2.1.4        Impact monitoring for air quality and construction noise were conducted in accordance with the EM&A Manual in the reporting period under Works Contract 11286. Continuous noise monitoring was not required in the reporting period for the Works Contracts according to the Continuous Noise Monitoring Plan (CNMP). The air quality and construction noise for this reporting period are summarised in Tables 2.3 and 2.4. Details of the monitoring requirements, locations, equipment, methodology and QA/QC procedures are presented in the EM&A Reports as provided in Appendices A.

2.1.5        No environmental complaint; no exceedance of action and limit levels; and no notification of summons or successful prosecutions was received during this reporting period. Log for environmental complaints, notification of summons and successful prosecutions are provided in Table 2.5.

2.1.6        Regular site inspections were conducted by the respective ETs (both Works Contract Nos. 11286 and 11234) on a weekly basis to check the implementation of environmental pollution control and mitigation measures for the Project. No non-conformance was identified in the reporting period.


Table 2.3          Summary of TSP Monitoring Results in the Reporting Period

 

Monitoring Station ID

 

Location

TSP

Concentration (mg/m3)

Action Level (mg/m3)

Limit Level (mg/m3)

Exceedance due to the Project

Construction (Yes/ No/ N/A)

Works Contracts 1102 and 1103

DMS-1(10)

C.U.H.K.A.A. Thomas

Cheung School

N/A

148.7

260

N/A

Works Contract 1103

DMS-2(11)

Price Memorial Catholic Primary School

N/A

167.4

260

N/A

Works Contracts 1103 and 1106

DMS-3(12)

Hong Kong S.K.H Nursing Home (1)

N/A

159.1

260

N/A

Works Contract 1106(9)

DMS-4(12)

Block 1, Rhythm Garden

N/A

160.4

260

N/A

Works Contract 1108 (4)

Works Contract 1109

DMS-6

Katherine Building (2)

N/A

156.8

260

N/A

DMS-8

SKH Good Shepherd Primary School

N/A

152.2

260

N/A

DMS-9

No. 12 Pau Chung

Street (3)(8)

N/A

160.9

260

N/A

DMS-10

Chat Ma Mansion

N/A

170.4

260

N/A

Works Contract 1111

AM1(5)(13)

No. 234 238 Chatham

Road North (6)

N/A

183.9

260

N/A

Works Contract 1112

AM2

Site Boundary of Finger

Pier Adjacent to Harbourfront Horizon (7)

N/A

182

260

N/A

Works Contract 11240 (4)

Works Contract 11286

DMS-7 (14)

Sky Tower - Tower 2

20-52

166.7

260

No

Notes:

(1)       Alternative monitoring location to Shek On House

(2)       Alternative monitoring location to Prosperity House

(3)       Alternative monitoring location to Lucky Building

(4)       No TSP monitoring is required under this contract

(5)       AM1 named as HUH-1-3 in SCL(TAW-HUH) and SCL(HHS) EIA Reports.

(6)       Alternative monitoring location to Wing Fung Building

(7)       Alternative monitoring location to Harbourfront Horizon

(8)       Alternative monitoring location of No. 26 Kowloon City Road

(9)       The 24-hour TSP monitoring works would be taken up by Works Contract 1106 since the completion of Works Contract 1107 in Feb 2018.

(10)    The cessation of monitoring works at DMS-1 was approved by EPD and the last monitoring was conducted on 16 Jul 2018.

(11)    The temporary cessation of monitoring works at DMS-2 was approved by EPD in end-June 2019. The last monitoring date was 27 June 2019.

(12)    The cessation of monitoring works at DMS-3 and DMS-4 was approved by EPD on 31 Jul 2019. The last monitoring was conducted on 30 Jul 2019.

(13)    The cessation of monitoring works at AM1 was proposed on 25 Jul 2019 and EPD expressed no objection on 31 Jul 2019.

(14)    ET has obtained the permission from Sky Tower to deploy the High-Volume Sampler (HVS) at the location same as the originally proposed dust monitoring location of DMS-7 in the approved EM&A Manual for SCL (TAW HUH). 24-hour TSP thus has been conducted at Sky Tower - Tower 2 (podium level) since 27 October 2023.


Table 2.4          Summary of Construction Noise Monitoring Results in the Reporting Period

Monitoring Station ID

Location

Noise Level (LAeq,30mins, dB(A))

Limit Level (dB(A))

Exceedance due to the

Project Construction (Yes/No/N/A)

Measured

Baseline

Corrected (7)

Works Contracts 1102 and 1103

NMS-CA-1(12)

C.U.H.K.A.A. Thomas Cheung School

N/A

57.0

N/A

70

(65 during examination period)

N/A

Works Contract 1103

NMS-CA-2(13)

Price Memorial Catholic Primary School

N/A

66.0

N/A

70

(65 during examination period)

N/A

Works Contracts 1103 and 1106

NMS-CA-3(14)

Hong Kong S.K.H Nursing Home (1)

N/A

73.0

N/A

70

N/A

Works Contracts 1106(11)

NMS-CA-4(14)

Block 1, Rhythm Garden (north- eastern façade)

N/A

71.0

N/A

75

N/A

NMS-CA-5(14)

Block 1, Rhythm Garden (northern façade) (2)

N/A

74.0

N/A

70

(65 during examination period)

N/A

Works Contract 1108 (6)

Works Contract 1109

NMS-CA-6

No. 16-23 Nam Kok Road (3)

N/A

76.1

N/A

75

N/A

 

NMS-CA-8

 

SKH Good Shepherd Primary School

 

N/A

 

75.4

 

N/A

70

(65 during examination period) (79 during the period of conducting the continuous

noise monitoring) (8)

 

N/A

NMS-CA-9

Kong Yiu Mansion (4)

N/A

69.2

N/A

75

N/A

NMS-CA-10

Chat Ma Mansion

N/A

76.6

N/A

75

N/A

Works Contract 1111

 

 

NM1(15)

 

Carmel Secondary School (South Block)

 

N/A

 

68.0

 

N/A

70

(65 during examination period) (68 during the period of conducting the continuous

noise monitoring) (9)

 

N/A

NM2(15)

No. 234 238 Chatham Road

North (5)

N/A

79.0

N/A

75 (77) (10)

N/A

Works Contract 1112 (6)

Works Contract 11240 (6)


 

Monitoring Station ID

Location

Noise Level (LAeq,30mins, dB(A))

Limit Level (dB(A))

Exceedance due to the Project Construction (Yes/No/N/A)

Measured

Baseline

Corrected (7)

Works Contract 11286

NMS-CA-7

Sky Tower - Tower 2

67.9 68.9

70.0

< Baseline

75

No

Notes:

(1)       Alternative monitoring location to Shek On House.

(2)       Alternative monitoring location to Canossa Primary School (San Po Kong).

(3)       Alternative monitoring location to Prosperity House.

(4)       Alternative monitoring location to Lucky Building.

(5)       Alternative monitoring location to Wing Fung Building.

(6)       No construction noise monitoring is required under this contract.

(7)       The measured noise levels are corrected against the corresponding baseline noise levels.

(8)      The Limit Level of 79 dB(A) was updated on 22 Aug 2013 as per the latest Construction Noise Mitigation Measures Plan (CNMMP) and Continuous Noise Monitoring Plan (CNMP) which were approved by EPD.

(9)      The Limit of 68 dB(A) was updated on 20 Jan 2014 as per the latest CNMMP and CNMP which were approved by EPD.

(10)    Daytime noise Limit Level of 77 dB(A) applies during the continuous noise monitoring period.

(11)    The construction noise monitoring works would be taken up by Works Contract 1106 since the completion of Works Contract 1107 in Feb 2018.

(12)    The cessation of monitoring works at NMS-CA-1 was approved by EPD and the last monitoring was conducted on 17 Jul 2018.

(13)    The temporary cessation of monitoring works at NMS-CA-2 was approved by EPD in end-June 2019. The last monitoring date was 24 Jun 2019.

(14)    The cessation of monitoring works at NMS-CA-3, NMS-CA-4 and NMS-CA-5 was approved by EPD on 31 Jul 2019. The last monitoring proposed on 31 Jul 2019 was rescheduled to 1 Aug 2019 due to adverse weather and the hoist of Typhoon Signal No.8 (Typhoon “Wipha”).

(15)    The cessation of monitoring works at NM1 and NM2 were proposed on 25 Jul 2019 and EPD expressed no objection on 31 Jul 2019.


Table 2.5          Log for Environmental Complaints, Notification of Summons and Successful Prosecutions for the Reporting Month

 

Works Contract

Environmental Complaints

Notification of Summons

Successful Prosecutions

11286

0

0

0

11234

0

0

0

 

3                 IMPLEMENTATION STATUS ON THE ENVIRONMENTAL PROTECTION REQUIREMENTS

 

3.1.1 The respective Contractors have implemented all mitigation measures and requirements as stated in the EIA Reports, EM&A Manuals and EPs (EP-437/2012/B and EP- 438/2012/K). The status of required submissions under the EPs as of the reporting period are summarised in Tables 3.1 and 3.2.

Table 3.1      Summary of Status of Required Submissions for EP-437/2012/B

EP Condition (EP-437/2012/B)

Submission

Submission date

Condition 1.11

Notification of Commencement Date of Construction of the Project

30 Nov 2012

Condition 2.3

Notification of Information of Community Liaison Groups

30 Nov 2012

Condition 2.5

Management Organisation of Main Construction Companies

19 Dec 2012 (1st submission)

30 Apr 2013 (2nd submission)

Condition 2.6

Construction Programme and EP

Submission Schedule

19 Dec 2012

 

 

Condition 2.7

 

 

Construction Noise Mitigation Measures Plan (CNMMP)

30 Nov 2012 (1st submission)

8 Feb 2013 (Approved)

26 Apr 2013 (2nd submission)

11 Jun 2013 (3rd submission)

27 Aug 2013 (Approved)

20 Jan 2014 (4th submission)

28 Apr 2016 (Approved)

 

Condition 2.8

 

Continuous Noise Monitoring Plan (CNMP)

30 Nov 2012 (1st submission)

11 Jan 2013 (2nd submission)

8 Feb 2013 (Approved)

20 Jan 2014 (3rd submission)

28 Apr 2016 (Approved)

Condition 2.9

Construction and Demolition Materials Management Plan (C&DMMP)

6 Jul 2012 (1st submission)

12 Sep 2012 (2nd submission)

15 Oct 2012 (Approved)

 

Condition 2.10

 

Sediment Management Plan

6 Jul 2012 (1st submission)

12 Sep 2012 (2nd submission)

5 Oct 2012 (3rd submission)

15 Oct 2012 (Approved)

 

 

 

Condition 2.11

 

 

Visual, Landscape, Tree Planting & Tree Protection Plan (VLTTP)

14 Nov 2012 (1st submission)

8 Feb 2013 (2nd submission)

4 Feb 2015 (3rd submission)

26 Jun 2015 (4th submission)

12 May 2017 (5th submission)

17 Apr 2018 (6th submission)

17 Apr 2019 (7th submission)

9 Apr 2020 (8th submission)

 

Condition 2.14

As-built drawing(s) of Measures for Mitigating Landscape and Visual Impact and Tree Planting

23 August 2021 (1st submission)

23 March 2022 (2nd submission)

18 Jan 2024 (3rd submission)

26 Jun 2024 (Approved)

 

Condition 2.16

Operational Ground-borne Noise Mitigation Measures Plan

23 Mar 2017 (1st submission)

17 May 2017 (2nd submission)

28 Jun 2017 (3rd submission)

20 Jul 2017 (Approved)

Condition 2.19

As-built drawing(s) for Operation Air-borne Noise Mitigation Measure

10 Jan 2018 (1st submission)

9 Feb 2018 (Approved)


 

EP Condition (EP-437/2012/B)

Submission

Submission date

 

Condition 2.21

Proposal for Updating Maximum Allowable Sound Power Levels of Fixed Plant Sources

26 Jul 2019 (Batch 1 Version A

submission)

14 Aug 2019 (Batch 1 Version A approved)

Condition 2.21

Fixed Plant Noise Audit Report

29 Aug 2019 (Batch 1 Version A submission)

11 Oct 2019 (Approved)

Condition 3.1

Proposal for Cessation of EM&A

Programme at Hung Hom North Approach Tunnels

25 Jul 2019 (1st submission)

31 Jul 2019 (Approved)

Condition 3.1

Proposal for Cessation of EM&A Programme at Hung Hom Station and

Stabling Sidings

21 Oct 2020 (1st submission)

29 Oct 2020 (Approved)

 

 

Condition 3.3

Baseline Monitoring Report (Works Contracts 1103, 1106 and 1111 Hin Keng to Diamond Hill Tunnels, Diamond Hill Station, and Hung Hom North Approach

Tunnels)

 

 

19 Oct 2012

Condition 3.4

Monthly EM&A Reports No. 5-99

Reported in previous Monthly EM&A Reports

Condition 3.4

Final EM&A Review Report

15 Jan 2024 (1st submission)

 

 

Table 3.2          Summary of Status of Required Submissions for EP-438/2012/L

EP Condition

(EP-438/2012/K)

Submission

Submission date

Condition 1.12

Notification of Commencement Date of

Construction of the Project

1 Aug 2012

Condition 2.3

Notification of Information of Community Liaison Groups

13 Jul 2012 (1st submission)

31 Aug 2012 (2nd submission)

30 Nov 2012 (3rd submission)

 

 

Condition 2.7

 

Management Organisation of Main Construction Companies

27 Jul 2012 (1st submission)

21 Aug 2012 (2nd submission)

19 Dec 2012 (3rd submission)

22 Jan 2013 (4th submission)

30 Apr 2013 (5th submission)

21 May 2013 (6th submission)

Condition 2.8

Construction Programme and EP

Submission Schedule

27 Jul 2012

 

 

 

 

 

 

 

 

 

Condition 2.9

 

 

 

 

 

 

 

 

Construction Noise Mitigation Measures Plan (CNMMP)

1 Aug 2012 (1st submission)

28 Sep 2012 (2nd submission)

30 Nov 2012 (3rd submission)

11 Jan 2013 (4th submission)

8 Feb 2013 (Approved)

8 Feb 2013 (5th submission)

26 Apr 2013 (6th submission)

11 Jun 2013 (7th submission)

12 Jul 2013 (Approved)

26 Jul 2013 (8th submission)

22 Aug 2013 (Approved)

23 Aug 2013 (9th submission)

13 Sep 2013 (Approved)

20 Jan 2014 (10th submission)

26 Feb 2014 (Approved)

31 Mar 2015 (Contract 1106 submission only)

13 Apr 2015 (Contract 1106 submission only)

15 Apr 2015 (Approved)


 

EP Condition (EP-438/2012/K)

Submission

Submission date

 

 

 

 

 

 

 

Condition 2.10

 

 

 

 

 

 

 

Continuous Noise Monitoring Plan (CNMP)

1 Aug 2012 (1st submission)

28 Sep 2012 (2nd submission)

30 Nov 2012 (3rd submission)

11 Jan 2013 (4th submission)

8 Feb 2013 (Approved)

8 Feb 2013 (5th submission)

26 Apr 2013 (6th submission)

11 Jun 2013 (7th submission)

12 Jul 2013 (Approved)

26 Jul 2013 (8th submission)

22 Aug 2013 (Approved)

23 Aug 2013 (9th submission)

13 Sep 2013 (Approved)

20 Jan 2014 (10th submission)

26 Feb 2014 (Approved)

7 Oct 2014 (11th submission)

23 Oct 2014 (Approved)

Condition 2.11

Construction and Demolition Materials Management Plan (C&DMMP)

6 Jul 2012 (1st submission)

12 Sep 2012 (2nd submission)

10 Oct 2012 (Approved)

 

 

 

Condition 2.12

 

 

 

Sediment Management Plan

6 Jul 2012 (1st submission)

12 Sep 2012 (2nd submission)

5 Oct 2012 (3rd submission)

10 Oct 2012 (Approved)

4 Mar 2013 (4th submission)

9 May 2013 (5th submission)

24 Jul 2013 (6th submission)

26 Jul 2013 (Approved)

 

 

 

 

 

 

 

Condition 2.13

 

 

 

 

 

 

Visual, Landscape, Tree Planting & Tree Protection Plan

6 Jul 2012 (1st submission)

30 Aug 2012 (2nd submission)

3 Oct 2012 (3rd submission)

13 Nov 2013 (Approved)

14 Nov 2012 (4th submission)

8 Feb 2013 (5th submission)

18 Mar 2013 (6th submission)

18 Jun 2013 (7th submission)

12 Jul 2013 (Approved)

23 Mar 2017 (8th submission)

7 Mar 2018 (9th submission)

30 Jul 2018 (10th submission)

28 Feb 2019 (11th submission)

5 Mar 2019 (12th submission)

29 May 2019 (13th submission)

19 Jul 2019 (Approved)

 

Condition 2.14

Transplantation Proposal for Plant Species of Conservation Importance

22 Aug 2012 (1st submission)

5 Oct 2012 (2nd submission)

26 Nov 2012 (3rd submission)

4 Dec 2012 (Approved)

Condition 2.15

Conservation Plan

31 Jan 2013 (1st submission)

18 Mar 2013 (2nd submission)

24 Apr 2013 (Approved)

 

 

Condition 2.16

 

Archaeological Action Plan(s) (AAP(s)) for Works Contract 1109

10 Aug 2012 (1st submission)

3 Sep 2012 (2nd submission)

21 Sep 2012 (Approved)

11 Oct 2013 (3rd submission)

1 Nov 2013 (Approved)

Condition 2.16

Archaeological Action Plan(s) (AAP(s)) for Works Contract 1106

29 Jan 2013 (1st submission)

19 Mar 2013 (2nd submission)

8 Apr 2013 (Approved)

Condition 2.23

Supplementary Contamination Assessment

Report for New Territories South Animal Centre

28 Sep 2012

25 Oct 2012 (Approved)


 

EP Condition (EP-438/2012/K)

Submission

Submission date

 

 

 

 

 

 

 

 

 

 

 

 

Condition 2.27

 

 

 

 

 

 

 

 

 

 

 

 

Operational Ground-borne Noise Mitigation Measures Plan

18 Mar 2016 (Batch 1 Version A

submission)

28 Apr 2016 (Batch 1 Version B submission)

28 Apr 2016 (Batch 2 Version A submission)

1 Jun 2016 (Batch 1 Version C submission)

1 Jun 2016 (Batch 2 Version B submission)

23 Jun 2016 (Batch 1 Version D submission)

23 Jun 2016 (Batch 2 Version C submission)

15 Jul 2016 (Batch 1 Version D approved)

15 Jul 2016 (Batch 2 Version C approved)

15 Sep 2016 (Batch 3 Version A submission)

4 Oct 2016 (Batch 3 Version A approved)

8 Mar 2017 (Batch 4 Version A)

7 Apr 2017 (Batch 4 Version A approved)

7 Jun 2017 (Final)

20 Jul 2017 (Approved)

Condition 2.28

As-built Drawings for Operational Ground- borne Noise Mitigation Measures

10 Aug 2017 (1st submission)

15 Sep 2017 (Approved)

 

 

 

Condition 2.30

 

 

 

As-built Drawings for Operational Air-borne Noise Mitigation Measures

4 Dec 2015 (1st submission)

28 Dec 2015 (2nd submission)

4 Feb 2016 (Approved)

20 Mar 2018 (3rd submission)

18 Jul 2018 (Approved)

4 May 2018 (4th submission)

23 Jul 2018 (Approved)

20 Feb 2020 (5th submission)

17 Mar 2020 (Approved)

 

 

 

Condition 2.31

 

 

Performance Test Report for Train Noise – Operational Airborne Railway and Ground- borne Noise

15 Nov 2018 (Batch 1 Version A submission)

30 Jan 2019 (Batch 2 Version A submission)

29 Mar 2019 (Batch 1 Version A & Batch 2 Version B submission)

15 April 2019 (Approved)

 

 

 

 

 

 

 

 

Condition 2.32

 

 

 

 

 

 

 

Proposal for Updating Maximum Allowable Sound Power Levels of Fixed Plant Sources

30 Jan 2019 (Batch 1 Version A submission)

27 Feb 2019 (Batch 1 Version B submission)

13 Mar 2019 (Batch 1 Version B approved)

15 Mar 2019 (Batch 2 Version A submission)

8 Apr 2019 (Batch 2 Version A approved)

24 April 2019 (Batch 3 & 4 Version A submission)

21 May 2019 (Batch 3 Version B submission)

11 Jun 2019 (Batch 3 Version B & Batch 4 Version A approved) 21 Jun 2019 (Batch 5 Version A

submission)


 

EP Condition (EP-438/2012/K)

Submission

Submission date

 

 

17 Jul 2019 (Batch 5 Version A

approved)

19 Jul 2019 (Batch 6 Version A submission)

26 Jul 2019 (Batch 7 Version A submission)

29 Jul 2019 (Batch 6 Version A approved)

14 Aug 2019 (Batch 7 Version A approved)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Condition 2.32

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Fixed Plant Noise Audit Report

30 Jan 2019 (Batch 1 Version A submission)

15 Mar 2019 (Batch 1 Version B submission)

4 Apr 2019 (Batch 1 Version B approved)

16 Apr 2019 (Batch 2 Version A submission)

7 May 2019 (Batch 2 Version A approved)

24 Jun 2019 (Batch 3 Version A and Batch 4 Version A submission)

6 Jul 2019 (Batch 3 Version A and Batch 4 Version A approved)

2 Aug 2019 (Batch 5 Version A submission)

27 Aug 2019 (Batch 6 Version A submission)

29 Aug 2019 (Batch 7 Version A submission)

3 Sep 2019 (Batch 5 Version A approved)

13 Sep 2019 (Batch 6 Version B approved)

23 Sep 2019 (Batch 7 Version B submission)

11 Oct 2019 (Batch 7 Version B approved)

 

 

 

 

 

Condition 2.33

 

 

 

 

 

As-built Drawings for Landscape and Visual Mitigation Measures

4 Dec 2015 (1st submission)

28 Dec 2015 (2nd submission)

4 Feb 2016 (Approved)

22 Aug 2018 (3rd submission)

5 Nov 2018 (4th submission)

6 Sep 2019 (5th submission)

11 Sep 2019 (Approved)

27 Sep 2019 (6th submission)

21 Feb 2020 (7th submission)

17 Sep 2020 (8th submission)

4 Nov 2020 (9th submission)

18 Jan 2024 (10th submission)

26 Jun 2024 (11th submission)

 

Condition 2.36

Contamination Assessment Plan (CAP) for the Temporary Magazine Site at TKO Area 137

23 Mar 2016 (1st submission)

20 Apr 2016 (2nd submission)

22 Apr 2016 (Approved)

 

Condition 2.36

Contamination Assessment Report (CAR) for the Temporary Magazine Site at TKO

Area 137

19 May 2016 (1st submission)

3 Jun 2016 (2nd submission)

15 Jun 2016 (Approved)

 

Condition 3.1

Proposal for Termination of Environmental Monitoring and Audit (EM&A) Programme for Kai Tak Barging Point Facilities

7 Oct 2016 (Approved)


 

EP Condition (EP-438/2012/K)

Submission

Submission date

Condition 3.1

Proposal for Cessation of EM&A Works at

Hin Keng

9 May 2018 (1st submission)

16 Jul 2018 (Approved)

Condition 3.1

Proposal for Cessation of EM&A Programme at Diamond Hill Station

25 Jul 2019 (1st submission)

31 Jul 2019 (Approved)

 

Condition 3.1

Proposal for Cessation of EM&A Programme at Hung Hom North Approach Tunnels

25 Jul 2019 (1st submission)

31 Jul 2019 (Approved)

 

Condition 3.1

Proposal for Cessation of EM&A Programme at Stations and Tunnels of Kowloon City Section

24 Aug 2020 (1st submission)

28 Aug 2020 (Approved)

 

Condition 3.1

Proposal for Cessation of EM&A Programme at Hung Hom Station and Stabling Sidings

21 Oct 2020 (1st submission)

29 Oct 2020 (Approved)

 

Condition 3.3

Baseline Monitoring Report (Works Contract 1109 - Stations and Tunnels of Kowloon City Section)

27 Jul 2012

Condition 3.3

Baseline Monitoring Report (Works

Contract 1108A Kai Tak Barging Point Facilities)

31 Jul 2012

 

Condition 3.3

Baseline Monitoring Report (Works Contracts 1103, 1106 and 1111 Hin Keng to Diamond Hill Tunnels, Diamond Hill

Station, and Hung Hom North Approach Tunnels)

19 Oct 2012

Condition 3.4

Monthly Operational Airborne Rail Noise Monitoring Report (Festival City) No. 1-6

Reported in previous Monthly EM&A Reports

 

Condition 3.4

Monthly EM&A Reports No. 1-113

 

 

Monthly EM&A Report No.114

Reported in previous Monthly EM&A Reports

 

13 September 2024


Appendix A

 

Monthly EM&A Report for

 

SCL (TAW-HUH) and SCL(MKK-HUH)

 

Pedestrian Link Connecting Pak Tai Street and Sung Wong

 

Toi Station

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 



 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Appendix B

 

Monthly EM&A Report for

SCL (TAW-HUH) and SCL(MKK-HUH)

Re-provisioning of Ma Chai Hang Recreation Ground (Contract No. 11234)