Table of Contents
2......... Environmental Monitoring and
Audit
3......... implementation status on the
environmental protection requirements
List of Tables
Table 1.1 Summary of Awarded Works Contracts
Table 2.1 Summary of Works Contracts and Respective EPs
Table 2.2 Summary of Major Construction Activities in the Reporting Period
Table 2.3 Summary of TSP Monitoring Results in the Reporting Period
Table 2.4 Summary of Construction Noise Monitoring Results in the Reporting Period
Table 3.1 Summary of Status of Required Submissions for EP-437/2012/A
Table 3.2 Summary of Status of Required Submissions for EP-438/2012/K
List of Appendices
Table 1.1 Summary of Awarded Works Contracts
Works Contract |
Description |
Construction Start Date |
Contractor |
Environmental Team |
1101(1) |
Ma
On Shan Line Modification Works |
December
2012 |
Sun
Fook Kong Joint Venture (SFKJV) |
ANewR
Consulting Ltd. (ANewR) |
1102(6) |
Hin
Keng Station and Approach Structures |
October
2013 |
Penta-Ocean
Construction Co. Ltd. |
Wellab Limited (Wellab) |
1103(7) |
Hin
Keng to Diamond Hill Tunnels |
February
2013 |
Vinci
Construction Grands Projets |
Ove
Arup & Partners Hong Kong Ltd. (Arup) |
October
2019 |
Wing
Ho Yuen Landscaping Co. Ltd. |
MTR
Co. Limited |
||
1106(8) |
Diamond
Hill Station |
March
2013 |
Leader
Joint Venture |
Cinotech Consultants Ltd. (Cinotech) |
1107(4) |
Diamond
Hill to Kai Tak Tunnels |
May
2013 |
Chun
Wo - SELI Joint Venture |
Cinotech Consultants Ltd. (Cinotech) |
1108(5) |
Kai
Tak Station and Associated Tunnels |
June
2013 |
Kaden
-Chun Wo Joint Venture |
Environmental
Pioneers & Solutions Ltd. |
1108A(2) |
Kai
Tak Barging Point Facilities |
September
2012 |
Concentric
– Hong Kong River Joint Venture (CCL-HKR JV) |
Cinotech Consultants Ltd. (Cinotech) |
1109(10) |
Stations
and Tunnels of Kowloon City Section |
September
2012 |
Samsung-Hsin
Chong JV (SSHCJV) |
ERM-Hong
Kong Limited (ERM) |
1111(9) |
Hung
Hom North Approach Tunnels |
January
2013 |
Gammon-Kaden
SCL1111 JV |
AECOM
Asia Co. Ltd. |
1112(11) |
Hung
Hom Station and Stabling Sidings |
June
2013 |
Leighton
Contractors (Asia) Limited |
SMEC
Asia Ltd., HK |
11240(3) |
Excavation,
Sorting and Disposal of Stockpiled Spoils to Approved Receptor Site |
October
2017 |
Crown
Asia Engineering Limited (CAEL) |
MTR
Co. Limited |
11286 |
Pedestrian
Link Connecting Pak Tai Street and Sung Wong Toi Station |
17
July 2023 |
Paul
Y. Engineering |
ERM-Hong
Kong Limited (ERM) |
Notes:
(1) All
construction works (works areas at Tai Wai Mei Tin Road and the offsite
temporary storage areas) under Works Contract 1101 were completed on 29
February 2016.
(2) All
construction works (Kai Tak Barging Point Facilities) under Works Contract
1108A were completed on 29 September 2016.
(3) All
construction works (Excavation, Sorting and Disposal of Stockpiled Spoils to
Approved Receptor Site) under Works Contract 11240 were completed on 3 January
2018.
(4) All
construction works (Diamond Hill to Kai Tak Tunnels) under Works Contract 1107
were completed on 22 February 2018.
(5) All
construction works (Kai Tak Station and associated tunnels) under Works
Contract 1108 were completed in July 2018.
(6) All
construction works (Hin Keng Station and Approach Structures) under Works
Contract 1102 were completed in December 2018. The Environmental Team was taken
over by Wellab Limited starting from 1 January 2019.
(7) All
construction works (Hin Keng to Diamond Hill Tunnels) under Works Contract 1103
were completed in June 2019. Minor landscaping works at Fung Tak had been
commenced in mid-October and all the works were completed at the end of October
2019.
(8) All
construction works (Diamond Hill Station) under Works Contract 1106 with
significant environmental impacts were substantially completed by 25 June 2019.
(9) All
major construction works (Hung Hom North Approach Tunnels) under Works Contract
1111 have been substantially completed since 18 November 2018.
(10) All construction works (Stations
and Tunnels of Kowloon City Section) under Works Contract 1109 have been
substantially completed on 12 August 2020.
(11) All major construction works
(Hung Hom Station and Stabling Sidings) under Works Contract 1112 have been
substantially completed by 17 September 2020.
Table 2.1 Summary of Works Contracts and Respective EPs
Works
Contract |
Contract
Title |
Works
Covered in Environmental Permit No. |
1101 |
Ma On
Shan Modification Works |
|
1102 |
Hin Keng
Station and Approach Structures |
|
1103 |
Hin Keng
to Diamond Hill Tunnels |
|
1106 |
Diamond
Hill Station |
|
1107 |
Diamond
Hill to Kai Tak Tunnels |
|
1108 |
Kai Tak
Station and Associated Tunnels |
|
1108A |
Kai Tak
Barging Point Facilities |
|
1109 |
Stations
and Tunnels of Kowloon City Section |
|
1111 |
Hung Hom
North Approach Tunnels |
EP-437/2012/A
& EP-438/2012/K |
1112 |
Hung Hom
Station and Stabling Sidings |
EP-437/2012/A
& EP-438/2012/K |
11240 |
Excavation,
Sorting and Disposal of Stockpiled Spoils to Approved Receptor Site |
EP-438/2012/K |
11286 |
Pedestrian
Link Connecting Pak Tai Street and Sung Wong Toi Station |
EP-438/2012/K |
Table 2.2 Summary of Major Construction Activities in the Reporting Period
Works Contract |
Site |
Construction Activities |
11286 |
Works in Sung Wong Toi (SUW) (formerly named as To Kwa Wan (TKW)) |
Near Sung Wong Toi Exit D (W1) · Site Formation · Bored pile · Pre-grout · Steel works Near Pak Tai Street (H2) · Site Formation · Pre-drill · UU diversion · Steel works |
Table 2.3 Summary of TSP Monitoring Results in the Reporting Period
Monitoring Station ID |
Location |
TSP Concentration (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
Exceedance due to the Project Construction (Yes/ No/ N/A) |
Works Contracts 1102 and 1103 |
|
|
|
|
|
DMS-1(10) |
C.U.H.K.A.A. Thomas Cheung School |
N/A |
148.7 |
260 |
N/A |
Works Contract 1103 |
|
|
|
|
|
DMS-2(11) |
Price Memorial Catholic Primary School |
N/A |
167.4 |
260 |
N/A |
Works Contracts 1103 and 1106 |
|
|
|
|
|
DMS-3(12) |
Hong Kong S.K.H Nursing Home (1) |
N/A |
159.1 |
260 |
N/A |
Works Contract 1106(9) |
|
|
|
|
|
DMS-4(12) |
Block 1, Rhythm Garden |
N/A |
160.4 |
260 |
N/A |
Works Contract 1108 (4) |
|
|
|
|
|
Works Contract 1109 |
|
|
|
|
|
DMS-6 |
Katherine Building (2) |
N/A |
156.8 |
260 |
N/A |
DMS-8 |
SKH Good Shepherd Primary School |
N/A |
152.2 |
260 |
N/A |
DMS-9 |
No. 12 Pau Chung Street (3)(8) |
N/A |
160.9 |
260 |
N/A |
DMS-10 |
Chat Ma Mansion |
N/A |
170.4 |
260 |
N/A |
Works Contract 1111 |
|
|
|
|
|
AM1(5)(13) |
No. 234 – 238 Chatham Road North (6) |
N/A |
183.9 |
260 |
N/A |
Works Contract 1112 |
|
|
|
|
|
Site Boundary of Finger Pier Adjacent To Harbourfront Horizon (7) |
N/A |
182 |
260 |
N/A |
|
Works Contract 11240 (4) |
|
|
|
|
|
Works Contract 11286 |
|
|
|
|
|
DMS-7 (14) |
Skytower Tower 2 |
45-76 |
166.7 |
260 |
No |
Notes:
(1) Alternative monitoring location to Shek On House
(2) Alternative monitoring location to Prosperity House
(3) Alternative monitoring location to Lucky Building
(4) No TSP monitoring is required under this contract
(5) AM1 named as HUH-1-3 in SCL(TAW-HUH) and SCL(HHS) EIA Reports.
(6) Alternative monitoring location to Wing Fung Building
(7) Alternative monitoring location to Harbourfront Horizon
(8) Alternative monitoring location of No. 26 Kowloon City Road
(9) The 24-hour TSP monitoring works would be taken up by Works Contract 1106 since the completion of Works Contract 1107 in Feb 2018.
(10) The cessation of monitoring works at DMS-1 was approved by EPD and the last monitoring was conducted on 16 Jul 2018.
(11) The temporary cessation of monitoring works at DMS-2 was approved by EPD in end-June 2019. The last monitoring date was 27 June 2019.
(12) The cessation of monitoring works at DMS-3 and DMS-4 was approved by EPD on 31 Jul 2019. The last monitoring was conducted on 30 Jul 2019.
(13) The cessation of monitoring works at AM1 was proposed on 25 Jul 2019 and EPD expressed no objection on 31 Jul 2019.
(14) ET has obtained the permission from Sky Tower to deploy the High Volume Sampler (HVS) at the location same as the originally proposed dust monitoring location of DMS-7 in the approved EM&A Manual for SCL (TAW HUH). 24-hour TSP thus has been conducted at Sky Tower Tower 2 (podium level) since 27 October 2023.
Table 2.4 Summary of Construction Noise Monitoring Results in the Reporting Period
Monitoring Station ID |
Location |
Noise Level (LAeq,30mins, dB(A)) |
Limit Level (dB(A)) |
Exceedance due to the Project Construction (Yes/No/N/A) |
||
Measured |
Baseline |
Corrected (7) |
||||
Works Contracts 1102 and 1103 |
|
|
|
|
|
|
NMS-CA-1(12) |
C.U.H.K.A.A. Thomas Cheung School |
N/A |
57.0 |
N/A |
70 (65 during examination period) |
N/A |
Works Contract 1103 |
|
|
|
|
|
|
NMS-CA-2(13) |
Price Memorial Catholic Primary School |
N/A |
66.0 |
N/A |
70 (65 during examination period) |
N/A |
Works Contracts 1103 and 1106 |
|
|
|
|
|
|
NMS-CA-3(14) |
Hong Kong S.K.H Nursing Home (1) |
N/A |
73.0 |
N/A |
70 |
N/A |
Works Contracts 1106(11) |
|
|
|
|
|
|
NMS-CA-4(14) |
Block 1, Rhythm Garden (north-eastern façade) |
N/A |
71.0 |
N/A |
75 |
N/A |
NMS-CA-5(14) |
Block 1, Rhythm Garden (northern façade)(2) |
N/A |
74.0 |
N/A |
70 (65 during examination period) |
N/A |
Works Contract 1108 (6) |
|
|
|
|
|
|
Works Contract 1109 |
|
|
|
|
|
|
NMS-CA-6 |
No. 16-23 Nam Kok Road (3) |
N/A |
76.1 |
N/A |
75 |
N/A |
NMS-CA-8 |
SKH Good Shepherd Primary School |
N/A |
75.4 |
N/A |
70 (65 during examination period) (79 during the period of conducting the continuous noise monitoring) (8) |
N/A |
NMS-CA-9 |
Kong Yiu Mansion (4) |
N/A |
69.2 |
N/A |
75 |
N/A |
NMS-CA-10 |
Chat Ma Mansion |
N/A |
76.6 |
N/A |
75 |
N/A |
Works Contract 1111 |
|
|
|
|
|
|
NM1(15) |
Carmel Secondary School (South Block) |
N/A |
68.0 |
N/A |
70 (65 during examination period) (68 during the period of conducting the continuous noise monitoring) (9) |
N/A |
NM2(15) |
No. 234 – 238 Chatham Road North (5) |
N/A |
79.0 |
N/A |
75 (77) (10) |
N/A |
Works Contract 1112 (6) |
|
|
|
|
|
|
Works Contract 11240 (6) |
|
|
|
|
|
|
Works Contract 11286 |
|
|
|
|
|
|
NMS-CA-7 |
Skytower Tower 2 |
67.3-68.9 |
70.0 |
< Baseline |
75 |
No |
Notes:
(1) Alternative monitoring location to Shek On House.
(2) Alternative monitoring location to Canossa Primary School (San Po Kong).
(3) Alternative monitoring location to Prosperity House.
(4) Alternative monitoring location to Lucky Building.
(5) Alternative monitoring location to Wing Fung Building.
(6) No construction noise monitoring is required under this contract.
(7) The measured noise levels are corrected against the corresponding baseline noise levels.
(8) The Limit Level of 79 dB(A) was updated on 22 Aug 2013 as per the latest Construction Noise Mitigation Measures Plan (CNMMP) and Continuous Noise Monitoring Plan (CNMP) which were approved by EPD.
(9) The Limit of 68 dB(A) was updated on 20 Jan 2014 as per the latest CNMMP and CNMP which were approved by EPD.
(10) Daytime noise Limit Level of 77 dB(A) applies during the continuous noise monitoring period.
(11) The construction noise monitoring works would be taken up by Works Contract 1106 since the completion of Works Contract 1107 in Feb 2018.
(12) The cessation of monitoring works at NMS-CA-1 was approved by EPD and the last monitoring was conducted on 17 Jul 2018.
(13) The temporary cessation of monitoring works at NMS-CA-2 was approved by EPD in end-June 2019. The last monitoring date was 24 Jun 2019.
(14) The cessation of monitoring works at NMS-CA-3, NMS-CA-4 and NMS-CA-5 was approved by EPD on 31 Jul 2019. The last monitoring proposed on 31 Jul 2019 was rescheduled to 1 Aug 2019 due to adverse weather and the hoist of Typhoon Signal No.8 (Typhoon “Wipha”).
(15) The cessation of monitoring works at NM1 and NM2 were proposed on 25 Jul 2019 and EPD expressed no objection on 31 Jul 2019.
Table 2.5 Log for Environmental Complaints, Notification of Summons and Successful Prosecutions for the Reporting Month
Works Contract |
Environmental Complaints |
Notification of Summons |
Successful Prosecutions |
11286 |
1 |
0 |
0 |
Table 3.1 Summary of Status of Required Submissions for EP-437/2012/A
EP Condition (EP-437/2012/A) |
Submission |
Submission date |
Condition 1.11 |
Notification of Commencement Date of Construction of the Project |
30 Nov 2012 |
Condition 2.3 |
Notification of Information of Community Liaison Groups |
30 Nov 2012 |
Condition 2.5 |
Management Organisation of Main Construction Companies |
19 Dec 2012 (1st submission) 30 Apr 2013 (2nd submission) |
Condition 2.6 |
Construction Programme and EP Submission Schedule |
19 Dec 2012 |
Condition 2.7 |
Construction Noise Mitigation Measures Plan (CNMMP) |
30 Nov 2012 (1st submission) 8 Feb 2013 (Approved) 26 Apr 2013 (2nd submission) 11 Jun 2013 (3rd submission) 27 Aug 2013 (Approved) 20 Jan 2014 (4th submission) 28 Apr 2016 (Approved) |
Condition 2.8 |
Continuous Noise Monitoring Plan (CNMP) |
30 Nov 2012 (1st submission) 11 Jan 2013 (2nd submission) 8 Feb 2013 (Approved) 20 Jan
2014 (3rd submission) |
Condition 2.9 |
Construction and Demolition Materials Management Plan (C&DMMP) |
6 Jul 2012 (1st submission) 12 Sep 2012 (2nd submission) 15 Oct 2012 (Approved) |
Condition 2.10 |
Sediment Management Plan |
6 Jul 2012 (1st submission) 12 Sep 2012 (2nd submission) 5 Oct 2012 (3rd submission) 15 Oct 2012 (Approved) |
Condition 2.11 |
Visual, Landscape, Tree Planting & Tree Protection Plan (VLTTP) |
14 Nov 2012 (1st submission) 8 Feb 2013 (2nd submission) 4 Feb 2015 (3rd submission) 26 Jun 2015 (4th submission) 12 May 2017 (5th submission) 17 Apr 2018 (6th submission) 17 Apr 2019 (7th submission) 9 Apr 2020 (8th submission) |
Condition 2.16 |
Operational Ground-borne Noise Mitigation Measures Plan |
23 Mar 2017 (1st submission) 17 May 2017 (2nd submission) 28 Jun 2017 (3rd submission) 20 Jul 2017 (Approved) |
Condition 2.19 |
As-built drawing(s) for Operation Air-borne Noise Mitigation Measure |
10 Jan 2018 (1st submission) 9 Feb 2018 (Approved) |
Condition 2.21 |
Proposal for Updating Maximum Allowable Sound Power Levels of Fixed Plant Sources |
26 Jul 2019 (Batch 1 Version A submission) 14 Aug 2019 (Batch 1 Version A approved) |
Condition 2.21 |
Fixed Plant Noise Audit Report |
29 Aug 2019 (Batch 1 Version A submission) 11 Oct 2019 (Approved) |
Condition 3.1 |
Proposal for Cessation of EM&A Programme at Hung Hom North Approach Tunnels |
25 Jul 2019 (1st submission) 31 Jul 2019 (Approved) |
Condition 3.1 |
Proposal for Cessation of EM&A Programme at Hung Hom Station and Stabling Sidings |
21 Oct 2020 (1st submission) 29 Oct 2020 (Approved) |
Condition 3.3 |
Baseline Monitoring Report (Works Contracts 1103, 1106 and 1111 – Hin Keng to Diamond Hill Tunnels, Diamond Hill Station, and Hung Hom North Approach Tunnels) |
19 Oct 2012 |
Condition 3.4 |
Monthly EM&A Reports No. 5-98
Monthly EM&A Report No. 99 |
Reported in previous Monthly EM&A Reports
11 Dec 2020 |
Table 3.2 Summary of Status of Required Submissions for EP-438/2012/K
EP Condition |
Submission |
Submission date |
Condition 1.12 |
Notification of Commencement Date of Construction of the Project |
1 Aug 2012 |
Condition 2.3 |
Notification of Information of Community Liaison Groups |
13 Jul 2012 (1st submission) 31 Aug 2012 (2nd submission) 30 Nov 2012 (3rd submission) |
Condition 2.7 |
Management Organisation of Main Construction Companies |
27 Jul 2012 (1st submission) 21 Aug 2012 (2nd submission) 19 Dec 2012 (3rd submission) 22 Jan 2013 (4th submission) 30 Apr 2013 (5th submission) 21 May 2013 (6th submission) |
Condition 2.8 |
Construction Programme and EP Submission Schedule |
27 Jul 2012 |
Condition 2.9 |
Construction Noise Mitigation Measures Plan (CNMMP) |
1 Aug 2012 (1st submission) 28 Sep 2012 (2nd submission) 30 Nov 2012 (3rd submission) 11 Jan 2013 (4th submission) 8 Feb 2013 (Approved) 26 Apr 2013 (6th submission) 11 Jun 2013 (7th submission) 12 Jul 2013 (Approved) 26 Jul 2013 (8th submission) 22 Aug 2013 (Approved) 23 Aug 2013 (9th submission) 13 Sep 2013 (Approved) 20 Jan 2014 (10th submission) 26 Feb 2014 (Approved) 31 Mar 2015 (Contract 1106 submission only) 13 Apr 2015 (Contract 1106 submission only) 15 Apr 2015 (Approved) |
Condition 2.10 |
Continuous Noise Monitoring Plan (CNMP) |
1 Aug 2012 (1st submission) 28 Sep 2012 (2nd submission) 30 Nov 2012 (3rd submission) 11 Jan 2013 (4th submission) 8 Feb 2013 (Approved) 8 Feb 2013 (5th submission) 26 Apr 2013 (6th submission) 11 Jun 2013 (7th submission) 12 Jul 2013 (Approved) 26 Jul 2013 (8th submission) 22 Aug 2013 (Approved) 23 Aug 2013 (9th submission) 13 Sep 2013 (Approved) 20 Jan 2014 (10th submission) 26 Feb 2014 (Approved) 7 Oct 2014 (11th submission) 23 Oct 2014 (Approved) |
Condition 2.11 |
Construction and Demolition Materials Management Plan (C&DMMP) |
6 Jul 2012 (1st submission) 12 Sep 2012 (2nd submission) 10 Oct 2012 (Approved) |
Condition 2.12 |
Sediment Management Plan |
6 Jul 2012 (1st submission) 12 Sep 2012 (2nd submission) 5 Oct 2012 (3rd submission) 10 Oct 2012 (Approved) 4 Mar 2013 (4th submission) 9 May 2013 (5th submission) 24 Jul 2013 (6th submission) 26 Jul 2013 (Approved) |
Condition 2.13 |
Visual, Landscape, Tree Planting & Tree Protection Plan |
6 Jul 2012 (1st submission) 30 Aug 2012 (2nd submission) 3 Oct 2012 (3rd submission) 13 Nov 2013 (Approved) 14 Nov 2012 (4th submission) 8 Feb 2013 (5th submission) 18 Mar 2013 (6th submission) 18 Jun 2013 (7th submission) 12 Jul 2013 (Approved) 23 Mar 2017 (8th submission) 7 Mar 2018 (9th submission) 30 Jul 2018 (10th submission) 28 Feb 2019 (11th submission) 5 Mar 2019 (12th submission) 29 May 2019 (13th submission) 19 Jul 2019 (Approved) |
Condition 2.14 |
Transplantation Proposal for Plant Species of Conservation Importance |
22 Aug 2012 (1st submission) 5 Oct 2012 (2nd submission) 26 Nov 2012 (3rd submission) 4 Dec 2012 (Approved) |
Condition 2.15 |
Conservation Plan |
31 Jan 2013 (1st submission) 18 Mar 2013 (2nd submission) 24 Apr 2013 (Approved) |
Condition 2.16 |
Archaeological Action Plan(s) (AAP(s)) for Works Contract 1109 |
10 Aug 2012 (1st submission) 3 Sep 2012 (2nd submission) 21 Sep 2012 (Approved) 11 Oct 2013 (3rd submission) 1 Nov 2013 (Approved) |
Condition 2.16 |
Archaeological Action Plan(s) (AAP(s)) for Works Contract 1106 |
29 Jan 2013 (1st submission) 19 Mar 2013 (2nd submission) 8 Apr 2013 (Approved) |
Condition 2.23 |
Supplementary Contamination Assessment Report for New Territories South Animal Centre |
28 Sep 2012 25 Oct 2012 (Approved) |
Condition 2.27 |
Operational Ground-borne Noise Mitigation Measures Plan |
18 Mar 2016 (Batch 1 Version A submission) 28 Apr 2016 (Batch 1 Version B submission) 28 Apr 2016 (Batch 2 Version A submission) 1 Jun 2016 (Batch 1 Version C submission) 1 Jun 2016 (Batch 2 Version B submission) 23 Jun 2016 (Batch 1 Version D submission) 23 Jun 2016 (Batch 2 Version C submission) 15 Jul 2016 (Batch 1 Version D approved) 15 Jul 2016 (Batch 2 Version C approved) 15 Sep 2016 (Batch 3 Version A submission) 4 Oct 2016 (Batch 3 Version A approved) 8 Mar 2017 (Batch 4 Version A) 7 Apr 2017 (Batch 4 Version A approved) 7 Jun 2017 (Final) 20 Jul 2017 (Approved) |
Condition 2.28 |
As-built Drawings for Operational Ground-borne Noise Mitigation Measures |
10 Aug 2017 (1st submission) 15 Sep 2017 (Approved) |
Condition 2.30 |
As-built Drawings for Operational Air-borne Noise Mitigation Measures |
4 Dec 2015 (1st submission) 28 Dec 2015 (2nd submission) 4 Feb 2016 (Approved) 20 Mar 2018 (3rd submission) 18 Jul 2018 (Approved) 4 May 2018 (4th submission) 23 Jul 2018 (Approved) 20 Feb 2020 (5th submission) 17 Mar 2020 (Approved) |
Condition 2.31 |
Performance Test Report for Train Noise – Operational Airborne Railway and Ground-borne Noise |
15 Nov 2018 (Batch 1 Version A submission) 30 Jan 2019 (Batch 2 Version A submission) 29 Mar 2019 (Batch 1 Version A & Batch 2 Version B submission) 15 April 2019 (Approved) |
Condition 2.32 |
Proposal for Updating Maximum Allowable Sound Power Levels of Fixed Plant Sources |
30 Jan 2019 (Batch 1 Version A submission) 27 Feb 2019 (Batch 1 Version B submission) 13 Mar 2019 (Batch 1 Version B approved) 15 Mar 2019 (Batch 2 Version A submission) 8 Apr 2019 (Batch 2 Version A approved) 24 April 2019 (Batch 3 & 4 Version A submission) 21 May 2019 (Batch 3 Version B submission) 11 Jun 2019 (Batch 3 Version B & Batch 4 Version A approved) 21 Jun 2019 (Batch 5 Version A submission) 17 Jul 2019 (Batch 5 Version A approved) 19 Jul 2019 (Batch 6 Version A submission) 26 Jul 2019 (Batch 7 Version A submission) 29 Jul 2019 (Batch 6 Version A approved) 14 Aug 2019 (Batch 7 Version A approved) |
Condition 2.32 |
Fixed Plant Noise Audit Report |
30 Jan 2019 (Batch 1 Version A submission) 15 Mar 2019 (Batch 1 Version B submission) 4 Apr 2019 (Batch 1 Version B approved) 16 Apr 2019 (Batch 2 Version A submission) 7 May 2019 (Batch 2 Version A approved) 24 Jun 2019 (Batch 3 Version A and Batch 4 Version A submission) 6 Jul 2019 (Batch 3 Version A and Batch 4 Version A approved) 2 Aug 2019 (Batch 5 Version A submission) 27 Aug 2019 (Batch 6 Version A submission) 29 Aug 2019 (Batch 7 Version A submission) 3 Sep 2019 (Batch 5 Version A approved) 13 Sep 2019 (Batch 6 Version B approved) 23 Sep 2019 (Batch 7 Version B submission) 11 Oct 2019 (Batch 7 Version B approved) |
Condition 2.33 |
As-built Drawings for Landscape and Visual Mitigation Measures |
4 Dec 2015 (1st submission) 28 Dec 2015 (2nd submission) 4 Feb 2016 (Approved) 22 Aug 2018 (3rd submission) 5 Nov 2018 (4th submission) 6 Sep 2019 (5th submission) 11 Sep 2019 (Approved) 27 Sep 2019 (6th submission) 21 Feb 2020 (7th submission) 17 Sep 2020 (8th submission) 4 Nov 2020 (9th submission) |
Condition 2.36 |
Contamination Assessment Plan (CAP) for the Temporary Magazine Site at TKO Area 137 |
23 Mar 2016 (1st submission) 20 Apr 2016 (2nd submission) 22 Apr 2016 (Approved) |
Condition 2.36 |
Contamination Assessment Report (CAR) for the Temporary Magazine Site at TKO Area 137 |
19 May 2016 (1st submission) 3 Jun 2016 (2nd submission) 15 Jun 2016 (Approved)
|
Condition 3.1 |
Proposal for Termination of Environmental Monitoring and Audit (EM&A) Programme for Kai Tak Barging Point Facilities |
7 Oct 2016 (Approved) |
Condition 3.1 |
Proposal for Cessation of EM&A Works at Hin Keng |
9 May 2018 (1st submission) 16 Jul 2018 (Approved) |
Condition 3.1 |
Proposal for Cessation of EM&A Programme at Diamond Hill Station |
25 Jul 2019 (1st submission) 31 Jul 2019 (Approved) |
Condition 3.1 |
Proposal for Cessation of EM&A Programme at Hung Hom North Approach Tunnels |
25 Jul 2019 (1st submission) 31 Jul 2019 (Approved) |
Condition 3.1 |
Proposal for Cessation of EM&A Programme at Stations and Tunnels of Kowloon City Section |
24 Aug 2020 (1st submission) 28 Aug 2020 (Approved) |
Condition 3.1 |
Proposal for Cessation of EM&A Programme at Hung Hom Station and Stabling Sidings |
21 Oct 2020 (1st submission) 29 Oct 2020 (Approved) |
Condition 3.3 |
Baseline Monitoring Report (Works Contract 1109 - Stations and Tunnels of Kowloon City Section) |
27 Jul 2012 |
Condition 3.3 |
Baseline Monitoring Report (Works Contract 1108A – Kai Tak Barging Point Facilities) |
31 Jul 2012 |
Condition 3.3 |
Baseline Monitoring Report (Works Contracts 1103, 1106 and 1111 – Hin Keng to Diamond Hill Tunnels, Diamond Hill Station, and Hung Hom North Approach Tunnels) |
19 Oct 2012 |
Condition 3.4 |
Monthly EM&A Reports No. 1-103
Monthly EM&A Report No. 104 |
Reported in previous Monthly EM&A Reports
14 November 2023 |
Condition 3.4 |
Monthly Operational Airborne Rail Noise Monitoring Report (Festival City) No. 1-6
|
Reported in previous Monthly EM&A Reports
|