MTR Corporation Limited
Shatin to Central Link – Tai Wai to Hung Hom Section and MongKok East to Hung Hom Section
Monthly EM&A Report No. 97
[Period from 1 to 30 September 2020] |
Table of Contents
Page
2......... Environmental Monitoring and Audit3
3......... implementation status on the environmental protection requirements
List of Tables
Table 1.1 Summary of Awarded Works Contracts
Table 2.1 Summary of Status of Required Submissions for EP-437/2012/A
Table 2.2 Summary of Status of Required Submissions for EP-438/2012/K
List of Appendices
Table 1.1 Summary of Awarded Works Contracts
Works Contract |
Description |
Construction Start Date |
Contractor |
Environmental Team |
1101(1) |
Ma On Shan Line Modification Works |
December 2012 |
Sun Fook Kong Joint Venture (SFKJV) |
ANewR Consulting Ltd. (ANewR) |
1102(6) |
Hin Keng Station and Approach Structures |
October 2013 |
Penta-Ocean Construction Co. Ltd. |
Wellab Limited (Wellab) |
1103(7) |
Hin Keng to Diamond Hill Tunnels |
February 2013 |
Vinci Construction Grands Projets |
Ove Arup & Partners Hong Kong Ltd. (Arup) |
October 2019 |
Wing Ho Yuen Landscaping Co. Ltd. |
MTR Co. Limited |
||
1106(8) |
Diamond Hill Station |
March 2013 |
Leader Joint Venture |
Cinotech Consultants Ltd. (Cinotech) |
1107(4) |
Diamond Hill to Kai Tak Tunnels |
May 2013 |
Chun Wo - SELI Joint Venture |
Cinotech Consultants Ltd. (Cinotech) |
1108(5) |
Kai Tak Station and Associated Tunnels |
June 2013 |
Kaden -Chun Wo Joint Venture |
Environmental Pioneers & Solutions Ltd. |
1108A(2) |
Kai Tak Barging Point Facilities |
September 2012 |
Concentric – Hong Kong River Joint Venture (CCL-HKR JV) |
Cinotech Consultants Ltd. (Cinotech) |
1109(10) |
Stations and Tunnels of Kowloon City Section |
September 2012 |
Samsung-Hsin Chong JV (SSHCJV) |
ERM-Hong Kong Limited (ERM) |
1111(9) |
Hung Hom North Approach Tunnels |
January 2013 |
Gammon-Kaden SCL1111 JV |
AECOM Asia Co. Ltd. |
1112 |
Hung Hom Station and Stabling Sidings |
June 2013 |
Leighton Contractors (Asia) Limited |
SMEC Asia Ltd., HK |
11240(3) |
Excavation, Sorting and Disposal of Stockpiled Spoils to Approved Receptor Site |
October 2017 |
Crown Asia Engineering Limited (CAEL) |
MTR Co. Limited |
Notes:
(1) All construction works (works areas at Tai Wai Mei Tin Road and the offsite temporary storage areas) under Works Contract 1101 were completed on 29 February 2016.
(2) All construction works (Kai Tak Barging Point Facilities) under Works Contract 1108A were completed on 29 September 2016.
(3) All construction works (Excavation, Sorting and Disposal of Stockpiled Spoils to Approved Receptor Site) under Works Contract 11240 were completed on 3 January 2018.
(4) All construction works (Diamond Hill to Kai Tak Tunnels) under Works Contract 1107 were completed on 22 February 2018.
(5) All construction works (Kai Tak Station and associated tunnels) under Works Contract 1108 were completed in July 2018.
(6) All construction works (Hin Keng Station and Approach Structures) under Works Contract 1102 were completed in December 2018. The Environmental Team was taken over by Wellab Limited starting from 1 January 2019.
(7) All construction works (Hin Keng to Diamond Hill Tunnels) under Works Contract 1103 were completed in June 2019. Minor landscaping works at Fung Tak had been commenced in mid-October and all the works were completed at the end of October 2019.
(8) All construction works (Diamond Hill Station) under Works Contract 1106 with significant environmental impacts were substantially completed by 25 June 2019.
(9) All major construction works (Hung Hom North Approach Tunnels) under Works Contract 1111 have been substantially completed since 18 November 2018 with only minor works remaining.
(10) All construction works (Stations and Tunnels of Kowloon City Section) under Works Contract 1109 have been substantially completed on 12 August 2020.
Works Contract |
Contract Title |
Works Covered in Environmental Permit No. |
1101 |
Ma On Shan Modification Works |
|
1102 |
Hin Keng Station and Approach Structures |
|
1103 |
Hin Keng to Diamond Hill Tunnels |
|
1106 |
Diamond Hill Station |
|
1107 |
Diamond Hill to Kai Tak Tunnels |
|
1108 |
Kai Tak Station and Associated Tunnels |
|
1108A |
Kai Tak Barging Point Facilities |
|
1109 |
Stations and Tunnels of Kowloon City Section |
|
1111 |
Hung Hom North Approach Tunnels |
EP-437/2012/A & EP-438/2012/K |
1112 |
Hung Hom Station and Stabling Sidings |
EP-437/2012/A & EP-438/2012/K |
11240 |
Excavation, Sorting and Disposal of Stockpiled Spoils to Approved Receptor Site |
EP-438/2012/K |
Table 2.1 Summary of Status of Required Submissions for EP-437/2012/A
EP Condition (EP-437/2012/A) |
Submission |
Submission date |
Condition 1.11 |
Notification of Commencement Date of Construction of the Project |
30 Nov 2012 |
Condition 2.3 |
Notification of Information of Community Liaison Groups |
30 Nov 2012 |
Condition 2.5 |
Management Organisation of Main Construction Companies |
19 Dec 2012 (1st submission) 30 Apr 2013 (2nd submission) |
Condition 2.6 |
Construction Programme and EP Submission Schedule |
19 Dec 2012 |
Condition 2.7 |
Construction Noise Mitigation Measures Plan (CNMMP) |
30 Nov 2012 (1st submission) 8 Feb 2013 (Approved) 26 Apr 2013 (2nd submission) 11 Jun 2013 (3rd submission) 27 Aug 2013 (Approved) 20 Jan 2014 (4th submission) 28 Apr 2016 (Approved) |
Condition 2.8 |
Continuous Noise Monitoring Plan (CNMP) |
30 Nov 2012 (1st submission) 11 Jan 2013 (2nd submission) 8 Feb 2013 (Approved) 20 Jan 2014 (3rd
submission) |
Condition 2.9 |
Construction and Demolition Materials Management Plan (C&DMMP) |
6 Jul 2012 (1st submission) 12 Sep 2012 (2nd submission) 15 Oct 2012 (Approved) |
Condition 2.10 |
Sediment Management Plan |
6 Jul 2012 (1st submission) 12 Sep 2012 (2nd submission) 5 Oct 2012 (3rd submission) 15 Oct 2012 (Approved) |
Condition 2.11 |
Visual, Landscape, Tree Planting & Tree Protection Plan (VLTTP) |
14 Nov 2012 (1st submission) 8 Feb 2013 (2nd submission) 4 Feb 2015 (3rd submission) 26 Jun 2015 (4th submission) 12 May 2017 (5th submission) 17 Apr 2018 (6th submission) 17 Apr 2019 (7th submission) 9 Apr 2020 (8th submission) |
Condition 2.16 |
Operational Ground-borne Noise Mitigation Measures Plan |
23 Mar 2017 (1st submission) 17 May 2017 (2nd submission) 28 Jun 2017 (3rd submission) 20 Jul 2017 (Approved) |
Condition 2.19 |
As-built drawing(s) for Operation Air-borne Noise Mitigation Measure |
10 Jan 2018 (1st submission) 9 Feb 2018 (Approved) |
Condition 2.21 |
Proposal for Updating Maximum Allowable Sound Power Levels of Fixed Plant Sources |
26 Jul 2019 (Batch 1 Version A submission) 14 Aug 2019 (Batch 1 Version A approved) |
Condition 2.21 |
Fixed Plant Noise Audit Report |
29 Aug 2019 (Batch 1 Version A submission) |
Condition 3.3 |
Baseline Monitoring Report (Works Contracts 1103, 1106 and 1111 – Hin Keng to Diamond Hill Tunnels, Diamond Hill Station, and Hung Hom North Approach Tunnels) |
19 Oct 2012 |
Condition 3.4 |
Monthly EM&A Reports No. 5-95
Monthly EM&A Report No. 96 |
Reported in previous Monthly EM&A Reports
11 Sep 2020 |
Table 2.2 Summary of Status of Required Submissions for EP-438/2012/K
EP Condition |
Submission |
Submission date |
Condition 1.12 |
Notification of Commencement Date of Construction of the Project |
1 Aug 2012 |
Condition 2.3 |
Notification of Information of Community Liaison Groups |
13 Jul 2012 (1st submission) 31 Aug 2012 (2nd submission) 30 Nov 2012 (3rd submission) |
Condition 2.7 |
Management Organisation of Main Construction Companies |
27 Jul 2012 (1st submission) 21 Aug 2012 (2nd submission) 19 Dec 2012 (3rd submission) 22 Jan 2013 (4th submission) 30 Apr 2013 (5th submission) 21 May 2013 (6th submission) |
Condition 2.8 |
Construction Programme and EP Submission Schedule |
27 Jul 2012 |
Condition 2.9 |
Construction Noise Mitigation Measures Plan (CNMMP) |
1 Aug 2012 (1st submission) 28 Sep 2012 (2nd submission) 30 Nov 2012 (3rd submission) 11 Jan 2013 (4th submission) 8 Feb 2013 (Approved) 26 Apr 2013 (6th submission) 11 Jun 2013 (7th submission) 12 Jul 2013 (Approved) 26 Jul 2013 (8th submission) 22 Aug 2013 (Approved) 23 Aug 2013 (9th submission) 13 Sep 2013 (Approved) 20 Jan 2014 (10th submission) 26 Feb 2014 (Approved) 31 Mar 2015 (Contract 1106 submission only) 13 Apr 2015 (Contract 1106 submission only) 15 Apr 2015 (Approved) |
Condition 2.10 |
Continuous Noise Monitoring Plan (CNMP) |
1 Aug 2012 (1st submission) 28 Sep 2012 (2nd submission) 30 Nov 2012 (3rd submission) 11 Jan 2013 (4th submission) 8 Feb 2013 (Approved) 8 Feb 2013 (5th submission) 26 Apr 2013 (6th submission) 12 Jul 2013 (Approved) 26 Jul 2013 (8th submission) 22 Aug 2013 (Approved) 23 Aug 2013 (9th submission) 13 Sep 2013 (Approved) 20 Jan 2014 (10th submission) 26 Feb 2014 (Approved) 7 Oct 2014 (11th submission) 23 Oct 2014 (Approved) |
Condition 2.11 |
Construction and Demolition Materials Management Plan (C&DMMP) |
6 Jul 2012 (1st submission) 12 Sep 2012 (2nd submission) 10 Oct 2012 (Approved) |
Condition 2.12 |
Sediment Management Plan |
6 Jul 2012 (1st submission) 12 Sep 2012 (2nd submission) 5 Oct 2012 (3rd submission) 10 Oct 2012 (Approved) 4 Mar 2013 (4th submission) 9 May 2013 (5th submission) 24 Jul 2013 (6th submission) 26 Jul 2013 (Approved) |
Condition 2.13 |
Visual, Landscape, Tree Planting & Tree Protection Plan |
6 Jul 2012 (1st submission) 30 Aug 2012 (2nd submission) 3 Oct 2012 (3rd submission) 13 Nov 2013 (Approved) 14 Nov 2012 (4th submission) 8 Feb 2013 (5th submission) 18 Mar 2013 (6th submission) 18 Jun 2013 (7th submission) 12 Jul 2013 (Approved) 23 Mar 2017 (8th submission) 7 Mar 2018 (9th submission) 30 Jul 2018 (10th submission) 28 Feb 2019 (11th submission) 5 Mar 2019 (12th submission) 29 May 2019 (13th submission) 19 Jul 2019 (Approved) |
Condition 2.14 |
Transplantation Proposal for Plant Species of Conservation Importance |
22 Aug 2012 (1st submission) 5 Oct 2012 (2nd submission) 26 Nov 2012 (3rd submission) 4 Dec 2012 (Approved) |
Condition 2.15 |
Conservation Plan |
31 Jan 2013 (1st submission) 18 Mar 2013 (2nd submission) 24 Apr 2013 (Approved) |
Condition 2.16 |
Archaeological Action Plan(s) (AAP(s)) for Works Contract 1109 |
10 Aug 2012 (1st submission) 3 Sep 2012 (2nd submission) 21 Sep 2012 (Approved) 11 Oct 2013 (3rd submission) 1 Nov 2013 (Approved) |
Condition 2.16 |
Archaeological Action Plan(s) (AAP(s)) for Works Contract 1106 |
29 Jan 2013 (1st submission) 19 Mar 2013 (2nd submission) 8 Apr 2013 (Approved) |
Condition 2.23 |
Supplementary Contamination Assessment Report for New Territories South Animal Centre |
28 Sep 2012 25 Oct 2012 (Approved) |
Condition 2.27 |
Operational Ground-borne Noise Mitigation Measures Plan |
18 Mar 2016 (Batch 1 Version A submission) 28 Apr 2016 (Batch 1 Version B submission) 28 Apr 2016 (Batch 2 Version A submission) 1 Jun 2016 (Batch 1 Version C submission) 1 Jun 2016 (Batch 2 Version B submission) 23 Jun 2016 (Batch 1 Version D submission) 23 Jun 2016 (Batch 2 Version C submission) 15 Jul 2016 (Batch 1 Version D approved) 15 Jul 2016 (Batch 2 Version C approved) 15 Sep 2016 (Batch 3 Version A submission) 4 Oct 2016 (Batch 3 Version A approved) 8 Mar 2017 (Batch 4 Version A) 7 Apr 2017 (Batch 4 Version A approved) 7 Jun 2017 (Final) 20 Jul 2017 (Approved) |
Condition 2.28 |
As-built Drawings for Operational Ground-borne Noise Mitigation Measures |
10 Aug 2017 (1st submission) |
Condition 2.30 |
As-built Drawings for Operational Air-borne Noise Mitigation Measures |
4 Dec 2015 (1st submission) 28 Dec 2015 (2nd submission) 4 Feb 2016 (Approved) 20 Mar 2018 (3rd submission) 18 Jul 2018 (Approved) 4 May 2018 (4th submission) 23 Jul 2018 (Approved) 20 Feb 2020 (5th submission) 17 Mar 2020 (Approved) |
Condition 2.31 |
Performance Test Report for Train Noise – Operational Airborne Railway and Ground-borne Noise |
15 Nov 2018 (Batch 1 Version A submission) 30 Jan 2019 (Batch 2 Version A submission) 29 Mar 2019 (Batch 1 Version A & Batch 2 Version B submission) 15 April 2019 (Approved) |
Condition 2.32 |
Proposal for Updating Maximum Allowable Sound Power Levels of Fixed Plant Sources |
30 Jan 2019 (Batch 1 Version A submission) 27 Feb 2019 (Batch 1 Version B submission) 13 Mar 2019 (Batch 1 Version B approved) 15 Mar 2019 (Batch 2 Version A submission) 8 Apr 2019 (Batch 2 Version A approved) 24 April 2019 (Batch 3 & 4 Version A submission) 21 May 2019 (Batch 3 Version B submission) 11 Jun 2019 (Batch 3 Version B & Batch 4 Version A approved) 21 Jun 2019 (Batch 5 Version A submission) 17 Jul 2019 (Batch 5 Version A approved) 19 Jul 2019 (Batch 6 Version A submission) 26 Jul 2019 (Batch 7 Version A submission) 29 Jul 2019 (Batch 6 Version A approved) 14 Aug 2019 (Batch 7 Version A approved) |
Condition 2.32 |
Fixed Plant Noise Audit Report |
30 Jan 2019 (Batch 1 Version A submission) 15 Mar 2019 (Batch 1 Version B submission) 4 Apr 2019 (Batch 1 Version B approved) 16 Apr 2019 (Batch 2 Version A submission) 7 May 2019 (Batch 2 Version A approved) 24 Jun 2019 (Batch 3 Version A and Batch 4 Version A submission) 6 Jul 2019 (Batch 3 Version A and Batch 4 Version A approved) 2 Aug 2019 (Batch 5 Version A submission) 27 Aug 2019 (Batch 6 Version A submission) 29 Aug 2019 (Batch 7 Version A submission) 3 Sep 2019 (Batch 5 Version A approved) 13 Sep 2019 (Batch 6 Version B approved) 23 Sep 2019 (Batch 7 Version B submission) 11 Oct 2019 (Batch 7 Version B approved) |
Condition 2.33 |
As-built Drawings for Landscape and Visual Mitigation Measures |
4 Dec 2015 (1st submission) 28 Dec 2015 (2nd submission) 4 Feb 2016 (Approved) 22 Aug 2018 (3rd submission) 5 Nov 2018 (4th submission) 6 Sep 2019 (5th submission) 27 Sep 2019 (6th submission) 21 Feb 2020 (7th submission) |
Condition 2.36 |
Contamination Assessment Plan (CAP) for the Temporary Magazine Site at TKO Area 137 |
23 Mar 2016 (1st submission) 20 Apr 2016 (2nd submission) 22 Apr 2016 (Approved) |
Condition 2.36 |
Contamination Assessment Report (CAR) for the Temporary Magazine Site at TKO Area 137 |
19 May 2016 (1st submission) 3 Jun 2016 (2nd submission) 15 Jun 2016 (Approved)
|
Condition 3.1 |
Proposal for Termination of Environmental Monitoring and Audit (EM&A) Programme for Kai Tak Barging Point Facilities |
7 Oct 2016 (Approved) |
Condition 3.1 |
Proposal for Cessation of EM&A Works at Hin Keng |
9 May 2018 (1st submission) 16 Jul 2018 (Approved) |
Condition 3.1 |
Proposal for Cessation of EM&A Programme at Diamond Hill Station |
25 Jul 2019 (1st submission) 31 Jul 2019 (Approved) |
Condition 3.1 |
Proposal for Cessation of EM&A Programme at Hung Hom North Approach Tunnels |
25 Jul 2019 (1st submission) 31 Jul 2019 (Approved) |
Condition 3.1 |
Proposal for Cessation of EM&A Programme at Stations and Tunnels of Kowloon City Section |
24 Aug 2020 (1st submission) 28 Aug 2020 (Approved) |
Condition 3.3 |
Baseline Monitoring Report (Works Contract 1109 - Stations and Tunnels of Kowloon City Section) |
27 Jul 2012 |
Condition 3.3 |
Baseline Monitoring Report (Works Contract 1108A – Kai Tak Barging Point Facilities) |
31 Jul 2012 |
Condition 3.3 |
Baseline Monitoring Report (Works Contracts 1103, 1106 and 1111 – Hin Keng to Diamond Hill Tunnels, Diamond Hill Station, and Hung Hom North Approach Tunnels) |
19 Oct 2012 |
Condition 3.4 |
Monthly EM&A Reports No. 1-95
Monthly EM&A Report No. 96 |
Reported in previous Monthly EM&A Reports
14 Sep 2020 |
Condition 3.4 |
Monthly Operational Airborne Rail Noise Monitoring Report (Festival City) No. 1-6
|
Reported in previous Monthly EM&A Reports
|