Table of Contents
2............ Environmental Monitoring and Audit
3............ implementation status on the environmental
protection requirements
List of
Tables
Table
1.1 Summary
of Awarded Works Contracts
Table 2.1 Summary
of Major Construction Activities in the Reporting Period
Table 2.2 Summary
of 24-Hour TSP Monitoring Results in the Reporting Period
Table 2.3 Summary
of Construction Noise Monitoring Results in the Reporting Period
Table 3.1 Summary
of Status of Required Submissions for and EP-438/2012/K
Table 3.2 Summary
of Status of Required Submissions for EP-437/2012/A
List of
Appendices
Appendix A 83rd Monthly EM&A Report for Works Contract
1109 – Stations and Tunnels of Kowloon City Section
Appendix B 79th Monthly EM&A Report for Works
Contract 1111 – Hung Hom North Approach Tunnels
Appendix C 77th Monthly EM&A Report for Works
Contract 1106 – Diamond Hill Station
Appendix D 74th Monthly EM&A Report for Works
Contract 1112 – Hung Hom Station and Stabling Sidings
Table
1.1 Summary
of Awarded Works Contracts
Works
Contract |
Description |
Construction
Start Date |
Contractor |
Environmental
Team |
1101(1) |
Ma
On Shan Line Modification Works |
December 2012 |
Sun
Fook Kong Joint Venture (SFKJV) |
ANewR Consulting Ltd. (ANewR) |
1102(6) |
Hin Keng Station
and Approach Structures |
October 2013 |
Penta-Ocean
Construction Co. Ltd. |
Wellab Limited (Wellab) |
1103(7) |
Hin Keng to
Diamond Hill Tunnels |
February 2013 |
Vinci
Construction Grands Projets |
Ove
Arup & Partners Hong Kong Ltd. (Arup) |
1106(8) |
Diamond
Hill Station |
March 2013 |
Leader
Joint Venture |
Cinotech Consultants Ltd. (Cinotech) |
1107(4) |
Diamond
Hill to Kai Tak Tunnels |
May 2013 |
Chun
Wo - SELI Joint Venture |
Cinotech Consultants Ltd. (Cinotech) |
1108(5) |
Kai
Tak Station and Associated Tunnels |
June 2013 |
Kaden
-Chun Wo Joint Venture |
Environmental
Pioneers & Solutions Ltd. |
1108A(2) |
Kai
Tak Barging Point Facilities |
September 2012 |
Concentric
– Hong Kong River Joint Venture (CCL-HKR JV) |
Cinotech Consultants Ltd. (Cinotech) |
1109 |
Stations
and Tunnels of Kowloon City Section |
September 2012 |
Samsung-Hsin Chong JV (SSHCJV) |
ERM-Hong
Kong Limited (ERM) |
1111(9) |
Hung Hom North Approach
Tunnels |
January 2013 |
Gammon-Kaden SCL1111 JV |
AECOM Asia Co. Ltd. |
1112 |
Hung
Hom Station and Stabling Sidings |
June 2013 |
Leighton
Contractors (Asia) Limited |
SMEC Asia Ltd., HK |
11240(3) |
Excavation,
Sorting and Disposal of Stockpiled Spoils to Approved Receptor Site |
October 2017 |
Crown
Asia Engineering Limited (CAEL) |
MTR Co. Limited |
Notes:
(1)
All construction
works (works
areas at Tai Wai Mei Tin Road and the offsite temporary storage areas) under Works Contract
1101 were completed on 29 February 2016.
(2)
All construction
works (Kai Tak Barging Point Facilities) under Works
Contract 1108A were completed on 29 September 2016.
(3)
All construction
works (Excavation,
Sorting and Disposal of Stockpiled Spoils to Approved Receptor Site) under Works
Contract 11240 were completed on 3 January 2018.
(4)
All construction works (Diamond Hill to Kai Tak
Tunnels) under Works Contract 1107 were completed on 22 February 2018.
(5)
All construction works (Kai Tak Station and
associated tunnels) under Works Contract 1108 were completed in July 2018.
(6)
All construction works (Hin Keng
Station and Approach Structures) under Works Contract 1102 were completed in
December 2018. The Environmental Team was taken over by Wellab
Limited starting from 1 January 2019.
(7)
All construction works (Hin Keng to Diamond Hill Tunnels)
under Works Contract 1103 were completed in June 2019.
(8)
All construction works (Diamond Hill
Station) under Works Contract 1106 with
significant environmental impacts were
substantially completed by 25 Jun 2019.
(9)
All major construction works (Hung Hom North Approach Tunnels) under Works Contract 1111 have
been substantially completed since 18 Nov 2018 with only minor works remaining.
Works Contract |
Contract Title |
Works Covered in Environmental Permit No. |
1101 |
Ma On Shan Modification Works |
|
1102 |
Hin Keng
Station and Approach Structures |
|
1103 |
Hin Keng
to Diamond Hill Tunnels |
|
1106 |
Diamond
Hill Station |
|
1107 |
Diamond
Hill to Kai Tak Tunnels |
|
1108 |
Kai Tak Station and Associated Tunnels |
|
1108A |
Kai Tak Barging Point Facilities |
|
1109 |
Stations and Tunnels of Kowloon
City Section |
|
1111 |
Hung Hom North Approach Tunnels |
EP-437/2012/A
& EP-438/2012/K |
1112 |
Hung Hom Station and Stabling Sidings |
|
11240 |
Excavation,
Sorting and Disposal of Stockpiled Spoils to Approved Receptor Site |
EP-438/2012/K |
Table 2.1 Summary
of Major Construction Activities in the Reporting Period
Works Contract |
Site |
Construction Activities |
1106 |
Diamond
Hill Station Area |
· Defect
rectification for SCL DIH station: remaining minor ABWF works; · TTMS
implementation: TTA for site access and temporary footpath diversion at Choi
Hung Road and Lung Cheung Road; and · General
site clearance works |
1109 |
Works
in To Kwa Wan (TKW) (formerly named as Ma Tau Wai (MTW)) |
· TKW
station - ABWF works; · Ma Tau
Wai Road – Pipe installation works; · Lok
Shan Road and To Kwa Complex Playground (Ventilation Shaft and Entrance A) –
Reinstatement works; · Entrance
B – Reinstatement of footpath; · Entrance
C – Installation of gally and footpath
reinstatement works; and · Ma Tau
Wai Road/ To Kwa Wan Road Garden (Entrance D) – Reinstatement works. |
Works
in Sung Wong Toi (SUW) (formerly named as To Kwa Wan (TKW)) |
· Olympic Garden – Reinstatement works; · Olympic Avenue – Reinstatement works; · SUW Station – ABWF works; and · Pet Garden – Reinstatement works of Sung
Wong Toi Playground |
|
1111 |
Ho Man
Tin |
· Defect
rectification |
NSL
(South) |
· Defect
rectification |
|
OB2 /
TB1 |
· Defect
rectification |
|
OB2A /
TB2 |
· Defect
rectification |
|
NSL 9
& Oi Sen Path |
· Defect
rectification |
|
1112 |
Hung Hom Station (HUH) |
· Minor
services connection at G.L J of HUH; · Platform
ABWF and E&M works; · Gate 3
excavation works; and · Asphalt
works to HHS |
SAT
Ventilation Shaft |
· Landscape
preparation works |
|
Concourse
level & Mid-level walkway |
· Modification
works |
Table
2.2 Summary of 24-Hour TSP Monitoring
Results in the Reporting Period
Monitoring Station ID |
Location |
TSP Concentration (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
Exceedance due to the Project
Construction (Yes/ No/ N/A) |
Works
Contracts 1102 and 1103 |
|
|
|
|
|
DMS-1(11) |
C.U.H.K.A.A.
Thomas Cheung School |
N/A |
148.7 |
260 |
N/A |
Works
Contract 1103 |
|
|
|
|
|
DMS-2(12) |
Price
Memorial Catholic Primary School |
N/A |
167.4 |
260 |
No |
Works
Contracts 1103 and 1106 |
|
|
|
|
|
DMS-3(13) |
Hong
Kong S.K.H Nursing Home (1) |
20.3 – 115.7 |
159.1 |
260 |
No |
Works
Contract 1106(10) |
|
|
|
|
|
DMS-4(13) |
Block
1, Rhythm Garden |
12.4 – 52.6 |
160.4 |
260 |
No |
Works
Contract 1108 (5) |
|
|
|
|
|
Works
Contract 1109 |
|
|
|
|
|
DMS-6 |
Katherine Building (2) |
21 – 39 |
156.8 |
260 |
No |
DMS-7 |
Parc
22 (3) |
12 – 54 |
166.7 |
260 |
No |
DMS-8 |
SKH
Good Shepherd Primary School |
14 – 62 |
152.2 |
260 |
No |
DMS-9 |
No.
12 Pau Chung Street (4)(9) |
22 – 82 |
160.9 |
260 |
No |
DMS-10 |
Chat
Ma Mansion |
14 – 53 |
170.4 |
260 |
No |
Works Contract 1111 |
|
|
|
|
|
AM1(6)(14) |
No.
234 – 238 Chatham Road North (7) |
22.8 – 46.0 |
183.9 |
260 |
No |
Works Contract 1112 |
|
|
|
|
|
AM2 |
Site
Boundary of Finger Pier Adjacent
To
Harbourfront Horizon (8) |
37.6 – 50.0 |
182 |
260 |
No |
Works
Contract 11240 (5) |
|
|
|
|
Notes:
(1)
Alternative monitoring location to Shek On House
(2)
Alternative monitoring location to
Prosperity House
(3)
Alternative monitoring location to Skytower Tower 2
(4)
Alternative
monitoring location to Lucky Building
(5)
No TSP monitoring is required under this
contract
(6)
AM1 named as HUH-1-3 in SCL(TAW-HUH) and
SCL(HHS) EIA Reports.
(7)
Alternative monitoring location to Wing
Fung Building
(8)
Alternative monitoring location to
Harbourfront Horizon
(9)
Alternative monitoring
location of No. 26 Kowloon City Road
(10)
The 24-hour TSP monitoring works would be
taken up by Works Contract 1106 since the completion of Works Contract 1107 in
Feb 2018.
(11)
The cessation
of monitoring works at DMS-1 was approved by EPD and the last monitoring was
conducted on 16 Jul 2018.
(12)
The temporary cessation
of monitoring works at DMS-2 was approved by EPD in end-June 2019. The last
monitoring date was 27 June 2019.
(13)
The cessation of monitoring works at DMS-3
and DMS-4 was approved
by EPD on 31 Jul 2019. The last monitoring was conducted on 30 Jul 2019.
(14)
The cessation of monitoring works at AM1
was proposed on 25 Jul 2019 and EPD expressed no objection on 31 Jul 2019.
Table 2.3 Summary of Construction Noise Monitoring Results in the
Reporting Period
Monitoring Station ID |
Location |
Noise Level (LAeq,30mins, dB(A)) |
Limit Level (dB(A)) |
Exceedance due to the Project
Construction (Yes/No) |
|||
Measured |
Baseline |
Corrected (7) |
|||||
Works Contracts
1102 and 1103 |
|
|
|
|
|
||
NMS-CA-1(12) |
C.U.H.K.A.A.
Thomas Cheung School |
N/A |
57.0 |
N/A |
70 (65
during examination period) |
No |
|
Works Contract
1103 |
|
|
|
|
|
||
NMS-CA-2(13) |
Price
Memorial Catholic Primary
School |
N/A |
66.0 |
N/A |
70 (65
during examination period) |
No |
|
Works Contracts
1103 and 1106 |
|
|
|
|
|
||
NMS-CA-3(14) |
Hong
Kong S.K.H Nursing
Home (1) |
70.0 – 73.3 |
73.0 |
< Baseline – 61.5 |
70 |
No |
|
Works Contracts
1106(11) |
|
|
|
|
|
||
NMS-CA-4(14) |
Block
1, Rhythm Garden (north-eastern façade) |
71.6 – 74.1 |
71.0 |
62.7 – 71.2 |
75 |
No |
|
NMS-CA-5(14) |
Block
1, Rhythm Garden (northern façade)(2) |
71.0 – 75.0 |
74.0 |
< Baseline – 68.1 |
70 (65 during examination period) |
No |
|
Works Contract
1108 (6) |
|
|
|
|
|
||
Works Contract
1109 |
|
|
|
|
|
||
NMS-CA-6 |
No. 16-23 Nam Kok Road (3) |
61.7 – 62.6 |
76.1 |
<
Baseline |
75 |
No |
|
NMS-CA-7 |
Skytower Tower
2 |
65.9 – 66.4 |
70.0 |
<
Baseline |
75 |
No |
|
NMS-CA-8 |
SKH
Good Shepherd Primary
School |
72.4 – 73.3 |
75.4 |
<
Baseline |
70 (65
during examination period) (79
during the period of conducting the continuous noise monitoring) (8) |
No |
|
NMS-CA-9 |
Kong Yiu Mansion (4) |
69.4 – 70.9 |
69.2 |
55.9 –
66.0 |
75 |
No |
|
NMS-CA-10 |
Chat Ma Mansion |
75.6 – 76.2 |
76.6 |
< Baseline |
75 |
No |
|
Works Contract
1111 |
|
|
|
|
|
||
NM1(15) |
Carmel
Secondary School (South
Block) |
63.5 – 66.8 |
68.0 |
< Baseline |
70 (65
during examination period) (68 during the period of conducting the
continuous noise monitoring) (9) |
No |
|
NM2(15) |
No.
234 – 238 Chatham Road North (5) |
67.8 – 69.0 |
79.0 |
< Baseline |
75 (77) (10) |
No |
|
Works Contract
1112 (6) |
|
|
|
|
|
||
Works Contract
11240 (6) |
|
|
|
|
|
||
Notes:
(1)
Alternative monitoring location to Shek On House.
(2)
Alternative monitoring location to Canossa
Primary School (San Po Kong).
(3)
Alternative monitoring location to
Prosperity House.
(4)
Alternative monitoring location to Lucky
Building.
(5)
Alternative monitoring location to Wing
Fung Building.
(6)
No construction noise monitoring is
required under this contract.
(7)
The measured noise levels are corrected
against the corresponding baseline noise levels.
(8)
The Limit Level of 79 dB(A) was updated on
22 Aug 2013 as per the latest Construction Noise Mitigation Measures Plan
(CNMMP) and Continuous Noise Monitoring Plan (CNMP) which were approved by EPD.
(9)
The Limit of 68
dB(A) was updated on 20 Jan 2014 as per the latest CNMMP and CNMP which were
approved by EPD.
(10)
Daytime noise
Limit Level of 77 dB(A) applies during the continuous noise monitoring period.
(11)
The
construction noise monitoring works would be taken up by Works Contract 1106
since the completion of Works Contract 1107 in Feb 2018.
(12)
The cessation
of monitoring works at NMS-CA-1 was approved by EPD and the last monitoring was
conducted on 17 Jul 2018.
(13)
The temporary
cessation of monitoring works at NMS-CA-2 was approved by EPD in end-June 2019.
The last monitoring date was 24 Jun 2019.
(14)
The cessation
of monitoring works at NMS-CA-3, NMS-CA-4 and NMS-CA-5 was approved by EPD on
31 Jul 2019. The
last monitoring proposed on 31 Jul 2019 was
rescheduled to 1 Aug 2019 due to adverse weather and the hoist of
Typhoon Signal No.8 (Typhoon “Wipha”).
(15)
The cessation of monitoring works at NM1 and
NM2 were proposed on 25 Jul 2019 and EPD expressed no objection on 31 Jul 2019.
Table 2.4 Log for Environmental Complaints, Notification of
Summons and Successful Prosecutions
for the Reporting Month
Works Contract |
Environmental Complaints |
Notification of Summons |
Successful Prosecutions |
1106 |
0 |
0 |
0 |
1109 |
3 |
0 |
0 |
1111 |
0 |
0 |
0 |
1112 |
0 |
0 |
0 |
Table 3.1 Summary of Status of Required
Submissions for and
EP-438/2012/K
Submission |
Submission
date |
|
Condition 1.12 |
Notification
of Commencement Date of Construction of the Project |
1
Aug 2012 |
Condition 2.3 |
Notification
of Information of Community Liaison Groups |
13
Jul 2012 (1st submission) 31
Aug 2012 (2nd submission) 30
Nov 2012 (3rd submission) |
Condition 2.7 |
Management
Organisation of Main Construction Companies |
27
Jul 2012 (1st submission) 21
Aug 2012 (2nd submission) 19
Dec 2012 (3rd submission) 22
Jan 2013 (4th submission) 30
Apr 2013 (5th submission) 21
May 2013 (6th submission) |
Condition 2.8 |
Construction
Programme and EP Submission Schedule |
27
Jul 2012 |
Condition 2.9 |
Construction
Noise Mitigation Measures Plan (CNMMP) |
1
Aug 2012 (1st submission) 28
Sep 2012 (2nd submission) 30
Nov 2012 (3rd submission) 11
Jan 2013 (4th submission) 8
Feb 2013 (Approved) 26
Apr 2013 (6th submission) 11
Jun 2013 (7th submission) 12
Jul 2013 (Approved) 26
Jul 2013 (8th submission) 22
Aug 2013 (Approved) 23
Aug 2013 (9th submission) 13
Sep 2013 (Approved) 20
Jan 2014 (10th submission) 26 Feb 2014 (Approved) 31 Mar 2015 (Contract 1106 submission only) 13 Apr 2015 (Contract 1106 submission only) 15 Apr 2015 (Approved) |
Condition 2.10 |
Continuous
Noise Monitoring Plan (CNMP) |
1
Aug 2012 (1st submission) 28
Sep 2012 (2nd submission) 30
Nov 2012 (3rd submission) 11
Jan 2013 (4th submission) 8
Feb 2013 (Approved) 8
Feb 2013 (5th submission) 26
Apr 2013 (6th submission) 12
Jul 2013 (Approved) 26
Jul 2013 (8th submission) 22
Aug 2013 (Approved) 23
Aug 2013 (9th submission) 13
Sep 2013 (Approved) 20
Jan 2014 (10th submission) 26 Feb 2014 (Approved) 7 Oct 2014 (11th submission) 23 Oct 2014 (Approved) |
Condition 2.11 |
Construction
and Demolition Materials Management Plan (C&DMMP) |
6
Jul 2012 (1st submission) 12
Sep 2012 (2nd submission) 10
Oct 2012 (Approved) |
Condition 2.12 |
Sediment
Management Plan |
6
Jul 2012 (1st submission) 12
Sep 2012 (2nd submission) 5
Oct 2012 (3rd submission) 10
Oct 2012 (Approved) 4
Mar 2013 (4th submission) 9
May 2013 (5th submission) 24
Jul 2013 (6th submission) 26
Jul 2013 (Approved) |
Condition 2.13 |
Visual,
Landscape, Tree Planting & Tree Protection Plan |
6
Jul 2012 (1st submission) 30
Aug 2012 (2nd submission) 3
Oct 2012 (3rd submission) 13
Nov 2013 (Approved) 14
Nov 2012 (4th submission) 8
Feb 2013 (5th submission) 18
Mar 2013 (6th submission) 18
Jun 2013 (7th submission) 12
Jul 2013 (Approved) 23 Mar 2017 (8th submission) 7 Mar 2018 (9th submission) 30 Jul 2018 (10th submission) 28 Feb 2019 (11th submission) 5 Mar 2019 (12th submission) 29 May 2019 (13th submission) 19 Jul 2019 (14th submission) |
Condition 2.14 |
Transplantation
Proposal for Plant Species of Conservation Importance |
22
Aug 2012 (1st submission) 5
Oct 2012 (2nd submission) 26
Nov 2012 (3rd submission) 4
Dec 2012 (Approved) |
Condition 2.15 |
Conservation
Plan |
31
Jan 2013 (1st submission) 18
Mar 2013 (2nd submission) 24
Apr 2013 (Approved) |
Condition 2.16 |
Archaeological
Action Plan(s) (AAP(s)) for Works Contract 1109 |
10
Aug 2012 (1st submission) 3
Sep 2012 (2nd submission) 21
Sep 2012 (Approved) 11 Oct 2013 (3rd submission) 1
Nov 2013 (Approved) |
Condition 2.16 |
Archaeological
Action Plan(s) (AAP(s)) for Works Contract 1106 |
29
Jan 2013 (1st submission) 19
Mar 2013 (2nd submission) 8
Apr 2013 (Approved) |
Condition 2.23 |
Supplementary
Contamination Assessment Report for New Territories South Animal Centre |
28
Sep 2012 25
Oct 2012 (Approved) |
Condition 2.27 |
Operational
Ground-borne Noise Mitigation Measures Plan |
18 Mar 2016 (Batch 1 Version A submission) 28 Apr 2016 (Batch 1 Version B submission) 28 Apr 2016 (Batch 2 Version A submission) 1 Jun 2016 (Batch 1 Version C submission) 1 Jun 2016 (Batch 2 Version B submission) 23 Jun 2016 (Batch 1 Version D submission) 23 Jun 2016 (Batch 2 Version C submission) 15 Jul 2016 (Batch 1 Version D approved) 15 Jul 2016 (Batch 2 Version C approved) 15 Sep 2016 (Batch 3 Version A submission) 4 Oct 2016 (Batch 3 Version A approved) 8 Mar 2017 (Batch 4 Version A) 7 Apr 2017 (Batch 4 Version A approved) 7 Jun 2017 (Final) 20 Jul 2017 (Approved) |
Condition 2.28 |
As-built Drawings for Operational Ground-borne
Noise Mitigation Measures |
10 Aug 2017 (1st submission) |
Condition 2.30 |
As-built Drawings for Operational Air-borne Noise
Mitigation Measures |
4 Dec 2015 (1st
submission) 28 Dec 2015 (2nd submission) 4 Feb 2016 (Approved) 20 Mar 2018 (3rd submission) |
Condition 2.31 |
Performance
Test Report for Train Noise – Operational Airborne Railway and
Ground-borne Noise |
15
Nov 2018 (Batch 1 Version A submission) 30
Jan 2019 (Batch 2 Version A submission) 29
Mar 2019 (Batch 1 Version A & Batch 2 Version B submission) 15 April 2019 (Approved) |
Condition 2.32 |
Proposal
for Updating Maximum Allowable Sound Power Levels of Fixed Plant Sources |
30
Jan 2019 (Batch 1 Version A submission) 27
Feb 2019 (Batch 1 Version B submission) 13
Mar 2019 (Batch 1 Version B approved) 15
Mar 2019 (Batch 2 Version A submission) 8
Apr 2019 (Batch 2 Version A approved) 24
April 2019 (Batch 3 & 4 Version A submission) 21
May 2019 (Batch 3 Version B submission) 11
Jun 2019 (Batch 3 Version B & Batch 4 Version A approved) 21
Jun 2019 (Batch 5 Version A submission) 17
Jul 2019 (Batch 5 Version A approved) 19
Jul 2019 (Batch 6 Version A submission) 26
Jul 2019 (Batch 7 Version A submission) |
Condition 2.32 |
Fixed
Plant Noise Audit Report |
30
Jan 2019 (Batch 1 Version A submission) 15
Mar 2019 (Batch 1 Version B submission) 16
April 2019 (Batch 2 Version A submission) 24
Jun 2019 (Batch 3 Version A and Batch 4 Version A submission) |
Condition 2.33 |
As-built Drawings for Landscape and Visual
Mitigation Measures |
4 Dec 2015 (1st
submission) 28 Dec 2015 (2nd submission) 4 Feb 2016 (Approved) 22 Aug 2018 (3rd submission) 5 Nov 2018 (4th submission) |
Condition
2.36 |
Contamination Assessment Plan (CAP) for the
Temporary Magazine Site at TKO Area 137 |
23 Mar 2016 (1st submission) 20 Apr 2016 (2nd submission) 22 Apr 2016 (Approved) |
Condition
2.36 |
Contamination Assessment Report (CAR) for the
Temporary Magazine Site at TKO Area 137 |
19 May 2016 (1st submission) 3 Jun 2016 (2nd submission) 15 Jun 2016 (Approved) |
Condition 3.1 |
Proposal for Termination of Environmental
Monitoring and Audit (EM&A) Programme for Kai Tak
Barging Point Facilities |
7 Oct 2016 (Approved) |
Condition 3.1 |
Proposal for Cessation of EM&A Works at Hin Keng |
9 May 2018 (1st submission) 16 July 2018 (Approved) |
Condition 3.1 |
Proposal for Cessation of EM&A Programme at
Diamond Hill Station |
25 July 2019 (1st submission) 31 July 2019 (Approved) |
Condition 3.1 |
Proposal for Cessation of EM&A Programme at
Hung Hom North Approach Tunnels |
25 July 2019 (1st submission) 31 July 2019 (Approved) |
Condition 3.3 |
Baseline
Monitoring Report (Works Contract 1109 - Stations and Tunnels of Kowloon City
Section ) |
27
Jul 2012 |
Condition 3.3 |
Baseline
Monitoring Report (Works Contract 1108A – Kai Tak
Barging Point Facilities) |
31
Jul 2012 |
Condition 3.3 |
Baseline
Monitoring Report (Works Contracts 1103, 1106 and 1111 – Hin
Keng to Diamond Hill Tunnels, Diamond Hill Station,
and Hung Hom North Approach Tunnels) |
19
Oct 2012 |
Condition 3.4 |
Monthly
EM&A Reports No.
1-81 Monthly
EM&A Report No. 82 |
Reported in previous Monthly EM&A Reports 12 Jul 2019 |
Table
3.2 Summary of Status of Required Submissions for EP-437/2012/A
EP Condition (EP-437/2012/A) |
Submission |
Submission date |
Condition 1.11 |
Notification of
Commencement Date of Construction of the Project |
30 Nov 2012 |
Condition 2.3 |
Notification of
Information of Community Liaison Groups |
30 Nov 2012 |
Condition 2.5 |
Management
Organisation of Main Construction Companies |
19 Dec 2012 (1st
submission) 30 Apr 2013 (2nd
submission) |
Condition 2.6 |
Construction
Programme and EP Submission Schedule |
19 Dec 2012 |
Condition 2.7 |
Construction
Noise Mitigation Measures Plan (CNMMP) |
30 Nov 2012 (1st
submission) 8 Feb 2013 (Approved ) 26 Apr 2013 (2nd
submission) 11 Jun 2013 (3rd
submission) 27 Aug 2013
(Approved) 20 Jan 2014 (4th
submission) 28 Apr 2016 (Approved) |
Condition 2.8 |
Continuous Noise
Monitoring Plan (CNMP) |
30 Nov 2012 (1st
submission) 11 Jan 2013 (2nd
submission) 8 Feb 2013
(Approved) 20 Jan 2014 (3rd
submission) |
Condition 2.9 |
Construction and
Demolition Materials Management Plan (C&DMMP) |
6 Jul 2012 (1st
submission) 12 Sep 2012 (2nd
submission) 15 Oct 2012
(Approved) |
Condition 2.10 |
Sediment
Management Plan |
6 Jul 2012 (1st
submission) 12 Sep 2012 (2nd
submission) 5 Oct 2012 (3rd
submission) 15 Oct 2012 (Approved) |
Condition 2.11 |
Visual,
Landscape, Tree Planting & Tree Protection Plan (VLTTP) |
14 Nov 2012 (1st
submission) 8 Feb 2013 (2nd
submission) 4 Feb 2015 (3rd
submission) 26 Jun 2015 (4th submission) 12 May 2017 (5th submission) 17 Apr 2018 (6th submission) |
Condition 2.16 |
Operational
Ground-borne Noise Mitigation Measures Plan |
23 Mar 2017 (1st submission) 17 May 2017 (2nd submission) 28 Jun 2017 (3rd submission) 20 Jul 2017 (Approved) |
Condition 2.21 |
Proposal for
Updating Maximum Allowable Sound Power Levels of Fixed Plant Sources |
26 Jul 2019
(Batch 1 Version A submission) |
Condition 3.3 |
Baseline
Monitoring Report (Works Contracts 1103, 1106 and 1111 – Hin
Keng to Diamond Hill Tunnels, Diamond Hill Station,
and Hung Hom North Approach Tunnels) |
19 Oct 2012 |
Condition 3.4 |
Monthly EM&A
Reports No. 5-81 Monthly EM&A
Report No. 82 |
Reported in previous Monthly EM&A Reports 12 Jul 2019 |