Table of Contents

1......... Introduction. 1

1.1          Background. 1

1.2          Project Programme. 1

1.3          Purpose of the Report 1

2......... Environmental Monitoring and Audit. 1

3......... implementation status on the environmental protection requirements. 1

 

List of Tables

Table 1.1              Summary of Awarded Works Contracts

Table 2.1              Summary of Major Construction Activities in the Reporting Period

Table 2.2              Summary of 24-Hour TSP Monitoring Results in the Reporting Period

Table 2.3              Summary of Construction Noise Monitoring Results in the Reporting Period

Table 2.4              Log for Environmental Complaints, Notification of Summons and Successful Prosecutions for the Reporting Month

Table 3.1              Summary of Status of Required Submissions for and EP-438/2012/K

Table 3.2              Summary of Status of Required Submissions for EP-437/2012

 

List of Appendices

Appendix A         57th Monthly EM&A Report for Works Contract 1109 – Stations and Tunnels of Kowloon City Section

Appendix B         53rd Monthly EM&A Report for Works Contract 1111 – Hung Hom North Approach Tunnels

Appendix C         52nd Monthly EM&A Report for Works Contract 1103 – Hin Keng to Diamond Hill Tunnels

Appendix D         51st Monthly EM&A Report for Works Contract 1106 – Diamond Hill Station

Appendix E         49th Monthly EM&A Report for Works Contract 1107 – Diamond Hill to Kai Tak Tunnels

Appendix F          48th Monthly EM&A Report for Works Contract 1112 – Hung Hom Station and Stabling Sidings

Appendix G         48th Monthly EM&A Report for Works Contract 1108 – Kai Tak Station and Associated Tunnels

Appendix H         44th Monthly EM&A Report for Works Contract 1102 – Hin Keng Station and Approach Structures

 

                                                                                                   


1                    Introduction

1.1               Background

1.1.1         The Shatin to Central Link (SCL) is a 17km extension of the existing Ma On Shan Line (MOL) and East Rail Line (EAL) comprising (i) The East-West Corridor which extends the MOL from Tai Wai to Hung Hom via East Kowloon to connect with the West Rail Line (WRL) at Hung Hom Station (HUH) and Stabling Sidings at Hung Hom Freight Yard (HHS); and (ii) The North-South Corridor which is an extension of the East Rail Line (EAL) at Hung Hom across the harbour to Admiralty Station (ADM).

1.1.2         Shatin to Central Link – Tai Wai to Hung Hom Section [SCL (TAW-HUH)] and Shatin to Central Link – Mong Kok East to Hung Hom Section [SCL (MKK-HUH) (hereafter referred to as “the Project”) are parts of the SCL. Shatin to Central Link – Stabling Sidings at Hung Hom Freight Yard [SCL (HHS)] is a proposed stabling sidings option for SCL (TAW – HUH) at the former freight yard in Hung Hom.

1.1.3         The Environmental Impact Assessment (EIA) Reports for SCL (TAW-HUH) (Register No.: AEIAR-167/2012), SCL (MKK-HUH) (Register No.: AEIAR-165/2012) and SCL (HHS) (Register No.: AEIAR-164/2012) were approved on 17 February 2012 under the Environmental Impact Assessment Ordinance (EIAO). Following the approval of the EIA Reports, two Environmental Permits (EPs) were granted on 22 March 2012, one covers SCL (TAW-HUH) and SCL (HHS) (EP No: EP-438/2012) and the other covers SCL (MKK-HUH) and SCL (HHS) (EP No.: EP-437/2012), for their construction and operation. Variations of environmental permit (VEP) was subsequently applied for EP-438/2012 and the latest Environmental Permit (EP No: EP-438/2012/K) was issued by Director of Environmental Protection (DEP) on 4 October 2016.

 

1.2               Project Programme

1.2.1         Ten civil construction works contracts of the Project have been awarded since July 2012. The construction of the Project commenced in September 2012 and is expected to complete in 2019 tentatively. Table 1.1 summarises the information of the awarded Works Contracts.

Table 1.1             Summary of Awarded Works Contracts

Works Contract

Description

Construction Start Date

Contractor

Environmental Team

1101(1)

Ma On Shan Line Modification Works

December 2012

Sun Fook Kong Joint Venture

(SFKJV)

ANewR Consulting Ltd. (ANewR)

1102

Hin Keng Station and Approach Structures

October 2013

Penta-Ocean Construction Co. Ltd.

Cinotech Consultants Ltd. (Cinotech)

1103

Hin Keng to Diamond Hill Tunnels

February 2013

Vinci Construction Grands Projets

Ove Arup & Partners Hong Kong Ltd. (Arup)

1106

Diamond Hill Station

March 2013

Leader Joint Venture

Cinotech Consultants Ltd. (Cinotech)

1107

Diamond Hill to Kai Tak Tunnels

May 2013

Chun Wo - SELI Joint Venture

Cinotech Consultants Ltd. (Cinotech)

1108

Kai Tak Station and Associated Tunnels

June 2013

Kaden -Chun Wo Joint Venture

Environmental Pioneers & Solutions Ltd.

1108A(2)

Kai Tak Barging Point Facilities

September 2012

Concentric – Hong Kong River Joint Venture (CCL-HKR JV)

Cinotech Consultants Ltd. (Cinotech)

1109

Stations and Tunnels of Kowloon City Section

September 2012

Samsung-Hsin Chong JV (SSHCJV)

ERM-Hong Kong Limited (ERM)

1111

Hung Hom North Approach Tunnels

January 2013

Gammon-Kaden SCL1111 JV

AECOM Asia Co. Ltd.

1112

Hung Hom Station and Stabling Sidings

June 2013

Leighton Contractors (Asia) Limited

SMEC Asia Ltd., HK

Notes:

(1)        All construction works (works areas at Tai Wai Mei Tin Road and the offsite temporary storage areas) under Works Contract 1101 were completed on 29 February 2016.

(2)        All construction works (Kai Tak Barging Point Facilities) under Works Contract 1108A were completed on 29 September 2016.

 

1.3               Purpose of the Report

1.3.1         The Environmental Monitoring and Audit (EM&A) programme for the Project commenced in September 2012. This is the fifty-seventh EM&A Report for the Project which summarises the EM&A works undertaken by the respective Contractor’s ETs during the period from 1 to 31 May 2017.

 

2                    Environmental Monitoring and Audit

2.1.1         The construction of SCL has been divided into different civil construction works contracts which are covered by EP No. EP-437/2012 and/or EP-438/2012/K. As per the EP Conditions, EM&A Reports for the works contracts as shown in the table below have been prepared by the respective Contractor’s ETs.

Works Contract

Contract Title

Works Covered in Environmental Permit No.

1101

Ma On Shan Modification Works

EP-438/2012/K

1102

Hin Keng Station and Approach Structures

EP-438/2012/K

1103

Hin Keng to Diamond Hill Tunnels

EP-438/2012/K

1106

Diamond Hill Station

EP-438/2012/K

1107

Diamond Hill to Kai Tak Tunnels

EP-438/2012/K

1108

Kai Tak Station and Associated Tunnels

EP-438/2012/K

1108A

Kai Tak Barging Point Facilities

EP-438/2012/K

1109

Stations and Tunnels of Kowloon City Section

EP-438/2012/K

1111

Hung Hom North Approach Tunnels

EP-437/2012 & EP-438/2012/K

1112

Hung Hom Station and Stabling Sidings

EP-437/2012 & EP-438/2012/K

 

2.1.2         The EM&A Reports for Works Contracts 1109, 1111, 1103, 1106, 1107, 1112, 1108, and 1102, prepared by the respective Contractor’s ETs are provided in Appendices A to H, respectively. The EM&A Reports provide details of the project information, EM&A requirements, impact monitoring and audit results for the corresponding Contracts.

2.1.3         A summary of the major construction activities undertaken by the respective Contractors of various Works Contracts during the reporting period are presented in Table 2.1.

 

Table 2.1             Summary of Major Construction Activities in the Reporting Period

Works Contract

Site

Construction Activities

1102

Hin Keng Station and Approach Structures

·         Soft Landscaping;

·         ABWF works at Hin Keng Station;

·         Modification of Retaining Wall and Installation of Noise Barrier;

·         Hard Landscape; and

·        E&M Works

1103

Diamond Hill Area

·        Underground remedial works

Hin Keng Area

·        Tunnel lining, partition walls, dividing slabs, drains, walkways and site formation

Fung Tak Area

·        Tunnels connection, RC concrete, ELS work, sheet piling for retaining wall and RRIW for PTT

Ma Chai Hang Area

·        Central core, ventilation tunnel, C&S works and ABWF works

Shui Chuen O

·        Storage area

1106

Diamond Hill Station Area

·         Construct Level U1 Wall and structural steel erection;

·         ABWF works at SCL-DIH station area;

·         Foundation works, temporary road diversion, TTA for site access and temporary footpath diversion at Choi Hung Road;

·         Excavation and lateral support works at Lung Cheung Road;

·         Construct Base Slab at MOE near Entrance B; and

·         Drilling works and raking pile installation at Entrance A2.

1107

Tunnel section next to Kai Tak Station

·         Reinstatement and Backfilling works of Drainage.

1108

Kai Tak Station

·         Open cut tunnel: DT and UT general cleaning and defect rectification, walkway top-up remedial works at Section A of DT and UT.

·         Cut and cover tunnel: DT and UT general cleaning and defect rectification, walkway top-up remedial works at Section A & B of DT and UT, and access shaft closure at UT completed.

·         Station: Drainage work at all area, leveling to F.F.L. in Area 3, installation of roof cladding at Entrance A, B & D, EVA construction for the first 2 portion, accessible ramp at DEE and Planter at Entrance A Cast and installation of glass canopy at DEE and SEE.

1109

Ma Tau Wai (MTW) Works Area

·         Along Ma Tau Wai Road and TKW/MTW Road Garden – Station construction; ABWF works; and EEP construction

To Kwa Wan (TKW) Works Area

·         Olympic Garden Construction of station entrance and new Pier 46;

·         TKW Station Construction of TKW station, and backfilling;

·         Tam Kung Road Sump pit construction; and

·         Nam Kok Road Construction of station entrance

1111

Mong Kok Freight Terminal (1)

·        All construction activities were completed in May 2015

Ho Man Tin

·         EVA construction

NSL 3 - 8

·         Concreting works, form work erection, reinforcement fixing, backfill, road & drainage construction, excavation, pipe laying

OB2

·         Backfill, TB1 dismantling, watermain diversion, upstand wall modification, OB2 bridge jacking and bearing replacement and parapet wall construction

OB2A

·         OB2A bridge reinstatement, precast parapet installation, bearing replacement, backfilling

NSL 9 & Oi Sen Path

·         Backfilling, drainage work, Scaffolding platform erection, dismantling of scaffolding, lifting works, temporary working platform removal, ELS removal, tunnel works, rock breaking

EWL 7 - 9

·         Reinstatement, road diversion, backfilling, steel deck dismantling

1112

Hong Hom (HUH and HHS) Works Area

·         Building services works at SAT

·         EVA Roadworks at SAT

·         Demolition works of bulkhead door adjacent to existing West Rail Stub Tunnel at SAT

·         Construction of tunnel structure at HUH, NAT

·         Drainage work at HHS

·         Platform ABWF and E&M works at HUH

·         Utility works at NAT

·        Modification works at Concourse level, mid-level walkway

Note:

(1)         Construction works were completed.

 

2.1.4         Impact monitoring for air quality and construction noise were conducted in accordance with the EM&A Manual in the reporting period. Continuous noise monitoring was not required in the reporting period for all Works Contracts according to the Continuous Noise Monitoring Plan (CNMP). The air quality and construction noise for this reporting month are summarised in Tables 2.2 and 2.3. Details of the monitoring requirements, locations, equipment, methodology and QA/QC procedures are presented in the EM&A Reports as provided in Appendices A to H.

2.1.5         Water quality monitoring was not carried out during this reporting period since no dredging activity was conducted in the reporting month.

2.1.6         An environmental compliant regarding dust issue under Works Contract 1111 was referred by EPD on 8 May 2017. Investigations were conducted and reported in the EM&A Report. A notification of summon under Works Contract 1108 was issued on 20 February 2017. The contractor attended to the court on 24 May 2017. The next court days were scheduled on 14 to 16 August 2017. No exceedance of action and limit levels were recorded during the reporting period. Log for environmental complaints, notification of summons and successful prosecutions are provided in Table 2.4.

2.1.7         Regular site inspections were conducted by the respective Contractor’s ETs on a weekly basis to check the implementation of environmental pollution control and mitigation measures for the Project. No non-conformance was identified in the reporting period.


 

Table 2.2             Summary of 24-Hour TSP Monitoring Results in the Reporting Period

Monitoring Station ID

Location

TSP Concentration (mg/m3)

Action Level

(mg/m3)

Limit Level (mg/m3)

Exceedance due to the Project Construction

(Yes/No)

Works Contract 1102 and 1103

 

 

 

 

DMS-1

C.U.H.K.A.A. Thomas Cheung School

21.9-59.1

148.7

260

No

Works Contract 1103

 

 

 

 

DMS-2

Price Memorial Catholic Primary School

23.2-83.0

167.4

260

No

Works Contracts 1103 and 1106

 

 

 

 

DMS-3

Hong Kong S.K.H Nursing Home (1)

29.4-67.5

159.1

260

No

Works Contract 1106 and 1107

 

 

 

 

DMS-4

Block 1, Rhythm Garden

28.2-82.9

160.4

260

No

Works Contract 1108 (5)

 

 

 

 

Works Contract 1109

 

 

 

 

DMS-6

Katherine Building (2)

62 – 65

156.8

260

No

DMS-7

Parc 22 (3)(10)

-

166.7

260

No

DMS-8

SKH Good Shepherd Primary School

63 – 78

152.2

260

No

DMS-9

No. 12 Pau Chung Street (4)(9)

53 – 83

160.9

260

No

DMS-10

Chat Ma Mansion

58 – 75

170.4

260

No

Works Contract 1111

 

 

 

 

AM1(6)

No. 234 – 238 Chatham Road North (7)

30.5 – 91.1

183.9

260

No

Works Contract 1112

 

 

 

 

AM2

Site Boundary of Finger Pier Adjacent To Harbourfront Horizon (8)

38.0 – 45.9

182

260

No

Notes:

(1)         Alternative monitoring location to Shek On House

(2)         Alternative monitoring location to Prosperity House

(3)         Alternative monitoring location to Skytower Tower 2

(4)         Alternative monitoring location to Lucky Building

(5)         No TSP monitoring is required under this contract

(6)         AM1 named as HUH-1-3 in SCL(TAW-HUH) and SCL(HHS) EIA Reports.

(7)         Alternative monitoring location to Wing Fung Building

(8)         Alternative monitoring location to Harbourfront Horizon

(9)         24-hour averaged dust monitoring at DMS-9 No. 26 Kowloon City Road (alternative location of Lucky Building) has been suspended since March 2014 due to denied access by the occupant of the premise. However, No. 12 Pau Chung Street, as an alternative monitoring location, was formally approved by EPD on 19 May 2014. Impact dust monitoring was resumed on 12 June 2014.

(10)     24-hour averaged dust monitoring at DMS-7 Parc 22 (alternative monitoring location of Skytower Tower 2) has been temporary suspended since 13 December 2016 due to request from the management office.


Table 2.3             Summary of Construction Noise Monitoring Results in the Reporting Period

Monitoring Station ID

Location

Noise Level (LAeq,30mins, dB(A))

Limit Level

(dB(A))

Exceedance due to the Project Construction

(Yes/No)

Measured

Baseline

Corrected (7)

Works Contract 1102 and 1103

 

 

 

 

 

NMS-CA-1

C.U.H.K.A.A. Thomas Cheung School

51.6-55.8

57.0

< Baseline

70

(65 during examination period)

No

Works Contract 1103

 

 

 

 

 

NMS-CA-2

Price Memorial Catholic

Primary School

60.0-62.0

66.0

< Baseline

70

(65 during examination period)

No

Works Contracts 1103 and 1106

 

 

 

 

 

NMS-CA-3

Hong Kong S.K.H

Nursing Home (1)

71.8-72.6

73.0

< Baseline

70

No

Works Contract 1106 and 1107

 

 

 

 

 

NMS-CA-4

Block 1, Rhythm Garden (north-eastern façade)

71.2-72.4

71.0

57.7-66.8

75

No

NMS-CA-5

Block 1, Rhythm Garden (northern façade)(2)

70.3-71.4

74.0

<Baseline

70

(65 during examination period)

No

Works Contract 1108 (6)

 

 

 

 

 

Works Contract 1109

 

 

 

 

 

NMS-CA-6

No. 16-23 Nam Kok Road (3)

62.9-63.2

76.1

< Baseline

75

No

NMS-CA-7

Skytower Tower 2

65.2-66.1

70.0

< Baseline

75

No

NMS-CA-8

SKH Good Shepherd

Primary School

71.8-73.0

75.4

< Baseline

70

(65 during examination period)

(79 during the period of conducting the continuous noise monitoring) (8)

No

NMS-CA-9

Kong Yiu Mansion (4)

68.4-69.2

69.2

≤ Baseline

75

No

NMS-CA-10

Chat Ma Mansion

75.6-76.8

76.6

< Baseline-63.3

75

No

Works Contract 1111

 

 

 

 

 

NM1

Carmel Secondary School

(South Block)

65.2-67.4

68.0

< Baseline

70

(65 during examination period)

(68 during the period of conducting the continuous noise monitoring) (9)

No

NM2

No. 234 – 238 Chatham Road North (5)

68.6-69.8

79.0

< Baseline

75 (77) (10)

No

Works Contract 1112 (6)

 

 

 

 

 

Notes:

(1)         Alternative monitoring location to Shek On House.

(2)         Alternative monitoring location to Canossa Primary School (San Po Kong).

(3)         Alternative monitoring location to Prosperity House.

(4)         Alternative monitoring location to Lucky Building.

(5)         Alternative monitoring location to Wing Fung Building.

(6)         No construction noise monitoring is required under this contract.

(7)         The measured noise levels are corrected against the corresponding baseline noise levels.

(8)        The Limit Level of 79 dB(A) was updated on 22 Aug 2013 as per the latest Construction Noise Mitigation Measures Plan (CNMMP) and Continuous Noise Monitoring Plan (CNMP) which were approved by EPD.

(9)        The Limit of 68 dB(A) was updated on 20 Jan 2014 as per the latest CNMMP and CNMP which were approved by EPD.

(10)     Daytime noise Limit Level of 77 dB(A) applies during the continuous noise monitoring period.

 

 

 

 


Table 2.4             Log for Environmental Complaints, Notification of Summons and Successful Prosecutions for the Reporting Month

Works Contract

Environmental Complaints

Notification of Summons

Successful Prosecutions

1102

0

0

0

1103

0

0

0

1106

0

0

0

1107

0

0

0

1108

0

0

0

1109

0

0

0

1111

1

0

0

1112

0

0

0

 

 

 


 

3                    implementation status on the environmental protection requirements

 

3.1.1         The respective Contractors have implemented all mitigation measures and requirements as stated in the EIA Reports, EM&A Manuals and EPs (EP-437/2012 and EP-438/2012/K). The status of required submissions under the EPs as of the reporting period are summarised in Tables 3.1 and 3.2.

Table 3.1             Summary of Status of Required Submissions for and EP-438/2012/K

EP Condition

(EP-438/2012/K)

Submission

Submission date

Condition 1.12

Notification of Commencement Date of Construction of the Project

1 Aug 2012

Condition 2.3

Notification of Information of Community Liaison Groups

13 Jul 2012 (1st submission)

31 Aug 2012 (2nd submission)

30 Nov 2012 (3rd submission)

Condition 2.7

Management Organisation of Main Construction Companies

27 Jul 2012 (1st submission)

21 Aug 2012 (2nd submission)

19 Dec 2012 (3rd submission)

22 Jan 2013 (4th submission)

30 Apr 2013 (5th submission)

21 May 2013 (6th submission)

Condition 2.8

Construction Programme and EP Submission Schedule

27 Jul 2012

Condition 2.9

Construction Noise Mitigation Measures Plan (CNMMP)

1 Aug 2012 (1st submission)

28 Sep 2012 (2nd submission)

30 Nov 2012 (3rd submission)

11 Jan 2013 (4th submission)

8 Feb 2013 (Approved)
8 Feb 2013 (5th submission)

26 Apr 2013 (6th submission)

11 Jun 2013 (7th submission)

12 July 2013 (Approved)

26 July 2013 (8th submission)

22 Aug 2013 (Approved)

23 Aug 2013 (9th submission)

13 Sept 2013 (Approved)

20 Jan 2014 (10th submission)

26 Feb 2014 (Approved)

31 Mar 2015 (Contract 1106 submission only)

13 Apr 2015 (Contract 1106 submission only)

15 Apr 2015 (Approved)

Condition 2.10

Continuous Noise Monitoring Plan (CNMP)

1 Aug 2012 (1st submission)

28 Sep 2012 (2nd submission)

30 Nov 2012 (3rd submission)

11 Jan 2013 (4th submission)

8 Feb 2013 (Approved)

8 Feb 2013 (5th submission)

26 Apr 2013 (6th submission)

11 Jun 2013 (7th submission)

12 July 2013 (Approved)

26 July 2013 (8th submission)

22 Aug 2013 (Approved)

23 Aug 2013 (9th submission)

13 Sept 2013 (Approved)

20 Jan 2014 (10th submission)

26 Feb 2014 (Approved)

7 Oct 2014 (11th submission)

23 Oct 2014 (Approved)

Condition 2.11

Construction and Demolition Materials Management Plan (C&DMMP)

6 Jul 2012 (1st submission)

12 Sep 2012 (2nd submission)

10 Oct 2012 (Approved)

Condition 2.12

Sediment Management Plan

6 Jul 2012 (1st submission)

12 Sep 2012 (2nd submission)

5 Oct 2012 (3rd submission)

10 Oct 2012 (Approved)

4 Mar 2013 (4th submission)

9 May 2013 (5th submission)

24 July 2013 (6th submission)

26 July 2013 (Approved)

Condition 2.13

Visual, Landscape, Tree Planting & Tree Protection Plan

6 Jul 2012 (1st submission)

30 Aug 2012 (2nd submission)

3 Oct 2012 (3rd submission)

13 Nov 2013 (Approved)

14 Nov 2012 (4th submission)

8 Feb 2013 (5th submission)

18 Mar 2013 (6th submission)

18 June 2013 (7th submission)

12 July 2013 (Approved)

23 Mar 2017 (8th submission)

Condition 2.14

Transplantation Proposal for Plant Species of Conservation Importance

22 Aug 2012 (1st submission)

5 Oct 2012 (2nd submission)

26 Nov 2012 (3rd submission)

4 Dec 2012 (Approved)

Condition 2.15

Conservation Plan

31 Jan 2013 (1st submission)

18 Mar 2013 (2nd submission)

24 Apr 2013 (Approved)

Condition 2.16

Archaeological Action Plan(s) (AAP(s)) for Works Contract 1109

10 Aug 2012 (1st submission)

3 Sep 2012 (2nd submission)

21 Sep 2012 (Approved)

11 Oct 2013 (3rd submission)

1 Nov 2013 (Approved)

Condition 2.16

Archaeological Action Plan(s) (AAP(s)) for Works Contract 1106

29 Jan 2013 (1st submission)

19 Mar 2013 (2nd submission)

8 Apr 2013 (Approved)

Condition 2.23

Supplementary Contamination Assessment Report for New Territories South Animal Centre

28 Sep 2012

25 Oct 2012 (Approved)

Condition 2.27

Operational Ground-borne Noise Mitigation Measures Plan

18 Mar 2016 (Batch 1 Version A submission)

28 Apr 2016 (Batch 1 Version B submission)

28 Apr 2016 (Batch 2 Version A submission)

1 Jun 2016 (Batch 1 Version C submission)

1 Jun 2016 (Batch 2 Version B submission)

23 Jun 2016 (Batch 1 Version D submission)

23 Jun 2016 (Batch 2 Version C submission)

15 Jul 2016 (Batch 1 Version D approved)

15 Jul 2016 (Batch 2 Version C approved)

15 Sep 2016 (Batch 3 Version A submission)

4 Oct 2016 (Batch 3 Version A approved)

8 Mar 2017 (Batch 4 Version A)

7 April 2017 (Batch 4 Version A approved)

Condition 2.30

As-built Drawings for Operational Air-borne Noise Mitigation Measures

4 Dec 2015 (1st submission)

28 Dec 2015 (2nd submission)

4 Feb 2016 (Approved)

Condition 2.33

As-built Drawings for Landscape and Visual Mitigation Measures

4 Dec 2015 (1st submission)

28 Dec 2015 (2nd submission)

4 Feb 2016 (Approved)

Condition 2.36

Contamination Assessment Plan (CAP) for the Temporary Magazine Site at TKO Area 137

23 Mar 2016 (1st submission)

20 Apr 2016 (2nd submission)

22 Apr 2016 (Approved)

Condition 2.36

Contamination Assessment Report (CAR) for the Temporary Magazine Site at TKO Area 137

19 May 2016 (1st submission)

3 Jun 2016 (2nd submission)

15 Jun 2016 (Approved)

 

Condition 3.1

Proposal for Termination of Environmental Monitoring and Audit (EM&A) Programme for Kai Tak Barging Point Facilities

7 Oct 2016 (Approved)

 

Condition 3.3

Baseline Monitoring Report (Works Contract 1109 - Stations and Tunnels of Kowloon City Section )

27 Jul 2012

Condition 3.3

Baseline Monitoring Report (Works Contract 1108A – Kai Tak Barging Point Facilities)

31 Jul 2012

Condition 3.3

Baseline Monitoring Report (Works Contracts 1103, 1106 and 1111 – Hin Keng to Diamond Hill Tunnels, Diamond Hill Station, and Hung Hom North Approach Tunnels)

19 Oct 2012

Condition 3.4

Monthly EM&A Reports No. 1-55

 

 

Monthly EM&A Report No. 56

 

 

Reported in previous Monthly EM&A Reports

 

12 May 2017

 

 

 


 

Table 3.2             Summary of Status of Required Submissions for EP-437/2012

EP Condition

(EP-437/2012)

Submission

Submission date

Condition 1.11

Notification of Commencement Date of Construction of the Project

30 Nov 2012

Condition 2.3

Notification of Information of Community Liaison Groups

30 Nov 2012

Condition 2.5

Management Organisation of Main Construction Companies

19 Dec 2012 (1st submission)

30 Apr 2013 (2nd submission)

Condition 2.6

Construction Programme and EP Submission Schedule

19 Dec 2012

Condition 2.7

Construction Noise Mitigation Measures Plan (CNMMP)

30 Nov 2012 (1st submission)

8 Feb 2013 (Approved )

26 Apr 2013 (2nd submission)

11 Jun 2013 (3rd submission)

27 Aug 2013 (Approved)

20 Jan 2014 (4th submission)

28 Apr 2016 (Approved)

Condition 2.8

Continuous Noise Monitoring Plan (CNMP)

30 Nov 2012 (1st submission)

11 Jan 2013 (2nd submission)

8 Feb 2013 (Approved)

20 Jan 2014 (3rd submission)
28 Apr 2016 (Approved)

Condition 2.9

Construction and Demolition Materials Management Plan (C&DMMP)

6 Jul 2012 (1st submission)

12 Sep 2012 (2nd submission)

15 Oct 2012 (Approved)

Condition 2.10

Sediment Management Plan

6 Jul 2012 (1st submission)

12 Sep 2012 (2nd submission)

5 Oct 2012 (3rd submission)

15 Oct 2012 (Approved)

Condition 2.11

Visual, Landscape, Tree Planting & Tree Protection Plan (VLTTP)

14 Nov 2012 (1st submission)

8 Feb 2013 (2nd submission)

4 Feb 2015 (3rd submission)

26 Jun 2015 (4th submission)

12 May 2017 (5th submission)

Condition 2.16

Operational Ground-borne Noise Mitigation Measures Plan

23 Mar 2017 (1st submission)

17 May 2017 (2nd submission)

Condition 3.3

Baseline Monitoring Report (Works Contracts 1103, 1106 and 1111 – Hin Keng to Diamond Hill Tunnels, Diamond Hill Station, and Hung Hom North Approach Tunnels)

19 Oct 2012

Condition 3.4

Monthly EM&A Reports No. 5-55

 

 

Monthly EM&A Report No. 56

Reported in previous Monthly EM&A Reports

 

12 May 2017

 

1