Table of
Contents
2......... Environmental Monitoring and Audit
3......... implementation status on the
environmental protection requirements
List of
Tables
Table
1.1 Summary
of Awarded Works Contracts
Table 2.1 Summary of Major Construction
Activities in the Reporting Period
Table 2.2 Summary of 24-Hour TSP Monitoring
Results in the Reporting Period
Table 2.3 Summary of Construction Noise
Monitoring Results in the Reporting Period
Table 3.1 Summary of Status of Required
Submissions for and EP-438/2012/K
Table 3.2 Summary of Status of Required
Submissions for EP-437/2012
List of
Appendices
Appendix B 53rd Monthly
EM&A Report for Works Contract 1111 – Hung Hom North Approach Tunnels
Appendix C 52nd Monthly
EM&A Report for Works Contract 1103 – Hin Keng to Diamond Hill Tunnels
Appendix D 51st Monthly EM&A Report for Works Contract
1106 – Diamond Hill Station
Appendix E 49th Monthly EM&A Report for Works Contract
1107 – Diamond Hill to Kai Tak
Tunnels
Appendix F 48th Monthly EM&A Report for Works Contract
1112 – Hung Hom Station and Stabling Sidings
Appendix G 48th Monthly EM&A Report for Works Contract
1108 – Kai Tak Station and Associated Tunnels
Table
1.1 Summary of Awarded Works Contracts
Works
Contract |
Description |
Construction
Start Date |
Contractor |
Environmental
Team |
1101(1) |
Ma On Shan Line Modification Works |
December 2012 |
Sun Fook Kong
Joint Venture (SFKJV) |
ANewR Consulting Ltd. (ANewR) |
1102 |
Hin Keng Station
and Approach Structures |
October 2013 |
Penta-Ocean Construction Co. Ltd. |
Cinotech Consultants Ltd. (Cinotech) |
1103 |
Hin Keng to
Diamond Hill Tunnels |
February 2013 |
Vinci Construction Grands Projets |
Ove Arup & Partners Hong Kong Ltd.
(Arup) |
1106 |
Diamond Hill Station |
March 2013 |
Leader Joint Venture |
Cinotech Consultants Ltd. (Cinotech) |
1107 |
Diamond Hill to Kai Tak
Tunnels |
May 2013 |
Chun Wo - SELI Joint Venture |
Cinotech Consultants Ltd. (Cinotech) |
1108 |
Kai Tak
Station and Associated Tunnels |
June 2013 |
Kaden -Chun Wo Joint Venture |
Environmental Pioneers & Solutions
Ltd. |
1108A(2) |
Kai Tak
Barging Point Facilities |
September 2012 |
Concentric – Hong Kong River Joint
Venture (CCL-HKR JV) |
Cinotech Consultants Ltd. (Cinotech) |
1109 |
Stations and Tunnels of Kowloon City
Section |
September 2012 |
Samsung-Hsin
Chong JV (SSHCJV) |
ERM-Hong Kong Limited (ERM) |
1111 |
Hung Hom North Approach Tunnels |
January 2013 |
Gammon-Kaden
SCL1111 JV |
AECOM Asia
Co. Ltd. |
1112 |
Hung Hom
Station and Stabling Sidings |
June 2013 |
Leighton Contractors (Asia) Limited |
SMEC Asia
Ltd., HK |
Notes:
(1)
All construction
works (works areas at Tai Wai Mei Tin Road and
the offsite temporary storage areas) under Works
Contract 1101 were completed on 29 February 2016.
(2)
All construction
works (Kai Tak Barging
Point Facilities) under Works
Contract 1108A were completed on 29 September 2016.
Works Contract |
Contract Title |
Works Covered in Environmental Permit No. |
1101 |
Ma On
Shan Modification Works |
|
1102 |
Hin Keng
Station and Approach Structures |
|
1103 |
Hin Keng to Diamond Hill Tunnels |
|
1106 |
Diamond
Hill Station |
|
1107 |
Diamond
Hill to Kai Tak Tunnels |
|
1108 |
Kai Tak Station and Associated Tunnels |
|
1108A |
Kai Tak Barging Point Facilities |
|
1109 |
Stations and Tunnels of Kowloon
City Section |
|
1111 |
Hung Hom North Approach Tunnels |
EP-437/2012
& EP-438/2012/K |
1112 |
Hung Hom Station and Stabling Sidings |
Table
2.1 Summary of Major Construction Activities in the
Reporting Period
Works
Contract |
Site |
Construction
Activities |
1102 |
Hin Keng
Station and Approach Structures |
·
Soft
Landscaping; ·
ABWF
works at Hin Keng
Station; ·
Modification
of Retaining Wall and Installation of Noise Barrier; ·
Hard
Landscape; and ·
E&M
Works |
1103 |
Diamond Hill Area |
·
Underground remedial works |
Hin Keng
Area |
·
Tunnel lining, partition walls, dividing slabs,
drains, walkways and site formation |
|
Fung Tak
Area |
·
Tunnels connection, RC concrete, ELS work, sheet
piling for retaining wall and RRIW for PTT |
|
Ma Chai Hang Area |
·
Central core, ventilation tunnel, C&S works
and ABWF works |
|
Shui Chuen
O |
·
Storage area |
|
1106 |
Diamond Hill Station Area |
·
Construct Level U1 Wall and structural steel
erection; ·
ABWF works at SCL-DIH station area; ·
Foundation works, temporary road diversion, TTA
for site access and temporary footpath diversion at Choi Hung Road; ·
Excavation and lateral support works at Lung
Cheung Road; ·
Construct Base Slab at MOE near Entrance B; and ·
Drilling works and raking pile installation at
Entrance A2. |
1107 |
Tunnel section next to Kai Tak Station |
·
Reinstatement and Backfilling works of Drainage. |
1108 |
Kai Tak
Station |
·
Open cut tunnel: DT and UT general cleaning and
defect rectification, walkway top-up remedial works at Section A of DT and UT. ·
Cut and cover tunnel: DT and UT general cleaning
and defect rectification, walkway top-up remedial works at Section A & B of DT and UT, and access shaft closure at UT
completed. ·
Station: Drainage work at all area, leveling to
F.F.L. in Area 3, installation of roof cladding at Entrance A, B & D, EVA
construction for the first 2 portion, accessible ramp at DEE and Planter at
Entrance A Cast and installation of glass canopy at DEE and SEE. |
1109 |
Ma Tau Wai (MTW) Works Area |
·
Along
Ma Tau Wai Road and TKW/MTW Road Garden – Station construction; ABWF works;
and EEP construction |
To Kwa Wan (TKW) Works Area |
·
Olympic Garden – Construction of station entrance and new Pier
46; ·
TKW Station – Construction of TKW station, and backfilling; ·
Tam Kung Road – Sump pit construction; and ·
Nam Kok Road – Construction of station entrance |
|
1111 |
Mong Kok
Freight Terminal (1) |
·
All construction activities were completed in May
2015 |
Ho Man Tin |
·
EVA construction |
|
NSL 3 - 8 |
·
Concreting works, form work erection,
reinforcement fixing, backfill, road & drainage construction, excavation,
pipe laying |
|
OB2 |
·
Backfill, TB1 dismantling, watermain
diversion, upstand wall modification, OB2 bridge jacking and bearing
replacement and parapet wall construction |
|
OB2A |
·
OB2A bridge reinstatement, precast parapet
installation, bearing replacement, backfilling |
|
NSL 9 & Oi Sen Path |
·
Backfilling, drainage work, Scaffolding platform
erection, dismantling of scaffolding, lifting works, temporary working
platform removal, ELS removal, tunnel works, rock breaking |
|
EWL 7 - 9 |
·
Reinstatement, road diversion, backfilling, steel
deck dismantling |
|
1112 |
Hong Hom
(HUH and HHS) Works Area |
·
Building services works at SAT ·
EVA Roadworks at SAT ·
Demolition works of bulkhead door adjacent to
existing West Rail Stub Tunnel at SAT ·
Construction of tunnel structure at HUH, NAT ·
Drainage work at HHS ·
Platform ABWF and E&M works at HUH ·
Utility works at NAT ·
Modification works at Concourse level, mid-level
walkway |
Note:
(1)
Construction works were completed.
Table
2.2 Summary of 24-Hour TSP Monitoring Results in the
Reporting Period
Monitoring
Station ID |
Location |
TSP
Concentration (mg/m3) |
Action
Level (mg/m3) |
Limit
Level (mg/m3) |
Exceedance
due to the Project Construction (Yes/No) |
Works Contract 1102 and 1103 |
|
|
|
|
|
DMS-1 |
C.U.H.K.A.A. Thomas Cheung
School |
21.9-59.1 |
148.7 |
260 |
No |
Works Contract 1103 |
|
|
|
|
|
DMS-2 |
Price Memorial Catholic Primary
School |
23.2-83.0 |
167.4 |
260 |
No |
Works Contracts 1103 and 1106 |
|
|
|
|
|
DMS-3 |
Hong Kong S.K.H Nursing Home (1) |
29.4-67.5 |
159.1 |
260 |
No |
Works Contract 1106 and 1107 |
|
|
|
|
|
DMS-4 |
Block 1, Rhythm Garden |
28.2-82.9 |
160.4 |
260 |
No |
Works Contract 1108 (5) |
|
|
|
|
|
Works Contract 1109 |
|
|
|
|
|
DMS-6 |
Katherine
Building (2) |
62 –
65 |
156.8 |
260 |
No |
DMS-7 |
Parc 22 (3)(10) |
- |
166.7 |
260 |
No |
DMS-8 |
SKH Good Shepherd Primary School |
63 –
78 |
152.2 |
260 |
No |
DMS-9 |
No. 12 Pau Chung Street (4)(9) |
53 –
83 |
160.9 |
260 |
No |
DMS-10 |
Chat Ma Mansion |
58 –
75 |
170.4 |
260 |
No |
Works
Contract 1111 |
|
|
|
|
|
AM1(6) |
No. 234 – 238 Chatham Road North
(7) |
30.5
– 91.1 |
183.9 |
260 |
No |
Works
Contract 1112 |
|
|
|
|
|
AM2 |
Site Boundary of Finger Pier Adjacent To Harbourfront
Horizon (8) |
38.0
– 45.9 |
182 |
260 |
No |
Notes:
(1)
Alternative monitoring location to Shek On House
(2)
Alternative monitoring location to
Prosperity House
(3)
Alternative monitoring location to Skytower Tower 2
(4)
Alternative
monitoring location to Lucky Building
(5)
No TSP monitoring is required under this
contract
(6)
AM1 named as HUH-1-3 in SCL(TAW-HUH)
and SCL(HHS) EIA Reports.
(7)
Alternative monitoring location to Wing
Fung Building
(8)
Alternative monitoring location to Harbourfront Horizon
(9)
24-hour averaged dust monitoring at DMS-9
No. 26 Kowloon City Road (alternative location of Lucky Building) has been
suspended since March 2014 due to denied access by the occupant of the premise.
However, No. 12 Pau Chung Street, as an alternative monitoring location, was
formally approved by EPD on 19 May 2014. Impact dust monitoring was resumed on
12 June 2014.
(10) 24-hour
averaged dust monitoring at DMS-7 Parc 22 (alternative
monitoring location of Skytower Tower 2) has been
temporary suspended since 13 December 2016 due to request from the management
office.
Table 2.3 Summary of Construction Noise Monitoring Results in the
Reporting Period
Monitoring
Station ID |
Location |
Noise
Level (LAeq,30mins,
dB(A)) |
Limit
Level (dB(A)) |
Exceedance
due to the Project Construction (Yes/No) |
|||
Measured |
Baseline |
Corrected
(7) |
|||||
Works Contract 1102 and 1103 |
|
|
|
|
|
||
NMS-CA-1 |
C.U.H.K.A.A. Thomas Cheung School |
51.6-55.8 |
57.0 |
< Baseline |
70 (65 during examination period) |
No |
|
Works Contract 1103 |
|
|
|
|
|
||
NMS-CA-2 |
Price Memorial Catholic Primary School |
60.0-62.0 |
66.0 |
< Baseline |
70 (65 during examination period) |
No |
|
Works Contracts 1103 and 1106 |
|
|
|
|
|
||
NMS-CA-3 |
Hong Kong S.K.H Nursing Home (1) |
71.8-72.6 |
73.0 |
< Baseline |
70 |
No |
|
Works Contract 1106 and 1107 |
|
|
|
|
|
||
NMS-CA-4 |
Block 1, Rhythm Garden (north-eastern
façade) |
71.2-72.4 |
71.0 |
57.7-66.8 |
75 |
No |
|
NMS-CA-5 |
Block 1, Rhythm Garden (northern façade)(2) |
70.3-71.4 |
74.0 |
<Baseline |
70 (65 during examination period) |
No |
|
Works Contract 1108 (6) |
|
|
|
|
|
||
Works Contract 1109 |
|
|
|
|
|
||
NMS-CA-6 |
No. 16-23 Nam
Kok Road (3) |
62.9-63.2 |
76.1 |
< Baseline |
75 |
No |
|
NMS-CA-7 |
Skytower Tower 2 |
65.2-66.1 |
70.0 |
< Baseline |
75 |
No |
|
NMS-CA-8 |
SKH Good Shepherd Primary School |
71.8-73.0 |
75.4 |
< Baseline |
70 (65 during examination period) (79 during the period of conducting the
continuous noise monitoring) (8) |
No |
|
NMS-CA-9 |
Kong Yiu
Mansion (4) |
68.4-69.2 |
69.2 |
≤ Baseline |
75 |
No |
|
NMS-CA-10 |
Chat
Ma Mansion |
75.6-76.8 |
76.6 |
< Baseline-63.3 |
75 |
No |
|
Works Contract 1111 |
|
|
|
|
|
||
NM1 |
Carmel Secondary School (South Block) |
65.2-67.4 |
68.0 |
< Baseline |
70 (65 during examination period) (68 during
the period of conducting the continuous noise monitoring) (9) |
No |
|
NM2 |
No. 234 – 238 Chatham Road North (5)
|
68.6-69.8 |
79.0 |
< Baseline |
75 (77) (10) |
No |
|
Works Contract 1112 (6) |
|
|
|
|
|
||
Notes:
(1)
Alternative monitoring location to Shek On House.
(2)
Alternative monitoring location to Canossa
Primary School (San Po Kong).
(3)
Alternative monitoring location to
Prosperity House.
(4)
Alternative monitoring location to Lucky
Building.
(5)
Alternative monitoring location to Wing
Fung Building.
(6)
No construction noise monitoring is
required under this contract.
(7)
The measured noise levels are corrected
against the corresponding baseline noise levels.
(8)
The Limit Level of 79 dB(A) was updated on
22 Aug 2013 as per the latest Construction Noise Mitigation Measures Plan
(CNMMP) and Continuous Noise Monitoring Plan (CNMP) which were approved by EPD.
(9)
The Limit of 68
dB(A) was updated on 20 Jan 2014 as per the latest
CNMMP and CNMP which were approved by EPD.
(10) Daytime noise Limit Level of 77 dB(A)
applies during the continuous noise monitoring period.
Table
2.4 Log for Environmental Complaints, Notification of
Summons and Successful Prosecutions for the Reporting Month
Works
Contract |
Environmental
Complaints |
Notification
of Summons |
Successful
Prosecutions |
1102 |
0 |
0 |
0 |
1103 |
0 |
0 |
0 |
1106 |
0 |
0 |
0 |
1107 |
0 |
0 |
0 |
1108 |
0 |
0 |
0 |
1109 |
0 |
0 |
0 |
1111 |
1 |
0 |
0 |
1112 |
0 |
0 |
0 |
Table
3.1 Summary of Status of Required Submissions for and
EP-438/2012/K
EP
Condition |
Submission |
Submission
date |
Condition 1.12 |
Notification of Commencement Date of
Construction of the Project |
1 Aug 2012 |
Condition 2.3 |
Notification of Information of Community
Liaison Groups |
13 Jul 2012 (1st submission) 31 Aug 2012 (2nd submission) 30 Nov 2012 (3rd submission) |
Condition 2.7 |
Management Organisation of Main
Construction Companies |
27 Jul 2012 (1st submission) 21 Aug 2012 (2nd submission) 19 Dec 2012 (3rd submission) 22 Jan 2013 (4th submission) 30 Apr 2013 (5th submission) 21 May 2013 (6th submission) |
Condition 2.8 |
Construction Programme and EP Submission
Schedule |
27 Jul 2012 |
Condition 2.9 |
Construction Noise Mitigation Measures
Plan (CNMMP) |
1 Aug 2012 (1st submission) 28 Sep 2012 (2nd submission) 30 Nov 2012 (3rd submission) 11 Jan 2013 (4th submission) 8 Feb 2013 (Approved) 26 Apr 2013 (6th submission) 11 Jun 2013 (7th submission) 12 July 2013 (Approved) 26 July 2013 (8th submission) 22 Aug 2013 (Approved) 23 Aug 2013 (9th submission) 13 Sept 2013 (Approved) 20 Jan 2014 (10th submission) 26 Feb 2014
(Approved) 31 Mar 2015
(Contract 1106 submission only) 13 Apr 2015
(Contract 1106 submission only) 15 Apr 2015
(Approved) |
Condition 2.10 |
Continuous Noise Monitoring Plan (CNMP) |
1 Aug 2012 (1st submission) 28 Sep 2012 (2nd submission) 30 Nov 2012 (3rd submission) 11 Jan 2013 (4th submission) 8 Feb 2013 (Approved) 8 Feb 2013 (5th submission) 26 Apr 2013 (6th submission) 11 Jun 2013 (7th submission) 12 July 2013 (Approved) 26 July 2013 (8th submission) 22 Aug 2013 (Approved) 23 Aug 2013 (9th submission) 13 Sept 2013 (Approved) 20 Jan 2014 (10th submission) 26 Feb 2014
(Approved) 7 Oct 2014 (11th submission) 23 Oct 2014
(Approved) |
Condition 2.11 |
Construction and Demolition Materials
Management Plan (C&DMMP) |
6 Jul 2012 (1st submission) 12 Sep 2012 (2nd submission) 10 Oct 2012 (Approved) |
Condition 2.12 |
Sediment Management Plan |
6 Jul 2012 (1st submission) 12 Sep 2012 (2nd submission) 5 Oct 2012 (3rd submission) 10 Oct 2012 (Approved) 4 Mar 2013 (4th submission) 9 May 2013 (5th submission) 24 July 2013 (6th submission) 26 July 2013 (Approved) |
Condition 2.13 |
Visual, Landscape, Tree Planting &
Tree Protection Plan |
6 Jul 2012 (1st submission) 30 Aug 2012 (2nd submission) 3 Oct 2012 (3rd submission) 13 Nov 2013 (Approved) 14 Nov 2012 (4th submission) 8 Feb 2013 (5th submission) 18 Mar 2013 (6th submission) 18 June 2013 (7th submission) 12 July 2013 (Approved) 23 Mar 2017
(8th submission) |
Condition 2.14 |
Transplantation Proposal for Plant
Species of Conservation Importance |
22 Aug 2012 (1st submission) 5 Oct 2012 (2nd submission) 26 Nov 2012 (3rd submission) 4 Dec 2012 (Approved) |
Condition 2.15 |
Conservation Plan |
31 Jan 2013 (1st submission) 18 Mar 2013 (2nd submission) 24 Apr 2013 (Approved) |
Condition 2.16 |
Archaeological Action Plan(s) (AAP(s))
for Works Contract 1109 |
10 Aug 2012 (1st submission) 3 Sep 2012 (2nd submission) 21 Sep 2012 (Approved) 11 Oct 2013 (3rd
submission) 1 Nov 2013 (Approved) |
Condition 2.16 |
Archaeological Action Plan(s) (AAP(s))
for Works Contract 1106 |
29 Jan 2013 (1st submission) 19 Mar 2013 (2nd submission) 8 Apr 2013 (Approved) |
Condition 2.23 |
Supplementary Contamination Assessment Report
for New Territories South Animal Centre |
28 Sep 2012 25 Oct 2012 (Approved) |
Condition 2.27 |
Operational Ground-borne Noise
Mitigation Measures Plan |
18 Mar 2016 (Batch
1 Version A submission) 28 Apr 2016 (Batch
1 Version B submission) 28 Apr 2016 (Batch
2 Version A submission) 1 Jun 2016 (Batch
1 Version C submission) 1 Jun 2016
(Batch 2 Version B submission) 23 Jun 2016
(Batch 1 Version D submission) 23 Jun 2016
(Batch 2 Version C submission) 15 Jul 2016
(Batch 1 Version D approved) 15 Jul 2016
(Batch 2 Version C approved) 15 Sep 2016
(Batch 3 Version A submission) 4 Oct 2016
(Batch 3 Version A approved) 8 Mar 2017
(Batch 4 Version A) 7 April 2017
(Batch 4 Version A approved) |
Condition 2.30 |
As-built
Drawings for Operational Air-borne Noise Mitigation Measures |
4 Dec 2015 (1st
submission) 28 Dec 2015 (2nd
submission) 4 Feb 2016
(Approved) |
Condition 2.33 |
As-built
Drawings for Landscape and Visual Mitigation Measures |
4 Dec 2015 (1st
submission) 28 Dec 2015 (2nd
submission) 4 Feb 2016
(Approved) |
Condition
2.36 |
Contamination
Assessment Plan (CAP) for the Temporary Magazine Site at TKO Area 137 |
23 Mar 2016
(1st submission) 20 Apr 2016
(2nd submission) 22 Apr 2016
(Approved) |
Condition
2.36 |
Contamination
Assessment Report (CAR) for the Temporary Magazine Site at TKO Area 137 |
19 May 2016
(1st submission) 3 Jun 2016 (2nd
submission) 15 Jun 2016
(Approved) |
Condition 3.1 |
Proposal for
Termination of Environmental Monitoring and Audit (EM&A) Programme for
Kai Tak Barging Point Facilities |
7 Oct 2016
(Approved) |
Condition 3.3 |
Baseline Monitoring Report (Works
Contract 1109 - Stations and Tunnels of Kowloon City Section ) |
27 Jul 2012 |
Condition 3.3 |
Baseline Monitoring Report (Works
Contract 1108A – Kai Tak Barging Point Facilities) |
31 Jul 2012 |
Condition 3.3 |
Baseline Monitoring Report (Works
Contracts 1103, 1106 and 1111 – Hin Keng to Diamond Hill Tunnels, Diamond Hill Station, and
Hung Hom North Approach Tunnels) |
19 Oct 2012 |
Condition 3.4 |
Monthly EM&A Reports No. 1-55 Monthly EM&A Report No. 56 |
Reported in
previous Monthly EM&A Reports 12 May 2017 |
Table
3.2 Summary of Status of Required Submissions for EP-437/2012
EP
Condition |
Submission |
Submission
date |
Condition 1.11 |
Notification of Commencement Date of
Construction of the Project |
30 Nov 2012 |
Condition 2.3 |
Notification of Information of Community
Liaison Groups |
30 Nov 2012 |
Condition 2.5 |
Management Organisation of Main
Construction Companies |
19 Dec 2012 (1st submission) 30 Apr 2013 (2nd submission) |
Condition 2.6 |
Construction Programme and EP Submission
Schedule |
19 Dec 2012 |
Condition 2.7 |
Construction Noise Mitigation Measures
Plan (CNMMP) |
30 Nov 2012 (1st submission) 8 Feb 2013 (Approved ) 26 Apr 2013 (2nd submission) 11 Jun 2013 (3rd submission) 27 Aug 2013 (Approved) 20 Jan 2014 (4th submission) 28 Apr 2016
(Approved) |
Condition 2.8 |
Continuous Noise Monitoring Plan (CNMP) |
30 Nov 2012 (1st submission) 11 Jan 2013 (2nd submission) 8 Feb 2013 (Approved) 20 Jan 2014 (3rd submission) |
Condition 2.9 |
Construction and Demolition Materials
Management Plan (C&DMMP) |
6 Jul 2012 (1st submission) 12 Sep 2012 (2nd submission) 15 Oct 2012 (Approved) |
Condition 2.10 |
Sediment Management Plan |
6 Jul 2012 (1st submission) 12 Sep 2012 (2nd submission) 5 Oct 2012 (3rd submission) 15 Oct 2012 (Approved) |
Condition 2.11 |
Visual, Landscape, Tree Planting &
Tree Protection Plan (VLTTP) |
14 Nov 2012 (1st submission) 8 Feb 2013 (2nd submission) 4 Feb 2015 (3rd submission) 26 Jun 2015
(4th submission) 12 May 2017
(5th submission) |
Condition 2.16 |
Operational Ground-borne Noise
Mitigation Measures Plan |
23 Mar 2017 (1st
submission) 17 May 2017
(2nd submission) |
Condition 3.3 |
Baseline Monitoring Report (Works
Contracts 1103, 1106 and 1111 – Hin Keng to Diamond Hill Tunnels, Diamond Hill Station, and
Hung Hom North Approach Tunnels) |
19 Oct 2012 |
Condition 3.4 |
Monthly EM&A Reports No. 5-55 Monthly EM&A Report No. 56 |
Reported in
previous Monthly EM&A Reports 12 May 2017 |