Table of
Contents
2......... Environmental Monitoring and Audit
3......... implementation status on the
environmental protection requirements
List of
Tables
Table
1.1 Summary
of Awarded Works Contracts
Table 2.1 Summary of Major Construction
Activities in the Reporting Period
Table 2.2 Summary of 24-Hour TSP Monitoring
Results in the Reporting Period
Table 2.3 Summary of Construction Noise
Monitoring Results in the Reporting Period
Table 3.1 Summary of Status of Required
Submissions for EP-438/2012/J
Table 3.2 Summary of Status of Required
Submissions for EP-437/2012
List of
Appendices
Appendix A 49th
Monthly EM&A Report for Works Contract 1108A – Kai Tak Barging Point
Facilities
Appendix C 45th Monthly
EM&A Report for Works Contract 1111 – Hung Hom North Approach Tunnels
Appendix D 44th Monthly
EM&A Report for Works Contract 1103 – Hin Keng to Diamond Hill Tunnels
Appendix E 43rd Monthly EM&A Report for Works Contract
1106 – Diamond Hill Station
Appendix F 41th Monthly EM&A Report for Works Contract
1107 – Diamond Hill to Kai Tak Tunnels
Appendix G 40th Monthly EM&A Report for Works Contract
1112 – Hung Hom Station and Stabling Sidings
Appendix H 40th Monthly EM&A Report for Works Contract
1108 – Kai Tak Station and Associated Tunnels
Table
1.1 Summary
of Awarded Works Contracts
Works
Contract |
Description |
Construction
Start Date |
Contractor |
Environmental
Team |
1101(1) |
Ma
On Shan Line Modification Works |
December 2012 |
Sun
Fook Kong Joint Venture (SFKJV) |
ANewR Consulting Ltd. (ANewR) |
1102 |
Hin
Keng Station and Approach Structures |
October 2013 |
Penta-Ocean
Construction Co. Ltd. |
Cinotech Consultants Ltd. (Cinotech) |
1103 |
Hin
Keng to Diamond Hill Tunnels |
February 2013 |
Vinci
Construction Grands Projets |
Ove
Arup & Partners Hong Kong Ltd. (Arup) |
1106 |
Diamond
Hill Station |
March 2013 |
Leader
Joint Venture |
Cinotech Consultants Ltd. (Cinotech) |
1107 |
Diamond
Hill to Kai Tak Tunnels |
May 2013 |
Chun
Wo - SELI Joint Venture |
Cinotech Consultants Ltd. (Cinotech) |
1108 |
Kai
Tak Station and Associated Tunnels |
June 2013 |
Kaden
-Chun Wo Joint Venture |
Environmental
Pioneers & Solutions Ltd. |
1108A |
Kai
Tak Barging Point Facilities |
September 2012 |
Concentric
– Hong Kong River Joint Venture (CCL-HKR JV) |
Cinotech Consultants Ltd. (Cinotech) |
1109 |
Stations
and Tunnels of Kowloon City Section |
September 2012 |
Samsung-Hsin Chong JV (SSHCJV) |
ERM-Hong
Kong Limited (ERM) |
1111 |
Hung Hom North Approach
Tunnels |
January 2013 |
Gammon-Kaden SCL1111 JV |
AECOM Asia Co. Ltd. |
1112 |
Hung
Hom Station and Stabling Sidings |
June 2013 |
Leighton
Contractors (Asia) Limited |
SMEC Asia Ltd., HK |
Notes:
(1)
All construction
works (works
areas at Tai Wai Mei Tin Road and the offsite temporary storage areas) under Works Contract
1101 were completed on 29 February 2016.
Works Contract |
Contract Title |
Works Covered in Environmental Permit No. |
1101 |
Ma On
Shan Modification Works |
|
1102 |
Hin Keng
Station and Approach Structures |
|
1103 |
Hin Keng to Diamond Hill Tunnels |
|
1106 |
Diamond
Hill Station |
|
1107 |
Diamond
Hill to Kai Tak Tunnels |
|
1108 |
Kai
Tak Station and Associated Tunnels |
|
1108A |
Kai
Tak Barging Point Facilities |
|
1109 |
Stations and Tunnels of Kowloon
City Section |
|
1111 |
Hung Hom North Approach Tunnels |
|
1112 |
Hung Hom Station and Stabling Sidings |
Table 2.1 Summary of Major Construction
Activities in the Reporting Period
Works Contract |
Site |
Construction Activities |
1102 |
Hin Keng Station and Approach Structures |
·
Slope
improvement works ·
External
wall tiling at viaduct & at-grade box ·
ABWF
works at Hin Keng Station ·
Modification
of retaining wall and installation of noise barrier |
1103 |
Diamond
Hill Area |
· Completion of tunnel shaft construction
(above-ground) |
Hin Keng Area |
· Tunnel lining and partition walls, dividing
slabs, drains and walkways |
|
Fung
Tak Area |
· Tunnels connection, RC concrete and ELS work and
sheet piling for retaining wall |
|
Ma Chai
Hang Area |
· Central core, ventilation tunnel and C&S
works |
|
Shui Chuen O |
· Storage area |
|
1106 |
Diamond
Hill Station Area |
· Construction of Level U1 wall, structural steel
erection, concourse and plant rooms passenger areas; · ABWF works at SCL-DIH station area; · Storage preparation works near DIH shaft area; · Foundation works and temporary road works at Lung
Cheung Road and Choi Hung Road; · Pre-boring works, sheet pilling work and
pre-drilling works on Lung Cheung Road; · Sheet piling and grouting works; and · Landscaping and tiling works, and planter
reinstatement works at Entrance A1. |
1107 |
Tunnel
section next to Kai Tak Station |
· Tunnel construction at cut and cover tunnels · Reinstatement and backfilling works of drainage |
1108 |
Kai Tak
Station |
· Open cut tunnel: Area 1 backfilling and
1108/1109, DT and UT general cleaning and defect rectification, waterproofing
and screeding on SUA roof and application of joint
sealant to tunnel walkway · Cut and cover tunnel: Receiving shaft backfilling
up to 1st & 2nd struts, tunnel tracks defect
rectification, receiving shaft S2 and S1 shoring dismantling, backfilling at nullah, drainage man-hole and U-channel construction · Station: Entrance of formwork and rebar fixing
for oil interceptor at SVS, erection of formwork for mass ramp at Entrance A,
drainage works at all area, backfilling for DCS trench, installation of
remaining members for steel roof frame at Entrance B, installation of
brackets for roof cladding at Entrance D and sheet pile extraction. |
1108A |
Kai Tak
Barging Point Facilities |
· Outstanding works including, reinstatement of
stone pitching to sloping seawall, trimming and compaction of formation
surface and final site clearance |
1109 |
Ma Tau
Wai (MTW) Works Area |
· Along Ma Tau Wai Road and TKW/MTW Road Garden –
Station excavation and construction; minipile
installation; and EEP construction. |
To Kwa
Wan (TKW) Works Area |
· Olympic Garden – Construction of station
entrance; · TKW Station – Pump installation, construction of TKW station,
and TBM decommissioning; · Tam Kung Road – Shaft construction; and · Nam Kok Road – Excavation and slab construction. |
|
1111 |
Mong
Kok Freight Terminal (1) |
· All construction activities were completed in May
2015. |
Hung Hom Area |
· Fencing removal work · Erection of noise enclosure, manhole
construction, pipe laying, cable trench, excavation works, grouting works,
cable laying, concreting works · Parapet modification works, bearing replacement · ELS & decking removal work, tunnel structure,
reinstatement · Tunnel/ sump pit structure, tunnel works,
backfilling, ELS dismantling · Scaffolding platform erection, dismantling of
scaffolding, construction of noise enclosure & steel truss, pre-split,
OHL modification, lifting works, deck excavation, temporary working platform,
ELS removal, rock breaking |
|
1112 |
Hong Hom (HUH and HHS) Works Area |
·
Slab
construction at HUH, NAT ·
Initial
excavation at HHS and SAT ·
Underpinning
at HUH ·
Utilities
diversion at SAT ·
Modification
works at Concourse level ·
Drainage
diversion at NAT ·
Noise
barrier installation at NAT ·
Construction
of Overhead Track Exhaust (OTE) structures · Construction of Back of House (BOH) structures |
Note:
(1)
Construction works were completed.
Table
2.2 Summary of 24-Hour TSP Monitoring Results in the
Reporting Period
Monitoring Station ID |
Location |
TSP Concentration (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
Exceedance due to the Project
Construction (Yes/No) |
Works
Contract 1102 and 1103 |
|
|
|
|
|
DMS-1 |
C.U.H.K.A.A.
Thomas Cheung School |
14.8-88.8 |
148.7 |
260 |
No |
Works
Contract 1103 |
|
|
|
|
|
DMS-2 |
Price
Memorial Catholic Primary School |
40.2-138.1 |
167.4 |
260 |
No |
Works
Contracts 1103 and 1106 |
|
|
|
|
|
DMS-3 |
Hong
Kong S.K.H Nursing Home (1) |
10.1-156.9 |
159.1 |
260 |
No |
Works
Contract 1106 and 1107 |
|
|
|
|
|
DMS-4 |
Block
1, Rhythm Garden |
18.2-106.5 |
160.4 |
260 |
No |
Works
Contract 1108 (5) |
|
|
|
|
|
Works
Contract 1108A (5) |
|
|
|
|
|
Works
Contract 1109 |
|
|
|
|
|
DMS-6 |
Katherine Building (2) |
46-70 |
156.8 |
260 |
No |
DMS-7 |
Parc
22 (3) |
51-69 |
166.7 |
260 |
No |
DMS-8 |
SKH
Good Shepherd Primary School |
52-72 |
152.2 |
260 |
No |
DMS-9 |
No.
12 Pau Chung Street (4)(9)(10) |
62-72 |
160.9 |
260 |
No |
DMS-10 |
Chat
Ma Mansion |
53-67 |
170.4 |
260 |
No |
Works Contract 1111 |
|
|
|
|
|
AM1(6) |
No.
234 – 238 Chatham Road North (7) |
16.9-156.8 |
183.9 |
260 |
No |
Works Contract 1112 |
|
|
|
|
|
AM2 |
Site
Boundary of Finger Pier Adjacent
To
Harbourfront Horizon (8) |
30.7-50.0 |
182 |
260 |
No |
Notes:
(1)
Alternative monitoring location to Shek On
House
(2)
Alternative monitoring location to
Prosperity House
(3)
Alternative monitoring location to Skytower Tower 2
(4)
Alternative monitoring
location to Lucky Building
(5)
No TSP monitoring is required under this
contract
(6)
AM1 named as HUH-1-3 in SCL(TAW-HUH)
and SCL(HHS) EIA Reports.
(7)
Alternative monitoring location to Wing
Fung Building
(8)
Alternative monitoring location to Harbourfront
Horizon
(9)
24-hour averaged dust monitoring at DMS-9
No. 26 Kowloon City Road (alternative location of Lucky Building) has been
suspended since March 2014 due to denied access by the occupant of the premise.
However, No. 12 Pau Chung Street, as an alternative monitoring location, was
formally approved by EPD on 19 May 2014. Impact dust monitoring was resumed on
12 June 2014.
(10)
24-hour averaged dust monitoring at DMS-9
(No. 12 Pau Chung Street) was temporary suspended since July 2016 due to
request from Management Office and was resumed on 20 September 2016.
Table 2.3 Summary of Construction Noise
Monitoring Results in the Reporting Period
Monitoring Station ID |
Location |
Noise Level (LAeq,30mins, dB(A)) |
Limit Level (dB(A)) |
Exceedance due to the Project
Construction (Yes/No) |
|||
Measured |
Baseline |
Corrected (7) |
|||||
Works Contract
1102 and 1103 |
|
|
|
|
|
||
NMS-CA-1 |
C.U.H.K.A.A.
Thomas Cheung School |
53.5-56.9 |
57.0 |
<
Baseline |
70 (65 during
examination period) |
No |
|
Works Contract
1103 |
|
|
|
|
|
||
NMS-CA-2 |
Price
Memorial Catholic Primary
School |
59.2-61.6 |
66.0 |
<
Baseline |
70 (65
during examination period) |
No |
|
Works Contracts
1103 and 1106 |
|
|
|
|
|
||
NMS-CA-3 |
Hong
Kong S.K.H Nursing
Home (1) |
66.6-69.3 |
73.0 |
<
Baseline |
70 |
No |
|
Works Contract
1106 and 1107 |
|
|
|
|
|
||
NMS-CA-4 |
Block
1, Rhythm Garden (north-eastern façade) |
71.8-73.3 |
71.0 |
64.1-69.4 |
75 |
No |
|
NMS-CA-5 |
Block
1, Rhythm Garden (northern façade)(2) |
70.6-72.7 |
74.0 |
<
Baseline |
70 (65 during
examination period) |
No |
|
Works Contract
1108 (6) |
|
|
|
|
|
||
Works Contract
1108A (6) |
|
|
|
|
|
||
Works Contract
1109 |
|
|
|
|
|
||
NMS-CA-6 |
No. 16-23 Nam Kok Road (3) |
62.4 – 64.0 |
76.1 |
< Baseline |
75 |
No |
|
NMS-CA-7 |
Skytower Tower
2 |
65.1 – 65.8 |
70.0 |
< Baseline |
75 |
No |
|
NMS-CA-8 |
SKH
Good Shepherd Primary
School |
74.4-75.4 |
75.4 |
< Baseline – = Baseline |
70 (65
during examination period) (79
during the period of conducting the continuous noise monitoring) (8) |
No |
|
NMS-CA-9 |
Kong
Yiu Mansion (4) |
71.0-71.7 |
69.2 |
66.3-68.1 |
75 |
No |
|
NMS-CA-10 |
Chat Ma Mansion |
75.9-76.4 |
76.6 |
< Baseline |
75 |
No |
|
Works Contract
1111 |
|
|
|
|
|
||
NM1 |
Carmel
Secondary School (South
Block) |
63.2-68.0 |
68.0 |
< Baseline – = Baseline |
70 (65
during examination period) (68 during the period of conducting the continuous
noise monitoring) (9) |
No |
|
NM2 |
No.
234 – 238 Chatham Road North (5) |
70.0-70.9 |
79.0 |
< Baseline |
75 (77) (10) |
No |
|
Works Contract
1112 (6) |
|
|
|
|
|
||
Notes:
(1)
Alternative monitoring location to Shek On House.
(2)
Alternative monitoring location to Canossa
Primary School (San Po Kong).
(3)
Alternative monitoring location to
Prosperity House.
(4)
Alternative monitoring location to Lucky
Building.
(5)
Alternative monitoring location to Wing
Fung Building.
(6)
No construction noise monitoring is
required under this contract.
(7)
The measured noise levels are corrected
against the corresponding baseline noise levels.
(8)
The Limit Level of 79 dB(A) was updated on
22 Aug 2013 as per the latest Construction Noise Mitigation Measures Plan (CNMMP)
and Continuous Noise Monitoring Plan (CNMP) which were approved by EPD.
(9)
The Limit of 68
dB(A) was updated on 20 Jan 2014 as per the latest
CNMMP and CNMP which were approved by EPD.
(10)
Daytime noise
Limit Level of 77 dB(A) applies during the continuous
noise monitoring period.
Table 2.4 Log for Environmental Complaints,
Notification of Summons and Successful Prosecutions
for the Reporting Month
Works Contract |
Environmental Complaints |
Notification of Summons |
Successful Prosecutions |
1102 |
0 |
0 |
0 |
1103 |
0 |
0 |
0 |
1106 |
0 |
0 |
0 |
1107 |
0 |
0 |
0 |
1108 |
0 |
0 |
0 |
1108A |
0 |
0 |
0 |
1109 |
0 |
0 |
0 |
1111 |
0 |
0 |
0 |
1112 |
0 |
0 |
0 |
Table 3.1 Summary
of Status of Required Submissions for EP-438/2012/J
(EP-438/2012/J) |
Submission |
Submission
date |
Condition 1.12 |
Notification
of Commencement Date of Construction of the Project |
1
Aug 2012 |
Condition 2.3 |
Notification
of Information of Community Liaison Groups |
13
Jul 2012 (1st submission) 31
Aug 2012 (2nd submission) 30
Nov 2012 (3rd submission) |
Condition 2.7 |
Management
Organisation of Main Construction Companies |
27
Jul 2012 (1st submission) 21
Aug 2012 (2nd submission) 19
Dec 2012 (3rd submission) 22
Jan 2013 (4th submission) 30
Apr 2013 (5th submission) 21
May 2013 (6th submission) |
Condition 2.8 |
Construction
Programme and EP Submission Schedule |
27
Jul 2012 |
Condition 2.9 |
Construction
Noise Mitigation Measures Plan (CNMMP) |
1
Aug 2012 (1st submission) 28
Sep 2012 (2nd submission) 30
Nov 2012 (3rd submission) 11
Jan 2013 (4th submission) 8
Feb 2013 (Approved) 26
Apr 2013 (6th submission) 11
Jun 2013 (7th submission) 12
July 2013 (Approved) 26
July 2013 (8th submission) 22
Aug 2013 (Approved) 23
Aug 2013 (9th submission) 13
Sept 2013 (Approved) 20
Jan 2014 (10th submission) 26 Feb 2014 (Approved) 31 Mar 2015 (Contract 1106 submission only) 13 Apr 2015 (Contract 1106 submission only) 15 Apr 2015 (Approved) |
Condition 2.10 |
Continuous
Noise Monitoring Plan (CNMP) |
1
Aug 2012 (1st submission) 28
Sep 2012 (2nd submission) 30
Nov 2012 (3rd submission) 11
Jan 2013 (4th submission) 8
Feb 2013 (Approved) 8
Feb 2013 (5th submission) 26
Apr 2013 (6th submission) 12
July 2013 (Approved) 26
July 2013 (8th submission) 22
Aug 2013 (Approved) 23
Aug 2013 (9th submission) 13
Sept 2013 (Approved) 20
Jan 2014 (10th submission) 26 Feb 2014 (Approved) 7 Oct 2014 (11th submission) 23 Oct 2014 (Approved) |
Condition 2.11 |
Construction
and Demolition Materials Management Plan (C&DMMP) |
6
Jul 2012 (1st submission) 12
Sep 2012 (2nd submission) 10
Oct 2012 (Approved) |
Condition 2.12 |
Sediment
Management Plan |
6
Jul 2012 (1st submission) 12
Sep 2012 (2nd submission) 5
Oct 2012 (3rd submission) 10
Oct 2012 (Approved) 4
Mar 2013 (4th submission) 9
May 2013 (5th submission) 24
July 2013 (6th submission) 26
July 2013 (Approved) |
Condition 2.13 |
Visual,
Landscape, Tree Planting & Tree Protection Plan |
6
Jul 2012 (1st submission) 30
Aug 2012 (2nd submission) 3
Oct 2012 (3rd submission) 13
Nov 2013 (Approved) 14
Nov 2012 (4th submission) 8
Feb 2013 (5th submission) 18
Mar 2013 (6th submission) 18
June 2013 (7th submission) 12
July 2013 (Approved) |
Condition 2.14 |
Transplantation
Proposal for Plant Species of Conservation Importance |
22
Aug 2012 (1st submission) 5
Oct 2012 (2nd submission) 26
Nov 2012 (3rd submission) 4
Dec 2012 (Approved) |
Condition 2.15 |
Conservation
Plan |
31
Jan 2013 (1st submission) 18
Mar 2013 (2nd submission) 24
Apr 2013 (Approved) |
Condition 2.16 |
Archaeological
Action Plan(s) (AAP(s)) for Works Contract 1109 |
10
Aug 2012 (1st submission) 3
Sep 2012 (2nd submission) 21
Sep 2012 (Approved) 11 Oct 2013 (3rd submission) 1
Nov 2013 (Approved) |
Condition 2.16 |
Archaeological
Action Plan(s) (AAP(s)) for Works Contract 1106 |
29
Jan 2013 (1st submission) 19
Mar 2013 (2nd submission) 8
Apr 2013 (Approved) |
Condition 2.23 |
Supplementary
Contamination Assessment Report for New Territories South Animal Centre |
28
Sep 2012 25
Oct 2012 (Approved) |
Condition 2.27 |
Operational
Ground-borne Noise Mitigation Measures Plan |
18 Mar 2016 (Batch 1 Version A submission) 28 Apr 2016 (Batch 1 Version B submission) 28 Apr 2016 (Batch 2 Version A submission) 1 Jun 2016 (Batch 1 Version C submission) 1 Jun 2016 (Batch 2 Version B submission) 23 Jun 2016 (Batch 1 Version D submission) 23 Jun 2016 (Batch 2 Version C submission) 15 Jul 2016 (Batch 1 Version D approved) 15 Jul 2016 (Batch 2 Version C approved) 15 Sep 2016 (Batch 3 Version A submission) |
Condition 2.30 |
As-built Drawings for Operational Air-borne Noise
Mitigation Measures |
4 Dec 2015 (1st
submission) 28 Dec 2015 (2nd submission) 4 Feb 2016 (Approved) |
Condition 2.33 |
As-built Drawings for Landscape and Visual
Mitigation Measures |
4 Dec 2015 (1st
submission) 28 Dec 2015 (2nd submission) 4 Feb 2016 (Approved) |
Condition
2.36 |
Contamination Assessment Plan (CAP) for the
Temporary Magazine Site at TKO Area 137 |
23 Mar 2016 (1st submission) 20 Apr 2016 (2nd submission) 22 Apr 2016 (Approved) |
Condition
2.36 |
Contamination Assessment Report (CAR) for the
Temporary Magazine Site at TKO Area 137 |
19 May 2016 (1st submission) 3 Jun 2016 (2nd submission) 15 Jun 2016 (Approved) |
Condition 3.3 |
Baseline
Monitoring Report (Works Contract 1109 - Stations and Tunnels of Kowloon City
Section ) |
27
Jul 2012 |
Condition 3.3 |
Baseline
Monitoring Report (Works Contract 1108A – Kai Tak Barging Point Facilities) |
31
Jul 2012 |
Condition 3.3 |
Baseline
Monitoring Report (Works Contracts 1103, 1106 and 1111 – Hin Keng to Diamond Hill Tunnels, Diamond Hill Station, and
Hung Hom North Approach Tunnels) |
19
Oct 2012 |
Condition 3.4 |
Monthly
EM&A Reports No. 1
- 47 Monthly
EM&A Report No. 48 |
Reported in previous Monthly EM&A Reports 14
Sep 2016 |
Table
3.2 Summary of Status of Required
Submissions for EP-437/2012
EP Condition |
Submission |
Submission date |
Condition 1.11 |
Notification of
Commencement Date of Construction of the Project |
30 Nov 2012 |
Condition 2.3 |
Notification of
Information of Community Liaison Groups |
30 Nov 2012 |
Condition 2.5 |
Management
Organisation of Main Construction Companies |
19 Dec 2012 (1st
submission) 30 Apr 2013 (2nd
submission) |
Condition 2.6 |
Construction
Programme and EP Submission Schedule |
19 Dec 2012 |
Condition 2.7 |
Construction
Noise Mitigation Measures Plan (CNMMP) |
30 Nov 2012 (1st
submission) 8 Feb 2013
(Approved ) 26 Apr 2013 (2nd
submission) 11 Jun 2013 (3rd
submission) 27 Aug 2013
(Approved) 20 Jan 2014 (4th
submission) 28 Apr 2016 (Approved) |
Condition 2.8 |
Continuous Noise
Monitoring Plan (CNMP) |
30 Nov 2012 (1st
submission) 11 Jan 2013 (2nd
submission) 8 Feb 2013
(Approved) 20 Jan 2014 (3rd
submission) |
Condition 2.9 |
Construction and
Demolition Materials Management Plan (C&DMMP) |
6 Jul 2012 (1st
submission) 12 Sep 2012 (2nd
submission) 15 Oct 2012
(Approved) |
Condition 2.10 |
Sediment
Management Plan |
6 Jul 2012 (1st
submission) 12 Sep 2012 (2nd
submission) 5 Oct 2012 (3rd
submission) 15 Oct 2012
(Approved) |
Condition 2.11 |
Visual,
Landscape, Tree Planting & Tree Protection Plan (VLTTP) |
14 Nov 2012 (1st
submission) 8 Feb 2013 (2nd
submission) 4 Feb 2015 (3rd
submission) 26 Jun 2015 (4th submission) |
Condition 3.3 |
Baseline
Monitoring Report (Works Contracts 1103, 1106 and 1111 – Hin Keng to Diamond Hill Tunnels, Diamond Hill Station, and
Hung Hom North Approach Tunnels) |
19 Oct 2012 |
Condition 3.4 |
Monthly EM&A
Reports No. 5 - 47 Monthly EM&A
Report No. 48 |
Reported in previous Monthly EM&A Reports 14 Sep 2016 |