Table of Contents
2.......... Environmental
Monitoring and Audit
3.......... implementation
status on the environmental protection requirements
List of Tables
Table 1.1 Summary of Awarded Works Contracts
Table 2.1 Summary of Major Construction Activities in
the Reporting Period
Table 2.2 Summary of 24-Hour TSP Monitoring Results in
the Reporting Period
Table 2.3 Summary of Construction Noise Monitoring
Results in the Reporting Period
Table 2.4 Summary of
Continuous Noise Monitoring Results in the Reporting Period
Table 3.1 Summary of Status of Required Submissions
for EP-438/2012/H
Table 3.2 Summary of Status of Required Submissions
for EP-437/2012
List of Appendices
Appendix A 35th
Monthly EM&A Report for Works Contract 1108A – Kai Tak Barging Point
Facilities
Appendix C 32nd
Monthly EM&A Report for Works Contract 1101 – Ma On
Shan Line Modification Works
Appendix D 31st Monthly
EM&A Report for Works Contract 1111 – Hung Hom North Approach Tunnels
Appendix E 30th Monthly EM&A Report for Works Contract
1103 – Hin Keng to Diamond Hill
Tunnels
Appendix F 29th Monthly EM&A Report for Works Contract
1106 – Diamond Hill Station
Appendix G 27th Monthly EM&A Report for Works Contract
1107 – Diamond Hill to Kai Tak Tunnels
Appendix H 26th Monthly EM&A Report for Works Contract
1112 – Hung Hom Station and Stabling Sidings
Appendix I 26th Monthly EM&A Report for Works Contract
1108 – Kai Tak Station and Associated Tunnels
Table 1.1 Summary of Awarded Works Contracts
Works Contract |
Description |
Construction
Start Date |
Contractor |
Environmental
Team |
1101 |
Ma On Shan Line Modification Works(1) |
December 2012 |
Sun Fook Kong Joint Venture (SFKJV) |
ANewR Consulting Ltd. (ANewR) |
1102 |
Hin Keng Station and Approach Structures |
October 2013 |
Penta-Ocean Construction Co. Ltd. |
Cinotech Consultants Ltd. (Cinotech) |
1103 |
Hin Keng to Diamond Hill Tunnels |
February 2013 |
Vinci Construction Grands Projets |
Ove Arup & Partners Hong Kong Ltd. |
1106 |
Diamond Hill Station |
March 2013 |
Sembawang – Leader Joint Venture |
Cinotech Consultants Ltd. (Cinotech) |
1107 |
Diamond Hill to Kai Tak Tunnels |
May 2013 |
Chun Wo - SELI Joint Venture |
Cinotech Consultants Ltd. (Cinotech) |
1108 |
Kai Tak Station and Associated Tunnels |
June 2013 |
Kaden -Chun Wo Joint Venture |
Environmental Pioneers & Solutions Ltd. |
1108A |
Kai Tak Barging Point Facilities |
September 2012 |
Concentric – Hong Kong River Joint Venture (CCL-HKR JV) |
Cinotech Consultants Ltd. (Cinotech) |
1109 |
Stations and Tunnels of Kowloon City Section |
September 2012 |
Samsung-Hsin Chong JV (SSHCJV) |
ERM-Hong Kong Limited (ERM) |
1111 |
Hung Hom North
Approach Tunnels |
January 2013 |
Gammon-Kaden SCL1111 JV |
AECOM Asia Co. Ltd. |
1112 |
Hung Hom Station and Stabling Sidings |
June 2013 |
Leighton Contractors (Asia) Limited |
SMEC Asia Ltd., HK |
Note:
(1) Only the EM&A
works for works areas at Tai Wai Mei Tin Road and the offsite temporary storage
areas are included in this Report.
Works Contract |
Contract Title |
Works Covered in Environmental Permit No. |
1101 |
Ma On Shan
Modification Works |
|
1102 |
Hin Keng Station
and Approach Structures |
|
1103 |
Hin Keng to Diamond Hill Tunnels |
|
1106 |
Diamond Hill
Station |
|
1107 |
Diamond Hill to
Kai Tak Tunnels |
|
1108 |
Kai Tak Station
and Associated Tunnels |
|
1108A |
Kai Tak Barging
Point Facilities |
|
1109 |
Stations and Tunnels of Kowloon City
Section |
|
1111 |
Hung Hom North Approach Tunnels |
|
1112 |
Hung Hom Station and Stabling Sidings |
Table 2.1 Summary
of Major Construction Activities in the Reporting Period
Works Contract |
Site |
Construction Activities |
1101(1) |
Tai Wai Mei Tin
Road |
· All the construction activities were completed in
September 2013. |
1102 |
Hin Keng Station and Approach Structures |
·
Slope improvement
works; ·
Pumping test; ·
ELS structure
installation at at-grade box; ·
Pier and pile
cap construction of viaduct; ·
Steel structure
and ABWF works at Hin Keng Station; and · Modification of retaining wall and installation
of noise barrier. |
1103 |
Diamond Hill
Area |
· Tunnel
Boring Machine (TBM) tunneling and machinery site
assembly. |
Hin Keng Area |
·
Pipe piling,
grouting and tunnel blasting. |
|
Fung Tak Area |
·
Shaft excavation
and ELS and sheet piling for retaining wall. |
|
Ma Chai Hang
Area |
·
Shaft
Excavation and ELS. |
|
1106 |
Diamond Hill
Station Area |
·
Construction of
slabs/beams, columns and walls at SCL-DIH station area, Interchange Adit, West Unpaid Link Adit and
Entrance A1; ·
Concreting
works; and · Preparation of piling works and pre-drilling
works. |
1107 |
Tunnel section
next to Kai Tak Station |
·
Tunnel
construction at cut and cover tunnels; ·
Backfilling
works at cut and cover tunnels; ·
TBM excavation;
and · Reprovision of box culvert. |
1108 |
Kai Tak Station |
·
Open Cut
Tunnel: sump pit cast concrete, staircase corridor roof cast concrete ·
Cut and Cover Tunnel:
Defect rectification, temporary drainage
system maintenance and monitoring ·
Package 4.5: Sheetpile extraction,
excavation, base slab cast, wall and roof construction, ·
Station
structure: North vent shaft, ground slab concreting, wall concreting, lower ground
slab concreting, water proofing, ·
Launching
Shaft: Tunnel mining, excavation, rebar fixing, strut installation · Receiving Shaft: Base slab cast concrete, base
slab formwork erection, concrete props at cast concrete, tunnel mining |
1108A |
Kai Tak Barging
Point Facilities |
·
Daily operation
and maintenance of the Barging Point Facilities to receive excavated spoil
delivered by trucks from Designated and Interfacing Contracts. ·
Temporary
stockpiling of received spoil in the Barging Point Facilities. · Marine transportation of received spoil to
receptor sites for beneficial reuse. |
1109 |
Ma Tau Wai (MTW)
Works Area |
·
TKW/MTW Road Garden – Operation of bentonite plant
and EEP construction; and · Along Ma Tau Wai Road – Predrilling for D wall, D wall panel
construction, trial pits for location
of utilities and station excavation. |
To Kwa Wan (TKW)
Works Area |
·
Olympic Garden
– Underpinning works, installation of pipe pile and TTMS preparation; ·
TKW Station – Pump installation, open cut excavation, and
tunnelling works; ·
Tam Kung Road – Shaft construction; and · Nam Kok Road – Installation of pipe pile. |
|
1111 |
Mong Kok Freight
Terminal(1) |
· All the construction activities were completed in
May 2015. |
Hung Hom Area |
·
Excavation
work, site clearance, slope work, cable detection, excavation lateral
support, form work erection, reinforcement fixing, ·
Construction of
drainage and man hole, foul water diversion ·
Trial pit,
trial trench, pre-drilling, pilling works, pre-grouting, grouting,
post-grouting, pre-spilt, backfilling, abutment works, ·
Erection of
hoarding, scaffolding platform, erection of utility temporary supports,
erection of temporary link walkway, temporary working platform, abandoned
utilities, utilities protection, ·
Tie back
installation, lifting works, construction of noise enclosure footing, decking
installation, installation of temporary support for OB2, modification work
for OB2, ·
Dismantling of
scaffolding, pumping test, ·
Architectural
Builders Works and Finishes (ABWF) & Electrical and Mechanical (E&M)
works. |
|
1112 |
Hong Hom (HUH and HHS) Works Area |
·
Piling for HUH,
NAT, HHS and SAT ·
Diaphragm wall
construction at HUH ·
Initial
excavation at HUH and HHS ·
Barging point
operation at Hung Hom Freight Pier ·
Operation of
Material Receiving Hopper at Hung Hom Freight Pier ·
Marine
transportation and disposal of spoil to designated dumping ground(s) · Underpinning works at HUH |
Note:
(1)
Construction works were completed.
Table 2.2 Summary of 24-Hour TSP
Monitoring Results in the Reporting Period
Monitoring Station ID |
Location |
TSP Concentration (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
Exceedance due to the Project
Construction (Yes/No) |
|
Works
Contract 1101 (5) |
|
|
|
|
||
Works
Contract 1102 and 1103 |
|
|
|
|
||
DMS-1 |
C.U.H.K.A.A.
Thomas Cheung School |
26.5 – 44.6 |
148.7 |
260 |
No |
|
Works
Contract 1103 |
|
|
|
|
||
DMS-2 |
Price
Memorial Catholic Primary School |
7.5 – 27.4 |
167.4 |
260 |
No |
|
Works
Contracts 1103 and 1106 |
|
|
|
|
||
DMS-3 |
Hong
Kong S.K.H Nursing Home (1) |
6.8 – 19.8 |
159.1 |
260 |
No |
|
Works
Contract 1106 and 1107 |
|
|
|
|
||
DMS-4 |
Block
1, Rhythm Garden |
12.8 – 62.1 |
160.4 |
260 |
No |
|
Works
Contract 1108 (5) |
|
|
|
|
||
Works
Contract 1108A (5) |
|
|
|
|
||
Works
Contract 1109 |
|
|
|
|
||
DMS-6 |
Katherine Building (2) |
58 – 67 |
156.8 |
260 |
No |
|
DMS-7 |
Parc 22 (3) |
(10) |
166.7 |
260 |
(10) |
|
DMS-8 |
SKH
Good Shepherd Primary School |
56 – 73 |
152.2 |
260 |
No |
|
DMS-9 |
No.
12 Pau Chung Street (4)(9) |
62 – 69 |
160.9 |
260 |
No |
|
DMS-10 |
Chat
Ma Mansion |
57 – 70 |
170.4 |
260 |
No |
|
Works Contract 1111 |
|
|
|
|
||
AM1(6) |
No.
234 – 238 Chatham Road North (7) |
27.7 – 64.6 |
183.9 |
260 |
No |
|
Works Contract 1112 |
|
|
|
|
||
AM2 |
Site
Boundary of Finger Pier Adjacent
To Harbourfront Horizon (8) |
17.7 – 61.0 |
182 |
260 |
No |
|
Note:
(1)
Alternative monitoring location to Shek On House
(2)
Alternative monitoring location to Prosperity House
(3)
Alternative monitoring location to Skytower Tower 2
(4)
Alternative monitoring
location to Lucky Building
(5)
No TSP monitoring is required under this contract
(6)
AM1 named as HUH-1-3 in SCL(TAW-HUH)
and SCL(HHS) EIA Reports.
(7)
Alternative monitoring location to Wing Fung
Building
(8)
Alternative monitoring location to Harbourfront Horizon
(9)
24-hour averaged dust monitoring at DMS-9 No. 26
Kowloon City Road (alternative location of Lucky Building) has been suspended
since March 2014 due to denied access by the occupant of the premise. However,
No. 12 Pau Chung Street, as an alternative monitoring location, was formally
approved by EPD on 19 May 2014. Impact dust monitoring was resumed on 12 June
2014.
(10) 24-hour averaged
dust monitoring at DMS-7 Parc-22 has been temporary suspended since July 2015
due to request from the management office.
Table 2.3 Summary
of Construction Noise Monitoring Results in the Reporting Period
Monitoring Station ID |
Location |
Noise Level (LAeq,30mins, dB(A)) |
Limit Level (dB(A)) |
Exceedance due to the Project Construction (Yes/No) |
|||
Measured |
Baseline |
Corrected (7) |
|||||
Works Contract 1101 (6) |
|
|
|
|
|
||
Works Contract 1102 and
1103 |
|
|
|
|
|
||
NMS-CA-1 |
C.U.H.K.A.A.
Thomas Cheung School |
57.4 – 59.0 |
57.0 |
= Baseline – 54.7 |
70 (65 during examination
period) |
No |
|
Works Contract 1103 |
|
|
|
|
|
||
NMS-CA-2 |
Price Memorial
Catholic Primary School |
65.7 – 66.9 |
66.0 |
< Baseline – 59.6 |
70 (65 during
examination period) |
No |
|
Works Contracts 1103 and
1106 |
|
|
|
|
|
||
NMS-CA-3 |
Hong Kong S.K.H
Nursing Home (1) |
70.4 – 71.4 |
73.0 |
< Baseline |
70 |
No |
|
Works Contract 1106 and
1107 |
|
|
|
|
|
||
NMS-CA-4 |
Block 1, Rhythm
Garden (north-eastern façade) |
69.4 – 72.6 |
71.0 |
< Baseline – 67.5 |
75 |
No |
|
NMS-CA-5 |
Block 1, Rhythm
Garden (northern façade)(2) |
65.3 – 72.2 |
74.0 |
< Baseline |
70 (65 during
examination period) |
No |
|
Works Contract 1108 (6) |
|
|
|
|
|
||
Works Contract 1108A (6) |
|
|
|
|
|
||
Works Contract 1109 |
|
|
|
|
|
||
NMS-CA-6 |
No. 16-23 Nam Kok Road (3) |
63.8 – 64.0 |
76.1 |
< Baseline |
75 |
No |
|
NMS-CA-7 |
Skytower Tower 2 |
65.6 – 66.1 |
70.0 |
< Baseline |
75 |
No |
|
NMS-CA-8 |
SKH Good
Shepherd Primary School |
73.3 – 75.0 |
75.4 |
< Baseline |
70 (65 during
examination period) (79 during the
period of conducting the continuous noise monitoring) (8) |
No |
|
NMS-CA-9 |
Kong Yiu
Mansion (4) |
72.7 – 74.1 |
69.2 |
70.1 – 72.4 |
75 |
No |
|
NMS-CA-10 |
Chat Ma Mansion |
76.2 – 77.0 |
76.6 |
< Baseline –
66.4 |
75 |
No |
|
Works Contract 1111 |
|
|
|
|
|
||
NM1 |
Carmel
Secondary School (South Block) |
63.4 – 68.1 |
68.0 |
< Baseline – 51.7 |
70 (65 during
examination period) (68 during the period of conducting the continuous noise monitoring) (9) |
No |
|
NM2 |
No. 234 – 238
Chatham Road North (5) |
69.2 – 73.3 |
79.0 |
< Baseline |
75 (77) (10) |
No |
|
Works Contract 1112 (6) |
|
|
|
|
|
||
Note:
(1)
Alternative monitoring location to Shek On House.
(2)
Alternative monitoring location to Canossa Primary
School (San Po Kong).
(3)
Alternative monitoring location to Prosperity
House.
(4)
Alternative monitoring location to Lucky Building.
(5)
Alternative monitoring location to Wing Fung
Building.
(6)
No construction noise monitoring is required under
this contract.
(7)
The measured noise levels are corrected against the
corresponding baseline noise levels.
(8) The Limit Level
of 79 dB(A) was updated on 22 Aug 2013 as per the latest Construction Noise
Mitigation Measures Plan (CNMMP) and Continuous Noise Monitoring Plan (CNMP)
which were approved by EPD.
(9) The Limit of 68 dB(A) was updated on 20 Jan
2014 as per the latest CNMMP and CNMP which were approved by EPD.
(10) Daytime noise Limit Level of 77 dB(A) applies
during the continuous noise monitoring period.
Table 2.4 Summary of Continuous Noise Monitoring Results in the Reporting Period
NSR ID |
NSR
Description |
Continuous Noise Monitoring Location |
Noise Level (LAeq,30mins, dB(A)) |
Action/Limit
Level (3) dB(A) |
Exceedance due
to the Project Construction (Yes/No) |
||
Measured |
Baseline |
Corrected (2) |
|||||
Works Contract
1101 (1) |
|
|
|
|
|
|
|
Works Contract
1102 (1) |
|
|
|
|
|
|
|
Works Contract 1103 |
|
|
|
|
|
|
|
TAW-6-7 |
C.U.H.K.A.A. Thomas Cheung School |
TAW-6-7 (C.U.H.K.A.A. Thomas
Cheung School) |
(4) |
(4) |
(4) |
66 (7) |
(4) |
Works Contract 1103 & 1106 |
|
|
|
|
|
|
|
DIH-9-1(1) |
Shek On Building |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
DIH-13-1(1) |
Canossa Primary School |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
Works Contract 1106 & 1107 |
|
|
|
|
|
|
|
DIH-14-1(1) |
Rhythm Garden Block 2 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
DIH-14-5(1) |
Rhythm Garden Block 1 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
Works Contract 1103, 1106 & 1107 |
|
|
|
|
|
|
|
DIH-14-4(1) |
Canossa Primary School (San Po Kong) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
Works Contract 1108 (1) |
|
|
|
|
|
|
|
Works Contract 1108A (1) |
|
|
|
|
|
|
|
Works Contract 1109 |
|
|
|
|
|
|
|
TKW-1-1(1) |
Parc 22 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
TKW-2-2(1) |
Skytower Tower 2 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
TKW-3-2 |
Prosperity House |
TKW-3-2(B) (Hing Fu Building) |
(4) |
(4) |
(4) |
80 |
(4) |
MTW-12-3 |
Lucky Mansion |
MTW-12-3(A) (SKH Good Shepherd
Primary School) |
(4) |
(4) |
(4) |
80 |
(4) |
MTW-12-4 |
352-354 Ma Tau Wai Rd (East Façade) |
MTW-12-4(A) (Kong Yiu Mansion) |
(4) |
(4) |
(4) |
80 |
(4) |
MTW-12-4-1 |
352-354 Ma Tau Wai Rd (North Facade) |
MTW-12-4-1(A) (59 Maidstone Road) |
(4) |
(4) |
(4) |
82 |
(4) |
MTW-12-10 |
Lucky Building (South Facade) |
MTW-12-10 (Lucky Building (South Façade)) |
(4) |
(4) |
(4) |
84 |
(4) |
MTW-12-10-1 |
Lucky Building (East Facade) |
MTW-12-10-1 (Lucky Building (East Façade)) |
(4) |
(4) |
(4) |
80 |
(4) |
MTW-12-11 |
Jing Ming Building |
MTW-12-11(A) (SKH Good Shepherd
Primary School) |
(4) |
(4) |
(4) |
81 |
(4) |
MTW-16-1 |
SKH Good Shepherd Primary School |
MTW-16-1 (SKH Good Shepherd
Primary School) |
70.2 – 90.7 |
75.4 |
< Baseline – 90.5 |
79 |
Yes |
MTW-18-2 (8) |
No. 2 Kowloon City Road |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
HOM-2-1--A (1) |
Faerie Court (East Façade) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
Works Contract 1111 |
|
|
|
|
|
|
|
OM4a |
Carmel Secondary School (South Block) |
NM1 (Carmel Secondary
School (South Block)) |
(4) |
(4) |
(4) |
68 (7) |
(4) |
HH2(6) |
Wing Fung Building |
NM2 (No. 234-238 Chatham
Road North(5)) |
(4) |
(4) |
(4) |
77 |
(4) |
Works
Contract 1112 (1) |
Note:
(1)
No continuous noise monitoring is required under
this contract.
(2)
Measured noise level (above the baseline noise
level) was corrected against the corresponding baseline level.
(3)
Reference to the predicted maximum noise level as
contained in the corresponding CNMMP.
(4)
According to the CNMMP and CNMP, continuous noise
monitoring is not required during this reporting month.
(5)
Alternative monitoring location to Wing Fung
Building.
(6)
HH2 named as HUH-1-3 in SCL (TAW-HUH) and SCL(HHS) EIA Reports.
(7)
Action/Limit level will only be applicable during
the examination period.
(8)
The building at MTW-18-2 has been demolished.
During the period of residual noise impact exceeding criteria predicted in the
corresponding CNMMP, there will be no NSR occupied at this location. It is
therefore not necessary carry out continuous noise monitoring at this location.
(9)
Investigations for some exceedances are being
conducted and detail investigation results will be provided in next reporting
month.
N/A Not applicable
Table 2.5 Log for Environmental
Complaints, Notification of Summons and Successful Prosecutions for the Reporting Month
Works
Contract |
Environmental Complaints |
Notification of Summons |
Successful Prosecutions |
1101 |
0 |
0 |
0 |
1102 |
0 |
0 |
0 |
1103 |
1 (1) |
0 |
0 |
1106 |
0 |
0 |
|
1107 |
0 |
0 |
0 |
1108 |
0 |
0 |
0 |
1108A |
0 |
0 |
0 |
1109 |
0 |
0 |
0 |
1111 |
0 |
0 |
0 |
1112 |
0 |
0 |
0 |
Note:
(1)
The complaint case under Works Contracts 1103 and
1106 referred to the same complaints as referred by the EPD.
Table 3.1 Summary of Status of Required Submissions
for EP-438/2012/H
Submission |
Submission date |
|
Condition 1.12 |
Notification of
Commencement Date of Construction of the Project |
1 Aug 2012 |
Condition 2.3 |
Notification of
Information of Community Liaison Groups |
13 Jul 2012 (1st
submission) 31 Aug 2012 (2nd
submission) 30 Nov 2012 (3rd
submission) |
Condition 2.7 |
Management Organisation of
Main Construction Companies |
27 Jul 2012 (1st
submission) 21 Aug 2012 (2nd
submission) 19 Dec 2012 (3rd
submission) 22 Jan 2013 (4th
submission) 30 Apr 2013 (5th
submission) 21 May 2013 (6th
submission) |
Condition 2.8 |
Construction Programme and
EP Submission Schedule |
27 Jul 2012 |
Condition 2.9 |
Construction Noise
Mitigation Measures Plan (CNMMP) |
1 Aug 2012 (1st
submission) 28 Sep 2012 (2nd
submission) 30 Nov 2012 (3rd
submission) 11 Jan 2013 (4th
submission) 8 Feb 2013 (Approved) 26 Apr 2013 (6th
submission) 11 Jun 2013 (7th
submission) 12 July 2013 (Approved) 26 July 2013 (8th
submission) 22 Aug 2013 (Approved) 23 Aug 2013 (9th
submission) 13 Sept 2013 (Approved) 20 Jan 2014 (10th
submission) 26
Feb 2014 (Approved) 31
Mar 2015 (Contract 1106 submission only) 13
Apr 2015 (Contract 1106 submission only) 15
Apr 2015 (Approved) |
Condition 2.10 |
Continuous Noise
Monitoring Plan (CNMP) |
1 Aug 2012 (1st
submission) 28 Sep 2012 (2nd
submission) 30 Nov 2012 (3rd
submission) 11 Jan 2013 (4th
submission) 8 Feb 2013 (Approved) 8 Feb 2013 (5th
submission) 26 Apr 2013 (6th
submission) 12 July 2013 (Approved) 26 July 2013 (8th
submission) 22 Aug 2013 (Approved) 23 Aug 2013 (9th
submission) 13 Sept 2013 (Approved) 20 Jan 2014 (10th
submission) 26
Feb 2014 (Approved) 7
Oct 2014 (11th submission) 23
Oct 2014 (Approved) |
Condition 2.11 |
Construction and
Demolition Materials Management Plan (C&DMMP) |
6 Jul 2012 (1st
submission) 12 Sep 2012 (2nd
submission) 10 Oct 2012 (Approved) |
Condition 2.12 |
Sediment Management Plan |
6 Jul 2012 (1st
submission) 12 Sep 2012 (2nd
submission) 5 Oct 2012 (3rd
submission) 10 Oct 2012 (Approved) 4 Mar 2013 (4th
submission) 9 May 2013 (5th
submission) 24 July 2013 (6th
submission) 26 July 2013 (Approved) |
Condition 2.13 |
Visual, Landscape, Tree
Planting & Tree Protection Plan |
6 Jul 2012 (1st
submission) 30 Aug 2012 (2nd
submission) 3 Oct 2012 (3rd
submission) 13 Nov 2013 (Approved for
Contracts 1101, 1106 and 1109) 14 Nov 2012 (4th
submission) 8 Feb 2013 (5th
submission) 18 Mar 2013 (6th
submission) 18 June 2013 (7th
submission) 12 July 2013 (Approved) |
Condition 2.14 |
Transplantation Proposal
for Plant Species of Conservation Importance |
22 Aug 2012 (1st
submission) 5 Oct 2012 (2nd
submission) 26 Nov 2012 (3rd
submission) 4 Dec 2012 (Approved) |
Condition 2.15 |
Conservation Plan |
31 Jan 2013 (1st
submission) 18 Mar 2013 (2nd
submission) 24 Apr 2013 (Approved) |
Condition 2.16 |
Archaeological Action
Plan(s) (AAP(s)) for Works Contract 1109 |
10 Aug 2012 (1st
submission) 3 Sep 2012 (2nd
submission) 21 Sep 2012 (Approved) 11 Oct 2013 (3rd submission) 1 Nov 2013 (Approved) |
Condition 2.16 |
Archaeological Action
Plan(s) (AAP(s)) for Works Contract 1106 |
29 Jan 2013 (1st
submission) 19 Mar 2013 (2nd
submission) 8 Apr 2013 (Approved) |
Condition 2.23 |
Supplementary
Contamination Assessment Report for
New Territories South Animal Centre |
28 Sep 2012 25 Oct 2012 (Approved) |
Condition 3.3 |
Baseline Monitoring Report
(Works Contract 1109 - Stations and Tunnels of Kowloon City Section ) |
27 Jul 2012 |
Condition 3.3 |
Baseline Monitoring Report
(Works Contract 1108A – Kai Tak Barging Point Facilities) |
31 Jul 2012 |
Condition 3.3 |
Baseline Monitoring Report
(Works Contracts 1103, 1106 and 1111 – Hin Keng to
Diamond Hill Tunnels, Diamond Hill Station, and Hung Hom
North Approach Tunnels) |
19 Oct 2012 |
Condition 3.4 |
Monthly EM&A Reports No. 1 - 33 Monthly EM&A Report
No. 34 |
Reported
in previous Monthly EM&A Reports 14 Jul 2015 |
Table 3.2 Summary of Status of
Required Submissions for EP-437/2012
EP Condition |
Submission |
Submission date |
Condition 1.11 |
Notification of Commencement Date of Construction of the Project |
30 Nov 2012 |
Condition 2.3 |
Notification of Information of Community Liaison Groups |
30 Nov 2012 |
Condition 2.5 |
Management Organisation of Main Construction Companies |
19 Dec 2012 (1st submission) 30 Apr 2013 (2nd submission) |
Condition 2.6 |
Construction Programme and EP Submission Schedule |
19 Dec 2012 |
Condition 2.7 |
Construction Noise Mitigation Measures Plan (CNMMP) |
30 Nov 2012 (1st submission) 8 Feb 2013 (Approved ) 26 Apr 2013 (2nd submission) 11 Jun 2013 (3rd submission) 27 Aug 2013 (Approved) 20 Jan 2014 (4th submission) |
Condition 2.8 |
Continuous Noise Monitoring Plan (CNMP) |
30 Nov 2012 (1st submission) 11 Jan 2013 (2nd submission) 8 Feb 2013 (Approved) 20 Jan 2014 (3rd submission) |
Condition 2.9 |
Construction and Demolition Materials Management Plan (C&DMMP) |
6 Jul 2012 (1st submission) 12 Sep 2012 (2nd submission) 15 Oct 2012 (Approved) |
Condition 2.10 |
Sediment Management Plan |
6 Jul 2012 (1st submission) 12 Sep 2012 (2nd submission) 5 Oct 2012 (3rd submission) 15 Oct 2012 (Approved) |
Condition 2.11 |
Visual, Landscape, Tree Planting & Tree Protection Plan (VLTTP) |
14 Nov 2012 (1st submission) 8 Feb 2013 (2nd submission) 4 Feb 2015 (3rd submission) 26 Jun 2015 (4th submission) |
Condition 3.3 |
Baseline Monitoring Report (Works Contracts 1103, 1106 and 1111 – Hin Keng to Diamond Hill Tunnels, Diamond Hill Station, and
Hung Hom North Approach Tunnels) |
19 Oct 2012 |
Condition 3.4 |
Monthly EM&A Reports No. 5 - 33 Monthly EM&A Report No. 34 |
Reported in previous Monthly EM&A
Reports 14 Jul 2015 |